Letter Sequence Approval |
|---|
|
Results
Other: ML21266A429, ML21266A430, ML21267A121, ML21267A122, ML22255A235, ML22255A237, ML22363A016, ML23034A223, ML23034A226, ML23184A005, ML23184A006, ML23184A017, ML23184A018
|
MONTHYEARPMNS20210713, Meeting with X-energy LLC: TRISO-X Pebble Fuel Qualification Methodology2021-05-25025 May 2021 Meeting with X-energy LLC: TRISO-X Pebble Fuel Qualification Methodology Project stage: Request ML21246A2892021-09-0202 September 2021 X-Energy, LLC, Submittal of Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology, Revision 2 Project stage: Request ML21266A4292021-09-28028 September 2021 Email to X Energy, LLC - Withholding Determination - Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: Other ML21266A4302021-09-28028 September 2021 NRC 897, Withholding Determination - X Energy, LLC - Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: Other ML21267A1212021-10-13013 October 2021 NRC 898, Completeness Determination, X Energy, LLC - Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: Other ML21267A1222021-10-13013 October 2021 Email to X Energy, LLC - Completeness Determination - Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: Other ML21334A2302021-12-0202 December 2021 Email to X Energy, LLC - Transmittal of Requests for Additional Information - Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: RAI PMNS20220087, Meeting with X Energy, LLC Regarding Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology2022-02-0101 February 2022 Meeting with X Energy, LLC Regarding Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: Request ML21354A2892022-02-11011 February 2022 Summary of the June 4, 2021, Closed Meeting with X-Energy, LLC TRISO-X Pebble Fuel Qualification Methodology Project stage: Meeting ML22059A7702022-03-28028 March 2022 X Energy, LLC (X-energy), Submission of Responses to Requests for Additional Information for Topical Report, TRISO-X Pebble Fuel Qualification Methodology Project stage: Response to RAI ML22108A1072022-04-18018 April 2022 NRC 897 Withholding Determination Form for Submission of X Energy, LLC Responses to Requests for Additional Information for Topical Report, TRISO-X Pebble Fuel Qualification Methodology Project stage: RAI ML22108A1362022-04-18018 April 2022 Email to X-Energy, LLC - Withholding Determination - RAI Responses for Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: RAI PMNS20220423, Closed Meeting with X Energy, LLC Regarding RAI Responses for Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology2022-04-18018 April 2022 Closed Meeting with X Energy, LLC Regarding RAI Responses for Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: Request ML22166A4182022-07-15015 July 2022 Summary of the February 10, 2022, Closed Meeting with X Energy, LLC Regarding XE-100 Topical Report TRISO-X Pebble Fuel Qualification Methodology Project stage: Meeting ML22166A4242022-07-15015 July 2022 Summary of the May 20, 2022, Closed Meeting with X Energy, LLC Regarding XE-100 Topical Report TRISO-X Pebble Fuel Qualification Methodology Project stage: Meeting ML22216A1792022-07-29029 July 2022 Submission of X Energy, LLC (X-energy) TRISO-X Pebble Fuel Qualification Methodology Project stage: Request ML22265A2182022-09-21021 September 2022 Withdrawal of X Energy, LLC (X-energy) Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology, Revisions 1 and 2 Project stage: Request ML22255A2352022-09-29029 September 2022 NRC Form 897, Withholding Determination, X Energy, LLC - Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology, Revision 3 Project stage: Other ML22255A2372022-09-29029 September 2022 Email to X Energy, LLC - Withholding Determination - Xe-100 Topical Report TRISO-X Pebble Fuel Qualification Methodology, Revision 3 Project stage: Other ML22363A0162022-09-29029 September 2022 X Energy, LLC - Change in Review Schedule for Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology, Revision 3 Project stage: Other ML22194A9482022-11-0707 November 2022 Transmittal Email - X Energy, LLC - Draft Safety Evaluation of Xe-100 Topical Report TRISO-X Pebble Fuel Qualification Methodology, Revision No. 3 