Issue date | From | Title | Project stage | |
---|---|---|---|---|
RS-20-139, Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-505, Revision 2, and 10 CFR 50.69 | 24 November 2020 | Exelon Simpson P | Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-505, Revision 2, and 10 CFR 50.69 | Response to RAI |
JAFP-21-0069, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors | 30 July 2021 | Exelon David Gudger | Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors | Request |
JAFP-21-0070, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b | 30 July 2021 | Exelon David Gudger | License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b | Request |
ML21246A211 | 3 September 2021 | Justin Poole Plant Licensing Branch I | Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-505 | Acceptance Review |
ML21246A207 | 3 September 2021 | Justin Poole Plant Licensing Branch I | Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 | Acceptance Review |
ML21285A149 | 22 October 2021 | Justin Poole Plant Licensing Branch I | Audit Plan in Support of Review of License Amendment Requests Regarding 50.69/TSFT-505 | Other |
JAFP-22-2020, Supplemental Information No. 1 for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b. and 10CFR 50.69, Risk-Info | 4 March 2022 | Constellation David Gudger | Supplemental Information No. 1 for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b. and 10CFR 50.69, Risk-Informed | Supplement |
ML22124A267 | 4 May 2022 | Justin Poole NRC/NRR/DORL/LPL1 | Request for Additional Information for James A. FitzPatrick Nuclear Power Plant TSTF-505 | RAI |
JAFP-22-0032, Response to Request for Additional Information for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b.. | 16 June 2022 | Constellation David Gudger | Response to Request for Additional Information for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b.. | Response to RAI |
ML22196A061 | 23 August 2022 | Justin Poole NRC/NRR/DORL/LPL1 | Issuance of Amendment No. 352 Adoption of 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors | Approval |
ML22238A120 | 31 August 2022 | Justin Poole Plant Licensing Branch I | Regulatory Audit Summary Regarding License Amendment Requests to Adopt 10 CFR 50.69 and to Permit the Use of Risk-Informed Completion Times in Accordance with TSTF-505, Rev. 2 (EPIDs L-2021-LLA 0142 and L-2021-LLA-0143) | Other |
ML22223A141 | 1 September 2022 | Justin Poole Plant Licensing Branch I | Issuance of Amendment No. 353 Adoption of TSTF - 505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B | Approval |