ML22342B253
| ML22342B253 | |
| Person / Time | |
|---|---|
| Site: | Grand Gulf |
| Issue date: | 10/14/2022 |
| From: | Heather Gepford Operations Branch IV |
| To: | Entergy Operations |
| References | |
| Download: ML22342B253 (1) | |
Text
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5
- 1. LOK 2. LOD 6
7 Ans Letter CFR 8
Q#
(F/H)
(1-5) stem focus cueing T/F cred dist partial job link minutia
- /
units back-ward K/A SRO-only B/M/N U/E/S A/B/C/
D 55.41x55
.43y Explanation 1
H 3
X B
E D
41.5 ON 2021 NRC EXAM.
REFERENCE PROVIDED. Please walk through question with reference to verify distractors.
Added more information to the distractor explanation. Q now S 2
H 3
B S
A 41.10 ON 2013 NRC EXAM.
- 3. Psychometric Flaws
- 4. Job Content Flaws
- 5. Other Instructions
[Refer to Section D of ES-401 and Appendix B for additional information regarding each of the following concepts.]
- 1. Enter the level of knowledge (LOK) of each question as either (F)undamental or (H)igher cognitive level.
- 2. Enter the level of difficulty (LOD) of each question using a 1 to 5 (easy to difficult) rating scale (questions in the 2 to 4 range are acceptable).
- 3. Check the appropriate box if a psychometric flaw is identified:
- a. The stem lacks sufficient focus to elicit the correct answer (e.g., unclear intent, more information is needed, or too much needless information).
- b. The stem or distractors contain cues (i.e., clues, specific determiners, phrasing, length, etc).
- c. The answer choices are a collection of unrelated true/false statements.
- d. The distractors are not credible; single implausible distractors should be repaired, more than one is unacceptable.
- e. One or more distractors is (are) partially correct (e.g., if the applicant can make unstated assumptions that are not contradicted by stem).
- 4. Check the appropriate box if a job content error is identified:
- a. The question is not linked to the job requirements (i.e., the question has a valid K/A but, as written, is not operational in content).
- b. The question requires the recall of knowledge that is too specific for the closed reference test mode (i.e., it is not required to be known from memory).
- c. The question contains data with an unrealistic level of accuracy or inconsistent units (e.g., panel meter in percent with question in gallons).
- d. The question requires reverse logic or application compared to the job requirements.
- 5. Check questions that are sampled for conformance with the approved K/A and those that are designated SRO-only (K/A and license level mismatches are unacceptable).
- 6. Enter question source: (B)ank, (M)odified, or (N)ew. Check that (M)odified questions meet criteria of ES-401 Section D.2.f.
- 7. Based on the reviewer's judgment, is the question as written (U)nsatisfactory (requiring repair or replacement), in need of (E)ditorial enhancement, or (S)atisfactory?
Place the answer letter here Place the 55.41 or 55.43 item here
- 8. At a minimum, explain any Unsat ratings (e.g., how the Appendix B psychometric attributes are not being met). a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 3
H 3
X N
U B
41.8 FIRST TEN. If the battery is designed to last for four hours, then I'm guessing it is also designed to last for two hours (potential two correct answers).
Add "a MINIMUM of" before (2).
Actually, should be "MAXIMUM" Changed MINIMUM TO MAXIMUM. Q now S 4
F 3
X B
E B
41.10 ON 2013 NRC EXAM. Add "within a MAXIMUM of" in stem Added "within a MAXIMUM of" to the stem. Q now S 5
H 3
X N
E C
41.6 Distractors C and D are very similar, which intimated to me that one of them was probably the correct answer. Discuss making this a 2X2 style question (if possible)
Made question into a 2x2 Q now S
6 F
3 X
N E
A 41.8 Need to have discussion to get a better understanding of why anyone would think the remote shutdown panel would be of any use without any power (B and C)
Changed answers from "Station Blackout" to "Loss of Offsite Power". More plausible due to being mentioned in the ONEP, The instructions in this procedure are also developed to mitigate the following conditions: A loss of offsite power.