Project stage: Draft Approval ML22362A0642023-02-0202 February 2023 X-Energy, LLC – Acknowledgement of Withdrawal of Revisions 1 and 2 of XE-100 Topical Report: TISO-X Pebble Fuel Qualification Methodology Project stage: Withdrawal ML23034A2262023-02-0303 February 2023 Email to X-energy - Withholding Determination for Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology, Revision 1 Project stage: Other ML23034A2232023-02-0303 February 2023 Form 897 Proprietary Determination for Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology, Revision 1 Project stage: Other ML22327A1982023-03-0909 March 2023 Cover Letter – X Energy, LLC - Safety Evaluation of Xe-100 Topical Report, TRISO-X Pebble Fuel Qualification Methodology, Revision No. 3 Project stage: Approval ML22327A2012023-03-0909 March 2023 X Energy LLC - Safety Evaluation of XE-100 Topical Report TRISO-X Pebble Fuel Qualification Methodology Revision No. 3 (EPID No. L-2021-TOP-0011) - Redacted Project stage: Approval ML23079A1082023-03-20020 March 2023 NRR E-mail Capture - X Energy, LLC - Safety Evaluation of Xe-100 Topical Report, TRISO-X Pebble Fuel Qualification Methodology, Revision No. 3 Project stage: Approval ML23184A0052023-07-0303 July 2023 Email to Travis Chapman of X-Energy Regarding Proprietary Review for Topical Report, TRISO-X Pebble Fuel Qualification Methodology, Accepted Version Project stage: Other ML23184A0062023-07-0303 July 2023 NRC 897 for TRISO-X -A Version Project stage: Other ML23184A0182024-02-0606 February 2024 X Energy LLC - NRC Form 896 -A Topical Report Verification for TRISO-X Pebble Fuel Qualification Methodology Topical Report Project stage: Other ML23184A0172024-02-0707 February 2024 X Energy, LLC - Email Correspondence Regarding -A Topical Report Verification for TRISO-X Fuel Qualification Methodology Topical Report Project stage: Other 2022-07-15
[Table View] |
Text
From:
Stephanie Devlin-Gill (She/Her)
Sent:
Monday, March 20, 2023 10:54 AM To:
Travis Chapman Cc:
Michael Orenak; Katie Wagner; Ingrid Nordby; Maggie Staiger
Subject:
X Energy, LLC - Safety Evaluation of Xe-100 Topical Report, TRISO-X Pebble Fuel Qualification Methodology, Revision No. 3 (EPID NO. L-2021-TOP-0011)
Dear Mr. Chapman:
Consistent with the following documents, the NRC staff placed a copy of the final safety evaluation that contains proprietary information of the Xe-100 Topical Report, TRISO-X Pebble Fuel Qualification Methodology, Revision No. 3 (EPID L-2021-TOP-0011) in the Box.com folder to which you have access. This email will also be made publicly available.
Title Accession Number X Energy LLC - Safety Evaluation of Xe-100 Topical Report TRISO-X Pebble Fuel Qualification Methodology Revision No. 3 (EPID NO. L-2021-TOP-0011) - REDACTED ML22327A201 Cover Letter - X Energy, LLC - Safety Evaluation of Xe-100 Topical Report, TRISO-X Pebble Fuel Qualification Methodology, Revision No. 3 (EPID NO. L-2021-TOP-0011) ML22327A198 If you have any questions or comments concerning this matter, please contact myself or Michael Orenak at (301) 415-3229 or via e-mail at or Michael.Orenak@nrc.gov.
Sincerely, stephanie Stephanie Devlin-Gill (she/her)
Senior Project Manager U.S. NRC, NRR, DANU, UAL1
- w. (301) 415-5301
Hearing Identifier:
NRR_DRMA Email Number:
2005 Mail Envelope Properties (DM6PR09MB4806B347D051D13E976DA92BBD809)
Subject:
X Energy, LLC - Safety Evaluation of Xe-100 Topical Report, TRISO-X Pebble Fuel Qualification Methodology, Revision No. 3 (EPID NO. L-2021-TOP-0011)
Sent Date:
3/20/2023 10:53:39 AM Received Date:
3/20/2023 10:53:00 AM From:
Stephanie Devlin-Gill (She/Her)
Created By:
Stephanie.Devlin-Gill@nrc.gov Recipients:
"Michael Orenak" <Michael.Orenak@nrc.gov>
Tracking Status: None "Katie Wagner" <Katie.Wagner@nrc.gov>
Tracking Status: None "Ingrid Nordby" <inordby@x-energy.com>
Tracking Status: None "Maggie Staiger" <mstaiger@x-energy.com>
Tracking Status: None "Travis Chapman" <TChapman@x-energy.com>
Tracking Status: None Post Office:
DM6PR09MB4806.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 1278 3/20/2023 10:53:00 AM Options Priority:
Normal Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date: