MONTHYEARML23046A2642023-02-17017 February 2023 NRC Form 898 Teusa PDC Topical Report Completeness Determination Project stage: Other ML23046A2692023-02-17017 February 2023 Email to Teusa - Acceptance Review Determination for PDC Topical Report Project stage: Acceptance Review ML24053A1712023-12-29029 December 2023 Terrestrial Energy USA, Inc., Principal Design Criteria for Imsr Structures, Systems and Components Topical Report Revision B (Document TR231229) Project stage: Request ML24095A3072024-04-0808 April 2024 Terrestrial Energy USA - Non-Prop - Audit Plan for the Principal Design Criteria for Imsr Structures, Systems, and Components Topical Report Project stage: Other ML24100A1142024-04-11011 April 2024 Email Withholding Determination PDC Teusa Project stage: Other ML24100A1122024-04-11011 April 2024 NRC Form 897 Request for Withholding Proprietary Information PDC for Imsr Structures, Systems and Components - Rev. B Topical Report Submitted Dec 29 2023 Project stage: Other PMNS20241042, Notice of Closed Meeting with Terrestrial Energy USA, Inc. (Terrestrial)2024-08-14014 August 2024 Notice of Closed Meeting with Terrestrial Energy USA, Inc. (Terrestrial) Project stage: Request ML24233A2432024-10-0707 October 2024 Teusa PDC TR Audit Report Transmittal Letter v4 Project stage: Other ML24233A2422024-10-0707 October 2024 Enclosure - Teusa Audit Report for PDC Topical Report Revb v6 Project stage: Other ML24275A1832024-10-10010 October 2024 Meeting Summary Closed-Terrestrial USA Inc-Principal Design Criteria for Imsr Structures, Systems, and Components Topical Report Rev C Review Discussion Project stage: Meeting ML24339A1212025-02-24024 February 2025 Non-Proprietary - Terrestrial PDC Topical Report Draft Safety Evaluation Project stage: Draft Approval ML25189A0482025-07-18018 July 2025 Teusa Imsr PDC TR Final SE Cover Letter Project stage: Approval ML25189A0492025-07-18018 July 2025 Teusa PDC Topical Report Final Safety Evaluation - Non Proprietary Project stage: Approval ML25328A0932025-11-25025 November 2025 Topical Report, TR240719-A, Principal Design Criterial for Imsr Structures, System and Components Project stage: Other ML25336A2692025-12-0303 December 2025 NRC 897-TEUSA PDC TR240719-A, Withholding Determination Project stage: Other ML25328A0952025-12-0303 December 2025 Email Submitting Form 896 -A Verification for Teusa Principal Design Criteria for Imsr Structures, Systems and Components (TR240719-A) Project stage: Other 2024-04-08
[Table View] |
Text
From:
Adrian Muniz To:
Francis Akstulewicz Cc:
Daniel Carleton
Subject:
Completeness Determination for TEUSA Principal Design Criteria Topical Report Date:
Friday, February 17, 2023 10:38:00 AM Attachments:
NRC Form 898 TEUSA PDC Topical Report Completeness Determination.pdf
- Frank,
Attached is the U.S. Nuclear Regulatory Commission (NRC) staff completeness determination for the Terrestrial Energy USA, Inc. (TEUSA) topical report titled Principal Design Criteria for IMSR Structures, Systems and Components, Revision A. Based on a preliminary review of the report, the NRC staff determined that it provides sufficient information for the NRC staff to begin a detailed technical review.
As discussed, the NRC staff plans to issue its draft safety evaluation by January 17, 2024.
If needed, the NRC staff will issue a request for additional information (RAI) by July 31, 2023, with a request for TEUSA to provide a response within 30 days. The NRC staff estimates that 325 staff hours will be needed to complete the technical review and issue the safety evaluation. The schedule and level of effort could change due to several factors including, the need for additional RAIs, unanticipated changes to the scope of the review, and unsolicited supplements to the topical report. The NRC staff will communicate any changes to the review schedule or estimated staff hours by email, including the reason(s) for the changes.
If you have any questions, please feel free to contact me at 301-415-4093 or by email at Adrian.Muniz@nrc.gov.
Docket No.: 99902076 EPID: L-2021-TOP-0034
Thank you,
Adrian Muniz, Senior Project Manager Advanced Reactor Licensing Branch 2 Division of Advanced Reactors and Non-Power Production and Utilization Facilities (DANU)
U.S. Nuclear Regulatory Commission