Notification of Readiness Postponement for NRC 95001 Inspection
ML23139A084
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 05/18/2023
From: Pat Navin
Constellation Energy Generation
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
NRC-23-016
Download: ML23139A084 (1)


Text

Constellation~. Patrick D. Navin Site Vice President Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657 410-495-5200 Office 717-817-6827 Mobile www.constellation.com Pat.Navin@constellation.com May 18, 2023 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Calvert Cliffs Nuclear Power Plant, Units 1 and 2 Renewed Facility Operating License Nos. DPR-53 and DPR-69 Docket Nos. 50-317 and 50-318

Subject:

Notification of Readiness Postponement for NRC 95001 Inspection

References:

1. Letter from David C. Lew (NRC) to David P. Rhoades (Constellation Energy Generation, LLC) , Calvert Cliffs Nuclear Power Plant, Unit 1 - Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation; Inspection Report 05000317 /2022090, dated December 5, 2022 (ADAMS Accession No. ML22314A100)
2. Letter from Patrick D. Navin (Constellation Energy Generation, LLC) to NRC Document Control Desk, Notification of Readiness for NRC 95001 Inspection, dated March 30, 2023 (ADAMS Accession No.

M L23089A 104)

In the Reference 1 letter, the NRC provided a final significance determination of a White finding and notice of violation associated with the failure of the Calvert Cliffs Nuclear Power Plant (CCNPP), Unit 1, 1A Diesel Generator on February 19, 2022. In support of the associated supplemental inspection for this finding , the Reference 2 letter documents the Constellation Energy Generation, LLC (CEG) notification to the NRC of readiness for a supplemental inspection in accordance with Inspection Procedure 95001, "Supplemental Inspection Response to Action Matrix Column 2 (Regulatory Response) Inputs." In response, the NRC notified CEG of the plan to perform the supplemental inspection the week of June 5, 2023.

This letter requests a postponement in the NRC's performance of the 95001 Inspection for CCNPP, Unit 1. This request is based on time needed to complete an additional causal analysis associated with the 1A Diesel Generator.

CEG will advise the NRC in writing of our readiness to conduct the inspection upon completion of the casual analysis.

U.S. Nuclear Regulatory Commission Notification of Readiness for NRC 95001 Inspection May 18, 2023 Page 2 There are no new regulatory commitments contained in this letter. If you should have any questions, please contact Mr. Larry D. Smith, Regulatory Assurance Manager, at 41 0-495-5219.

I Patrick D. Navin Site Vice President Calvert Cliffs Nuclear Power Plant cc: USNRC Administrator, Region I USNRC Project Manager, CCNPP USNRC Senior Resident Inspector, CCNPP S. Seaman, State of Maryland

U.S. Nuclear Regulatory Commission Notification of Readiness for NRC 95001 Inspection May 18, 2023 Page 3 bee: M.J. Herr, Sr. Vice President, MidAtlantic Operations G. Kaegi, Vice President - Nuclear Security and Licensing P.O. Navin, Site Vice President P.F. Moodie, Plant Manager D.J. Baker, Director, Site Maintenance H.M. Crockett, Director, Organizational Performance and Regulatory L.D. Smith, Manager, Regulatory Assurance D.M. Reddick, Director, Licensing D.P. Helker, Sr. Manager, Licensing NRC 23-016