Changed KA, New Question Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 7
H 2
X N
E B
41.14 Margin typo in (2); place MINIMUM in caps Corrected margin in (2) stem and put minimum in all caps. Q now S 8
H 2
N S
D 41.7 9
H 3
X N
E C
41.10 Discuss - I would like to better understand why anyone would select A Per the Inadequate decay heat removal ONEP Step A9 with no decay heat removal available then flood the RPV, The student must know RWCU is still available. Q now S 10 H
3 X
X N
U A
41.12 Discuss - don't see how 1) or 2) would ever be wrong on any radiation hazard. This would leave only A and D as viable distractors.
Changed all answers to more viable distractors. Discuss BC comments - add "immediately" to stem. Added immediately to the stem Q now S 11 H
3 X
N E
A 41.10 Put ONLY at the end of B,C, and D. Instrument air is in three of the four distractors; discuss possible alternatives Changed another distractor and removed instrument air.
Rearanged distractors. Added Three minutes ago the CRS entered due to the instrument air isolation valves have a 30 second time delay after isolation signal. Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 12 F
3 X
N E
C 41.7 Discuss distractor D - would it be more plausible to choose a value just below (instead of just above) the scram setpoint?
Changed answer D to 1060 psig instead of 1065 psig to be below the scram setpoint. Q now S 13 H
3 X
X N
E B
41.9 REFERENCE PROVIDED. Please provide info regarding an appropriate event and not just "an event has occurred." Stem also needs rephrased, as the CRS is required to direct actions at all temperatures. Verify only the graph is provided.
Added a LOCA has occurred.
Changed stem to specific action in EP3, "require the CRS to INITIATE SPMU".
Only the HCTL is provided. Q now S 14 F
3 X
X X
N U
B 41.9 On 2008 NRC EXAM. Distractors (4) and (5) should be B and C.
Almost any abnormal condition in containment "may" cause containment or equipment damage. This immediately cues that either A or C must be the correct answer.
Changed question. New Question Q now S 15 H
3 N
S D
41.9 16 H
3 N
S A
41.7 a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 17 H
3 X
N E
C 41.10 In stem, change "cause" to "direct" Changed "cause" to "direct" in the stem. Q now S 18 H
3 X
N U
B 41.12 C does not appear to make sense as "immediate threat to health and safety of the public" happens at he General Emergency leval, and an Alert is still two levels below that.
D does not appear to make sense, either, as the ERO would have been activated long before a General Emergency was declared.
Changed answers Q now S 19 F
3 B
S C
41.7 ON 2021 NRC EXAM.
20 F
3 X
M E
A 41.10 ON FEB 2020 NRC EXAM.
Discuss possibility of changing voltages to 490 and 520, which would change the correct answer and qualify as a modified bank (it looks like we may have too many questions from the last two exams). This question is from the 2/2020 exam which is not part of the last 2. GG had exams in 2/2020 and 10/2020 and 10/2021 Changed answers to 490 and 520, now 'A' is the correct answer. Changed to 'M' modified. Added original question Q now S 21 H
3 N
S A
41.5 22 F
3 N
S C
41.4 a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 23 F
2 X
X X
X N
U B
41.10 Two correct answers as written; add MINIMUM in stem to prevent D from also being correct. Also, add "per procedure/document XXX" for second part of answer
+change ALL to WR to make A and C more plausible. Would second part be SRO only because it's a TS bases question?
Added MINIMUM to the stem.
Added per procedure in the stem. Changed #2 for answers
'A' and 'C' to state "To prevent a loss of Wide range.."
Corrected Explanation on Wide Range level indication.
This is a RO question due to being EP Bases not Tech Spec.
Q now S 24 H
2 N
S D
41.5 25 H
2 B
S A
41.6 ON 2021 NRC EXAM.
26 H
2 X
X N
U C
41.11 Two stem typos (an, indications).Question needs restructuring, as every component in the correct answer is listed in three of the four distractors (cues C is correct).
Changed question Changed answer C from Containment to ESF Switchgear Room ventilation.Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 27 F
2 X
N E
C 41.7 Distractor A seems awfully low and D seems awfully high to be plausible (discuss).
Used recognizable numbers associated with the RHR/ Low Pressure ECCS systems. Q now S
28 H
2 X
N E
D 41.14 Would "throttle open" or "throttle close" be more accurate in the distractors? Why would anyone believe they meet an entry condition for a ONEP given the information provided in the stem (distractors A and B)?
Added "Throttle" to answers.
Per ONEP Symptoms, "Rising Spent Fuel Pool OR Reactor Coolant temperature." Added more information in the stem for setup of rising temps. Q now S 29 F
2 X
X N
E B
41.11 Add MINIMUM in stem. Discuss plausibility of 1000 or 10,000 mRem/hr (C and D); not sure anyone wold believe that the setpoint to require action would be that high Added MINIMUM to stem. 1000 (103 is between the Operating limit (EP-4 entry condition) and the Max Safe limit of SC-1 Table. Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 30 H
2 X
N E
A 41.7 Discuss, explanations don't appear to match up with the distractors; I'd like to better understand why someone would believe the pump would not start if the pushbutton was "armed and depressed."
Corrected all explanations.
Changed stem to E21-F011, Min flow valve and F005 Injection valve, removed pump. Q now S 31 F
2 N
S D
41.7 32 H
2 X
N E
B 41.6 Discuss; don't understand why anyone would think SLC pumps would not be vitally powered (A and D).
Its not a question of not being powered from vital buses but, will the system restore after LSS to a running condition.
Several systems require a compontent restart after power has been restored. The applicant must be aware that the SLC handswitches are maintain contact switches and the system will be restored as soon as power is restored.
Deleted pump status in all answers. Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 33 H
2 X
N U
A 41.6 B RPS trips and all the B lights go out; maybe I'm missing something but it appears pretty obvious. D appears implausible in any case, as a single train RPS failure deenergizing everything seems far fetched.
Changed question Q now S 34 F
2 B
S B
41.7 ON FEB 2020 NRC EXAM.
35 H
2 B
S B
41.7 ON FEB 2020 NRC EXAM.
36 H
4 X
B E
C 41.6 ON 2015 NRC EXAM.
REFERENCE PROVIDED. Please walk through question using the power to flow map to verify disctractors.
The PF map is used to determine the plant is operating in the OPRM Armed region.
The applicant must be aware that THI has been detected by the OPRM system and automatic actions did not occur. Added PF map Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 37 H
2 X
X N
U D
41.7 Answer appears to be in stem (flow controller is 100% open in auto); even aside from that, knowledge of taking manual control of a failed automatic function is not very discrimiating.
Picture can be removed, comment during in house validation. Its how the operator takes control, the thumbwheel no longer will work to adjust flow due to the flow feedback signal being lost, the operator must move the selector switch to the MAN position and use the OPEN/CLOSE pushbuttons.
Remove picture and change (2) answers to say Place in MAN Q now S 38 H
2 X
N E
B 41.5 Capitalize EARLIEST in stem Earliest in all caps in the stem.
Q now S 39 H
2 B
S A
41.7 ON 2017 NRC EXAM. a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 40 F
2 X
N E
A 41.7 Lockout transfer relay control switch - if this switch does not exist, what makes it viable (distractors B and C)?
The Lockout Transfer Relay control switch does exist, its used when separating the Control Room controls from the RDP control, i.e. like during a fire in the control room. Other components on the RSP require an EMERGENCY switch be manipulated prior to the component switch being used.
Like a permissive, several RHR system valves require a NORM /
EMER switch being placed in EMER for the component switch to work. The SRV switches do not require and permissive switch being used.
The SRVs will operate anytime the valve switch is taken to open. Q now S 41 H
2 B
S D
41.4 ON 2017 NRC EXAM.
42 H
2 B
S C
41.7 43 F
2 X
X N
U C
41.7 Distractors A and B imply that 10CFR guidelines don't apply, which does not appear credible.
Also, questionable match to the K/A - would probably be better if you asked for an actual limit (ability to predict and/or monitor limits) instead of what the limit is based on.
Changed question to show limits and change correct answer to 'C' Removed the first two sentences from the stem. Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 44 H
2 X
N U
A 41.8 C and D state the breaker is incapable of being operated at all (even manually) without control power; this does not appear credible. Also, if D was correct, it appears C would also be correct.
Pretty obvious that A is the correct answer.
Reworded answers 'C' and 'D' Q now S 45 H
2 B
S C
41.7 ON FEB 2020 NRC EXAM.
46 H
2 X
X N
E D
41.8 Add "expected" before indication in stem. Need to discuss - I'm not sure I understand the viability of A or B.
If the applicant thinks that the charger is the only thing supplying voltage to the bus then the indication would be '0'.
If the applicant knows there are 2 chargers sharing the load the the loss of one the output would only be 50% therefore, half of 135 is 67. Changed 'A' and 'B' to closer numbers. Q now S 47 H
2 B
S D
41.7 ON 2014 NRC EXAM.
48 F
2 N
S C
41.7 49 F
2 N
S A
41.7 50 H
2 N
S B
41.4 a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 51 H
2 X
B U
B 41.14 Distractors C and D appear to employ "impossible physics" as I have never seen any regen HX flow control valve open in response to lowering temps and close in response to rising temps.Changed KA due to inability to develop a discriminatory RO question.
New Q from bank and was on the 2011 NRC Exam Q now S 52 H
2 X
N E
A 41.4 REFERENCE PROVIDED. Please walk through the question with the references to verify plausibility of distractors. NRC Submittal Comments; changed (2) to the following:Can use Either HS-M630B or HS-M008B and Must use Both HS-M630B and HS-M008B Q now S 53 H
2 X
X N
E D
41.8 "Place CRD SYS FLO CONT to MAN and CLOSE" is in three out of the four answers (cues that portion is correct with probably something else with it). Discuss possibilities of modifying distractors to make correct answer less obvious.
Changed Answer 'C' to restore power to MCC ONLY. Changed stem to "action(s) is/are" Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 54 F
2 X
N E
D 41.6 Hard to believe D palusible with all lights off at the end of the evolution. Discuss "A" Changed 'A' to say "Insert using In Time Skip." Developed new question, changed correct answer to 'D' Q now S 55 H
2 B
S C
41.2 ON 2021 NRC EXAM.
56 F
2 X
B E
A 41.3 FIRST TEN. Potential cueing, as "A" is in both the stem and the answer (made me guess correctly). Discuss.
Changed answer 'A' to 601 Blue pen. This is exactally what the operator would see. Removed
'A' in the stem and added "One Filter Demin is in service" to stem. Not able to write a discriminatory RO level question, changed KA. Changed to bank question. Q now S 57 F
2 X
X N
E A
41.2 Too much information in stem.
Combine the two sentences into one and leave out that the detectors pose a significant radiation hazard and must be shielded.
Combined the two sentences. Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 58 H
2 X
B E
B 41.7 C not plausible (nothing happens).
The stem doesn't say where level originally indicates; what if it's full upscale to begin with?
Added "all Wide Range indications are normal."
Changed answer 'C' to slow downward trend. Q now S 59 H
2 X
N E
D 41.13 Distractor D - don't see how a routine activity using an SOI is plausible as an emergency situation I'm assuming Distractor 'B' not
'D' since 'D' is the correct answer and an alarm not an SOI task. Changed answer 'B' to low Demin flow that would cause an alarm only but not low enough to cause a demin isolation that would in turn cause a pump trip and loss of cooling, therefore, entry into the ONEP. Q now S 60 F
2 N
S B
41.10 61 F
2 N
S A
41.7 62 H
2 N
S D
41.4 63 H
2 N
S C
41.10 64 F
2 X
X N
E A
41.7 C - thickness typo; add per 10 CFR 50.46 in stem Corrected typo in 'C' and added 10 CFR 50.46 to stem. Q now S 65 F
2 X
N E
B 41.7 Why is SPDS the only acronym spelled out?
Removed the spelled out part in answer 'D' Q now S 66 F
2 B
S D
41.10 ON 2017 NRC EXAM. a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 67 F
2 X
B U
C 41.10 Don't see startup or hot shutdown as credible given 145 degrees and a detensioned head Changed question with new plant conditions. Changed correct answer to 'C' Changed question. Now a bank question that was on the 2017 NRC Exam. Q now S 68 F
2 X
X N
E C
41.12 Add "at a MINIMUM" after comma (makes CRS a little more plausible) and "per EN-RP-101, XXX" at the end of stem (removes any doubt that SM permission is not "required.".
Added "at a MINIMUM" to the stem. Added per EN-RP-101 to end of the stem. Spell out CRS; Add LHRA in explanations. Q now S 69 F
2 X
X N
U B
41.10 FIRST TEN. As written, it appears that the most extreme distractor is the correct answer, rendering the other distractors as probably non-credible Discuss; would addition of "At a MINIMUM" in third sentence of stem make the other distractors more credible? Even with that, really don't see why one would think exceeding normal limits would require an ED (distractors C and D).
Changed "Max Normal" to "Operating Limit" per Table SC-1 of EP-4. Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 70 F
2 X
X X
N E
D 41.1 Add "At Grand Gulf Nuclear Station" in stem. Question not properly structured; "absorption" only distractor listed twice cueing it as probably in the corrcet answer. Discuss making 2X2 with fission and absorption.
Added at GGNS to stem.
Made question a 2X2. Q now S 71 F
2 X
B E
C 41.1 Stem: The reactor has been operating at full power for two weeks following a refueling outage. A grid disturbance causes a turbine trip and an automatic reactor scram. The grid disturnace was immediately resolved and the crew subsequently entered procedure XXX(specific to Grand Gulf) to perform a reactor startup.
When the reactor is brought critical approximately five hours after the automatic scram...
Changed question stem to make GG specific Q now S 72 F
2 X
B E
A 41.1 Add "At Grand Gulf Nuclear Station" in stem.
Added "At GGNS" to the stem Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 73 F
2 X
N U
B 41.14 Any ratio with an "ideal" on top would result in over 100%
efficiency (C and D not plausible).
What is a "reaction" turbine (D)?
Changed KA to K1.12 instead of K1.08. New question Made changes to form 4.1-1 Rejected KAs. Removed (subcooled) from stem Q now S 74 F
2 X
B E
C 41.14 Add "At Grand Gulf Nuclear Station" in stem. Reference and distractor explanations?
Added "At GGNS" to the stem.
Completed References and distractor explanations. Q now S
75 F
2 X
B E
D 41.14 Add "At Grand Gulf Nuclear Station" in stem. Reference and distractor explanations?
Added "At GGNS" to the stem.
Completed References and distractor explanations. Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 76 H
3 X
N E
B 43.5 REFERENCE PROVIDED. Please walk through question using the reference; not sure I can see why lowering flow would be plausible in this situation.
The objective of the actions is to reduce reactor power to get below the MELLLA Boundary, per the PF map with current core flow the target would be 73% power. Reducing core flow would reduce power, but, would still remain above the boundary line. The plausibility is knowling that power needs to be reduced and lowering core flow would reduce power but not be blow the boundary line.
Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 77 H
3 X
X N
E B
43.5 I'd like to better understand why C and D are wrong, as the stem does not indicate any local indication of breaker or component damage nor a confirmed cause (or does the fault alarm do that)? Could we add in the stem, which of the following is the NEXT action that should be directed in accordance with procedural requirements?
Worded stem to say "What should be the NEXT action directed by the CRS?"
The C4 alarm suggest a possible bus fault, which would require the CRS to investigate and then restore, with Instrument air supply valve being powered by the MCC there in not enough time to investigate. Plant data shows about 2 minutes before control rods begin to drift.
ONEP states, "ESF 480 V AC Bus is in LOCKOUT OR FAULTED Condition, Then, DO NOT RE-ENERGIZE Bus UNTIL condition is repaired OR isolated. Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 78 H
3 X
N E
A 43.5 FIRST TEN. REFERENCE PROVIDED. Discuss; appears that it would be fairly difficult to come up with the wrong answer on this one. In distractor D, essentially nothing changes, making it something of a "none of the above" distractor, which should be avoided.
Changed answer D to points on Attachment II graph which will not be used for this application. Q now S 79 H
3 X
X N
U C
43.5 FIRST TEN. Two correct answers as written. If complete loss of instrument air procedure is required to be entered <80 psig, then it's still going to be required to be entered <70 psig (distractor B). Also, isolating valves seems to pale as a success path compared to getting an air compressor running (i.e. are distractors A and D really credible?) Possibly add what is the "MAXIMUM" air pressure where procedure must be entered and give indication of some kind of a leak in the stem to make A and D more plausible.
Changed stem question to fill in blank directly from ONEP on what pressure would require CRS to transition to a different section of the ONEP and shutdown the plant. Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 80 H
3 X
X N
E A
43.5 FIRST TEN. EP2 appearing in two distractors may cue that EP2 is in the correct answer? Not sure why one would go for EP4? Add "use to" after CRS in stem.
Added Use to to question in stem. Removed reference to EPs entered to allow the CRS to make the decision as to which step should be next.
EP4 is used as a distractor due to entry from the RCIC steam line break, however the stem states that RCIC isolated and therefore there is no chance of ED from EP4. Q now S 81 H
3 X
N E
D 43.5 "from" should be "from the" in stem?
Added the to question stem to now state, the CRS should be directing from the. Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 82 H
3 X
X N
E C
43.5 FIRST TEN. Explanation lists the normal and emergency limits for MVAR's as the same (please explain). What is causing the alarm (one general protection relay failed)? Possible subset issue; if -297.5 to +697.5 were the correct answer, then wouldn't that make two answers correct since -
200 to +200 is inclusive to -297.5 to +697.5?
The procedure states the limits as the same, procedure change request sent to OPS.
A relay failure that has caused the voltage regulator to shift to MANUAL.
When the voltage regulator fails to MAN the VAR limits narrow to -200 to +200 from normal limit of -297.5 to +697.5. Q now S
83 H
3 X
N E
B 43.5 Discuss plausibility of incorrect distractors with the plant at full power (ED at full power?)
Changed answer A to Initiate SPMU, plausible due to this action is in the Suppression Pool Temperature leg but not in the Containment Temperature leg. Q now S 84 H
3 N
S D
43.5 a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 85 H
3 X
X B
E C
43.2 ON 2013 NRC EXAM.
REFERENCE PROVIDED.
"MAXIMUM" in caps in stem.
Please discuss question with references to ensure distractors are plausible.
Maximum in CAPs Added TS references for distractors to ensure plausibility.
Changed distractor A to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, if applicant stops at first completion time and not move to condition B to get to mode 3.
Changed distractor B to 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, if applicant incorrectly thinks both SBGT subsystems are INOP. Q now same TS as replacement admin JPM AS-3; Replace. On new question, delete "below any alarm setpoints" in stem third bullet.
Reworded distractor B Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 86 H
3 X
X N
E A
43.5 FIRST TEN. Discuss; isn't it apparent that a full core offload would minimize the need to have ECCS available? If (4) was required, wouldn't that also be covered in (2)? (2) is also pretty generic and appears that it would be correct under many circumstances (?). Why use "ECCS systems" in (2) but just "ECCS" in (4)?
Changed stem to include words from IOI on full core offload.
- 4 states to actually enter the LCO but the only requirement is to initiate a Potential LCO for 3.5.2.
Added "system" to #4 Replaced. Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 87 H
3 X
X N
E D
43.5 I'm not sure I'm understanding the question. Why would rods not be inserted if a scram signal was generated and the IRMs were reading normal after the transient?
Is the question trying to imply that an ATWS has occurred? Maybe stem needs some adjustment (Discuss).
The applicant is required to conclude that an ATWS has occurred, therefore EP2/2A must be entered along with the Reactor Scram ONEP. With power being well beiow 5% due to being on range 7 a normal RPV level band will be given.
Changed wording of stem and added associated alarms. Q now S 88 H
3 X
N E
A 43.2 FIRST TEN. What is the definition of "most limiting?" Please explain why someone would think an LCO with a 14 day action might be the "most limiting" TS LCO (i.e.
discuss credibility of B and D)?
New question. Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 89 H
3 X
N U
B 43.2 REFERENCE PROVIDED. Don't see how 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is plausible; in any case don't see any plausibility associated with restoring float voltage to category A or B limits with either 2 or 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. Could also be argued a "direct lookup" question Replaced with closed reference question. Q now S 90 H
3 X
N E
C 43.5 REFERENCE PROVIDED. What reference do you intend to providejust the applicable page, a section, the entire procedure?
Why is a reference necessary at all? Please walk through question and reference and discuss plausibility of distractors.
Re-write of question to determine Tech Spec LCO for mode 3 shutdown. Changed references. Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 91 H
3 X
X N
E D
43.6 In stem, change "what is" to "what should be" and change "will be" to "should be." What prohibits the CRS from entering the ONEP?
Changed "what is" to "what should be" and "will be" to "should be".
The SOI allows drive water DP to be raised during normal control rod movement up to 350 psid. After 350 psid is reached and rod will not move then the ONEP is entered and Inability to Withdraw Control Rods section is entered. Q now S 92 H
3 X
N U
A 43.2 REFERENCE PROVIDED. Why is "the" necessary in front of the valve number? Why would one bellieve that more than one system/subsystem is inoperable?
Why would one believe a completion time was not met when no times are given in the stem?
Removed "the" from in front of valve number.
RHR 'A' is already INOP for LPCI due to being in Suppression Pool Cooling with the F024A open. When the F024B fails to open and trips the breaker, LPCI 'B' is still operable, but, Suppression Pool cooling for 'B' is now INOP.
Changed 'D' to 14 days.
Replaced. Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 93 F
2 X
N U
B 43.4 Don't see how a ventilation problem in the control building could cause habitability issues in other buildings? This appears to make only one distractor plausible. Revised question to ask backup facility for the TTC Q now S 94 F
2 B
S B
43.5 ON 2017 NRC EXAM.
95 F
2 X
B E
C 43.5 ON OCT 2020 NRC EXAM.
Discuss - how/why are A and B considered refueling activities?
Answer A & B: Performance of both of these activities must be done during an outage with the Reactor Head removed for refueling purposes.
Changed Answer A explanation to the following: Replacing of a CRD Mech. is mostly done from undervessel area, however, when the control rod is uncoupled the Refueling Bridge is used to hold the control rod while being uncoupled.
Changed Answer B explanation to the following: Removing an SRM detector from the core is done by the Refueling Bridge, but, per Tech Specs is not considered a Core Alteration. Q now S 96 F
2 B
S A
43.2 ON 2017 NRC EXAM. a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 97 F
2 X
N E
D 43.2 Revise stem: "Which of the following is the MAXIMUM time allowed by Tech Specs to place the plant in Mode 4" Revised Stem to the following, Which of the following is the MAXIMUM time allowed by Tech Specs to place the plant in MODE 4? Q now S 98 F
2 X
N E
C 43.4 Discuss - shouldn't MAXIMUM be MINIMUM? (otherwise, wouldn't D be the correct answer?)
Changed MAXIMUM to MINIMUM Q now S 99 F
2 X
X N
E D
43.5 FIRST TEN. Just about any adverse condition COULD potentially cause substantial core damage. Better if stem is tied to the procedure being referenced, i.e. "According to Emergency Procedure 02-S-01-4O, which caution, if not adhered to" Added According to 02-S 40, EP Technical Bases to stem. Q now S a Rev 2
Form 2.3-5 GG-2022-10 Written Examination Review Worksheet Form 2.3-5 100 F
2 X
B E
A 43.5 ON 2011 NRC EXAM. Discuss distractor B - how is an airborne attack not an armed attack against the plant?
Changed answer B to "Plant control has been transferred to the Remote Shutdown Panel.
Is transferring control to the RSP in of itself an emergency?
Discuss making B some kind of flooding emergency. Q now S Results Table RO LOK -H 42 Avg RO LOD 2.29 Flaws 10 CFR Distribution RO LOK-F 33 AVG SRO LOD 2.68 Stem focus 31 41.1 15 43.1 0 SRO LOK - H 17 Overall LOD 2.39 Cues 8
41.2 2
43.2 6 SRO LOK - F 8
T/F 0
41.3 1
43.3 0 Cred Dist 53 41.4 5
43.4 2 RO Bank 23 30.67 SRO Bank 5
20 Partial 5
41.5 4
43.5 16 RO Mod 1
1.333 SRO Mod 0
0 job link 0
41.6 6
43.6 1 RO New 51 68 SRO New 20 80 units 0
41.7 22 43.7 0 minutia 0
41.8 5
Total Bank 28 28 backward 0
41.9 3
Total Mod 1
1 KA 1
41.10 15 Total New 71 71 SRO-only 1
41.11 2
LOD = 1 0
41.12 3
12 41.13 1
16 Answer Dist ( in %)
41.14 6
RO Edit 35 46.67 SRO Edit 18 72 RO-A 20 SRO-A 7
RO-B 19 SRO-B 6
Total Sat 29 29 Total Unsat 18 18 RO-C 19 SRO-C 6
Total Edit 53 53 RO-D 17 SRO-D 6 a Rev 2
Question Overlap with the Previous Two NRC Exams QA form ES-401-6 item 4 requires 4 or less questions on RO exam from previous two NRC exams, SRO portion two or less questions from previous two NRC exams*
- if this is exceeded, the region shall call NRR to explain why/reasons.
RO overlap from previous two NRC exams 4
SRO overlap from the previous two NRC exams 1
Questions Requiring References to Answer 6-10 questions rule of thumb on SRO portion of exam are allowed to be open reference, while the RO exam is generally none RO Questions that require hand-outs 4
SRO Questions that require hand-outs 6