2018 DB Ile ES-301-1 RO and SRO Admin Outlines
ML22186A198
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 11/08/2017
From: Randy Baker
NRC/RGN-III/DRS/OLB
To:
Baker R
Shared Package
ML17068A445 List:
References
L-17-281
Download: ML22186A198 (2)


Text

ES-301 Administrative Topics Outline Form ES-301-1

Facility: Davis Besse Nuclear Power Station Date of Examination: 2/5/2018 to 2/16/2018

Examination Level RO SRO Operating Test Number DB NRC 2018

Administrative Type Describe activity to be performed Topic Code*

(See Note)

Conduct of 2.1.37 (4.3)

Operations Knowledge of procedures, guidelines, or limitations associated with D, R reactivity management.

(RO A 1.1)

Perform a Calculation for Shutdown Value (JPM-259)

Conduct of 2.1.43 (4.1)

Operations Ability to use procedures to determine the effects on reactivity of plant D, R changes, such as reactor coolant system temperature, secondary plant, (RO A 1.2) fuel depletion, etc.

1/M Approach to Criticality (JPM-276)

Equipment 2.2.13 (4.1)

Control D, R Knowledge of tagging and clearance procedures.

(RO A 2)

Review a Safety Clearance for CC210 with eSOMs Unavailable (Peer Check) (JPM-TBD)

Radiation Control 2.3.7 (3.5)

(RO A 3) N, R Ability to comply with radiation work permit requirements during normal or abnormal conditions.

Stay Time Calculation (JPM-New)

Emergency Plan

(RO A 4) NOT EVALUATED

NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics (which would require all 5 items).

  • Type Codes & Criteria (C)ontrol Room, (S)imulator, or Class(R)oom (D)irect from bank (< 3 for ROs; < 4 for SROs & RO retakes)

(N)ew or (M)odified from bank ( > 1)

(P)revious 2 exams (< 1; randomly selected)

NUREG-1021, Revision 1 1 FENOC Facsimile Rev 1 ES-301 Administrative Topics Outline Form ES-301-1

Facility: Davis Besse Nuclear Power Station Date of Examination: 2/5/2018 to 2/16/2018

Examination Level RO SRO Operating Test Number: DB NRC 2018

Administrative Type Describe activity to be performed Topic Code*

(See Note)

Conduct of 2.1.37 (4.6)

Operations Knowledge of procedures, guidelines, or limitations associated with D, R reactivity management.

(SRO A 1.1)

Review a Shutdown Value Calculation (JPM-262)

Conduct of 2.1.31 (4.3)

Operations Ability to locate control room switches, controls, and indications, and to N, R determine that they correctly reflect the desired plant lineup.

(SRO A 1.2)

Review Miscellaneous Instrument Daily Checks per DB-OP-03007 (JPM-New)

Equipment Control 2.2.18 (3.9)

(SRO A 2) N, R Knowledge of the process for managing maintenance activities during shutdown operations, such as risk assessments, work prioritization, etc.

Perform Shutdown Safety Assessment (JPM-New)

Radiation Control 2.3.4 (3.7)

(SRO A 3) M, P, R Knowledge of radiation exposure limits under normal or emergency conditions.

Emergency Dose Authorization (JPM -280)

Emergency Plan D, R 2.4.44 (4.4)

(SRO A 4) Knowledge of the emergency action level thresholds and classifications.

Determine the Off-Site PAR (JPM150)

NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics (which would require all 5 items).

  • Type Codes & Criteria (C)ontrol Room, (S)imulator, or Class(R)oom (D)irect from bank (< 3 for ROs; < 4 for SROs & RO retakes)

(N)ew or (M)odified from bank ( > 1)

(P)revious 2 exams (< 1; randomly selected)

NUREG-1021, Revision 1 1 FENOC Facsimile Rev 1