MONTHYEARPMNS20210713, Meeting with X-energy LLC: TRISO-X Pebble Fuel Qualification Methodology2021-05-25025 May 2021 Meeting with X-energy LLC: TRISO-X Pebble Fuel Qualification Methodology Project stage: Request ML21246A2892021-09-0202 September 2021 X-Energy, LLC, Submittal of Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology, Revision 2 Project stage: Request ML21266A4292021-09-28028 September 2021 Email to X Energy, LLC - Withholding Determination - Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: Other ML21266A4302021-09-28028 September 2021 NRC 897, Withholding Determination - X Energy, LLC - Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: Other ML21267A1212021-10-13013 October 2021 NRC 898, Completeness Determination, X Energy, LLC - Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: Other ML21267A1222021-10-13013 October 2021 Email to X Energy, LLC - Completeness Determination - Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: Other ML21334A2302021-12-0202 December 2021 Email to X Energy, LLC - Transmittal of Requests for Additional Information - Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: RAI PMNS20220087, Meeting with X Energy, LLC Regarding Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology2022-02-0101 February 2022 Meeting with X Energy, LLC Regarding Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: Request ML21354A2892022-02-11011 February 2022 Summary of the June 4, 2021, Closed Meeting with X-Energy, LLC TRISO-X Pebble Fuel Qualification Methodology Project stage: Meeting ML22059A7702022-03-28028 March 2022 X Energy, LLC (X-energy), Submission of Responses to Requests for Additional Information for Topical Report, TRISO-X Pebble Fuel Qualification Methodology Project stage: Response to RAI ML22108A1072022-04-18018 April 2022 NRC 897 Withholding Determination Form for Submission of X Energy, LLC Responses to Requests for Additional Information for Topical Report, TRISO-X Pebble Fuel Qualification Methodology Project stage: RAI ML22108A1362022-04-18018 April 2022 Email to X-Energy, LLC - Withholding Determination - RAI Responses for Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: RAI PMNS20220423, Closed Meeting with X Energy, LLC Regarding RAI Responses for Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology2022-04-18018 April 2022 Closed Meeting with X Energy, LLC Regarding RAI Responses for Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Project stage: Request ML22166A4182022-07-15015 July 2022 Summary of the February 10, 2022, Closed Meeting with X Energy, LLC Regarding XE-100 Topical Report TRISO-X Pebble Fuel Qualification Methodology Project stage: Meeting ML22166A4242022-07-15015 July 2022 Summary of the May 20, 2022, Closed Meeting with X Energy, LLC Regarding XE-100 Topical Report TRISO-X Pebble Fuel Qualification Methodology Project stage: Meeting ML22216A1792022-07-29029 July 2022 Submission of X Energy, LLC (X-energy) TRISO-X Pebble Fuel Qualification Methodology Project stage: Request ML22265A2182022-09-21021 September 2022 Withdrawal of X Energy, LLC (X-energy) Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology, Revisions 1 and 2 Project stage: Request ML22255A2352022-09-29029 September 2022 NRC Form 897, Withholding Determination, X Energy, LLC - Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology, Revision 3 Project stage: Other ML22255A2372022-09-29029 September 2022 Email to X Energy, LLC - Withholding Determination - Xe-100 Topical Report TRISO-X Pebble Fuel Qualification Methodology, Revision 3 Project stage: Other ML22363A0162022-09-29029 September 2022 X Energy, LLC - Change in Review Schedule for Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology, Revision 3 Project stage: Other ML22194A9482022-11-0707 November 2022 Transmittal Email - X Energy, LLC - Draft Safety Evaluation of Xe-100 Topical Report TRISO-X Pebble Fuel Qualification Methodology, Revision No. 3 Project stage: Draft Approval ML22362A0642023-02-0202 February 2023 X-Energy, LLC – Acknowledgement of Withdrawal of Revisions 1 and 2 of XE-100 Topical Report: TISO-X Pebble Fuel Qualification Methodology Project stage: Withdrawal ML23034A2262023-02-0303 February 2023 Email to X-energy - Withholding Determination for Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology, Revision 1 Project stage: Other ML23034A2232023-02-0303 February 2023 Form 897 Proprietary Determination for Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology, Revision 1 Project stage: Other ML22327A1982023-03-0909 March 2023 Cover Letter – X Energy, LLC - Safety Evaluation of Xe-100 Topical Report, TRISO-X Pebble Fuel Qualification Methodology, Revision No. 3 Project stage: Approval ML22327A2012023-03-0909 March 2023 X Energy LLC - Safety Evaluation of XE-100 Topical Report TRISO-X Pebble Fuel Qualification Methodology Revision No. 3 (EPID No. L-2021-TOP-0011) - Redacted Project stage: Approval ML23079A1082023-03-20020 March 2023 NRR E-mail Capture - X Energy, LLC - Safety Evaluation of Xe-100 Topical Report, TRISO-X Pebble Fuel Qualification Methodology, Revision No. 3 Project stage: Approval ML23184A0052023-07-0303 July 2023 Email to Travis Chapman of X-Energy Regarding Proprietary Review for Topical Report, TRISO-X Pebble Fuel Qualification Methodology, Accepted Version Project stage: Other ML23184A0062023-07-0303 July 2023 NRC 897 for TRISO-X -A Version Project stage: Other ML23184A0182024-02-0606 February 2024 X Energy LLC - NRC Form 896 -A Topical Report Verification for TRISO-X Pebble Fuel Qualification Methodology Topical Report Project stage: Other ML23184A0172024-02-0707 February 2024 X Energy, LLC - Email Correspondence Regarding -A Topical Report Verification for TRISO-X Fuel Qualification Methodology Topical Report Project stage: Other 2022-07-15
[Table View] |
Text
MEMORANDUM TO:
William Kennedy, Acting Chief Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation FROM:
Lucieann Vechioli Feliciano, Project Manager Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF THE FEBRUARY 10, 2022, CLOSED MEETING WITH X ENERGY, LLC REGARDING XE-100 TOPICAL REPORT: TRISO-X PEBBLE FUEL QUALIFICATION METHODOLOGY (EPID NO.: L-2021-TOP-0011)
On February 10, 2022, the U.S. Nuclear Regulatory Commission (NRC) staff held a closed videoconference meeting with X Energy, LLC (X-energy) regarding clarification of the Requests for Additional Information sent by the NRC staff on December 2, 2021 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML21334A230 and ML21334A233 (nonpublic)) regarding XE00-R-R1ZZ-RDZZ-L-000633, Revision 2 of Xe-100 Topical Report:
TRISO-X Pebble Fuel Qualification Methodology (ML21246A289). Participants included personnel from X-energy.
The public meeting was noticed on February 1, 2022 (ML22032A068). The List of Attendees is provided as an enclosure.
The NRC staff began the meeting with an introduction and pertaining logistical information.
During the meeting, X-energy representatives asked the NRC staff questions regarding individual RAI questions. The questions were followed by an open discussion between the participants to discuss certain aspects of the questions that required clarification. Finally, the X-energy representatives and the NRC staff discussed the next steps in the review of the topical report.
Project No. 99902071
Enclosure:
List of Attendees CONTACT: Lucieann Vechioli Feliciano, NRR/DANU 301-415-0673 July 15, 2022 Signed by Vechioli, Lu on 07/15/22
SUBJECT:
SUMMARY
OF THE FEBRUARY 10, 2022, CLOSED MEETING WITH X ENERGY, LLC REGARDING XE-100 TOPICAL REPORT: TRISO-X PEBBLE FUEL QUALIFICATION METHODOLOGY (EPID NO.: L-2021-TOP-0011)
DATED: JULY 15, 2022 DISTRIBUTION:
PUBLIC DANU R/F RidsNrrDanu Resource RidsNrrDanuUarl Resource RidsNrrLACSmith Resource LVechioli, NRR KWagner, NRR BTravis, NRR WKennedy, NRR ADAMS Accession Number: ML22166A418 NRR-106 OFFICE NRR/DANU/UAL1:PM NRR/DANU/UAL1:PM NRR/DANU/UAL1:LA NAME KWagner LVechioli CSmith DATE 06/16/2022 06/17/2022 07/11/2022 OFFICE NRR/DANU/UAL1:BC(A)
NRR/DANU/UAL1:PM NAME WKennedy LVechioli DATE 07/14/2022 07/15/2022 OFFICIAL RECORD COPY
Enclosure List of Attendees Closed Meeting with X Energy, LLC regarding Xe-100 Topical Report: TRISO-X Pebble Fuel Qualification Methodology Thursday, February 10, 2022 11:00 a.m. - 12:00 p.m.
Name Organization Lucieann Vechioli U.S. Nuclear Regulatory Commission (NRC)
Katherine Wagner NRC Boyce Travis NRC Travis Chapman X Energy, LLC (X-energy)
Eben Mulder X-energy Pete Pappano X-energy Paul Loza X-energy Raymond Wang X-energy Kyle Metzroth X-energy Milan Hanus X-energy Sonat Sen X-energy Dirk Olivier X-energy Ingrid Nordby X-energy