MONTHYEARML21028A7532021-01-28028 January 2021 Triennial Update to Decommissioning Funding Plan (DFP) for the Framatome Inc. Richland Nuclear Fuel Fabrication Facility Project stage: Request ML21074A0222021-03-17017 March 2021 NRC Acceptance of Framatome Inc.'S Triennial Decommissioning Funding Plan Update for Review Project stage: Acceptance Review ML21116A1412021-04-30030 April 2021 Request for Additional Information Framatome'S Triennial DFP Update Project stage: RAI ML22181B0682021-07-29029 July 2021 NRC Final Approval to Fram 2021 DFP Project stage: Other 2021-03-17
[Table View] |
|
---|
Category:Letter
MONTHYEARML24026A2792024-01-31031 January 2024 Framatome - Richland Integrated Inspection Report 07001257/2023004 ML24031A5432024-01-23023 January 2024 Triennial Update to Decommissioning Funding Plan (DFP) for the Framatome Inc., Richland Nuclear Fuel Fabrication Facility Cover Letter ML23352A3912023-12-20020 December 2023 Framatome Inc. - Richland Material Control and Accounting Program Inspection Report 07001257-2023401-Public Cover Letter ML23313A0772023-11-27027 November 2023 Framatome Inc. - Request to Amend License and Approve Criticality Safety Methods - License Amendment 19 (Enterprise Project Identification Number L-2023-LLA-0073) ML23296A0072023-10-25025 October 2023 Framatome-Richland - Core Inspection Report 07001257/2023003 ML23291A2042023-10-18018 October 2023 Framatome Inc., Richland Nuclear Fuel Fabrication Facility'S Request to Amend License No. SNM-1227 and Approval of Criticality Safety Methods ML23255A2892023-09-15015 September 2023 Framatome-Richland Inspection Schedule for Calendar Year 2024 ML23254A2502023-09-13013 September 2023 Request of Additional Information Letter to Framatome ML23202A2022023-07-24024 July 2023 Framatome Richland Core Inspection Report 07001257/2023002 ML23198A3172023-07-17017 July 2023 Framatome Inc. Richland Nuclear Fuel Fabrication Facility'S Revised Chapter 1 of License No. SNM-1227 ML23144A3092023-06-21021 June 2023 Acceptance Letter for Request by Framatome for a License Amendment for an Approval of Criticality Safety Methods ML23144A3372023-06-12012 June 2023 Letter to Framatome Approval of Request to Withhold Proprietary Information ML23145A3082023-06-0202 June 2023 Framatome - Licensing Project Manager Change Letter ML23137A3962023-05-17017 May 2023 Framatome, Inc., Richland Nuclear Fuel Fabrication Facilitys Request to Amend License No. SNM-1227; and Approval of Criticality Safety Methods ML23137A4062023-05-17017 May 2023 Framatome, Inc., Submittal of NRC Form 327s Which Report the Results of Material Balance Accounting and Seid Calculations for the Period March 22, 2022 to March 20, 2023 ML23089A2592023-04-10010 April 2023 2023-001 Framatome-Richland - NRC Integrated Inspection Report 07001257/2023001 ML23089A2602023-03-30030 March 2023 Framatome, Inc. - 2023 Fee Increase for Fuel Cycle Licensees; License No. SNM-1227; Docket No. 70-1257 ML23054A2562023-02-23023 February 2023 60-Day Report to January 2, 2023, Incident Reported Under 10 CFR 70 Appendix a Concurrent Report (NRC Event No. 56292); Framatome Richland Facility; License No. SNWI-1227; Docket No. 70-1257 ML22336A0992023-02-0303 February 2023 Cover Letter - Framatome Proprietary Approval 3x Letter of Intent Submittals 11/21/2022 and 11/29/2022 ML23030B6172023-01-31031 January 2023 Framatome-Richland - Core Inspection Report 07001257/2022004 ML23025A3172023-01-25025 January 2023 Submittal of Integrated Safety Analysis (ISA) Summary Annual Update for Framatome Inc.'S (Framatome'S) Richland, Washington Fuel Fabrication Facility ML22341A1562022-12-0707 December 2022 60-day Follow Up Report for an Incident Reported Under 10 CFR 70 Appendix a (C) Concurrent Report (NRC Event No.56713); Framatome Richland Facility ML22272A0252022-10-0404 October 2022 Framatome-Richland -Integrated Inspection Report 07001257/2022003 ML22263A4652022-09-20020 September 2022 Framatome, Inc. Submittal of Revised Fundamental Nuclear Material Control Plan ML22255A0122022-08-31031 August 2022 Framatome Inc. - Required Reporting of Effluents Per 10 CFR 70.59 ML22238A1602022-08-24024 August 2022 Framatome Richland Facility Emergency Plan Version 16.0 ML22236A5872022-08-23023 August 2022 Framatome Inc., Richland Nuclear Fuel Fabrication Facility'S Intent to Amend License No. SNM-1227; ML22201A5352022-07-21021 July 2022 Framatome 2022-002 Integrated Quarterly Inspection Report ML22192A1272022-07-11011 July 2022 Framatome, Inc., 60-day Report for a May 12, 2022 Incident Reported Under 10 CFR 70 Appendix a 24-hour Report (NRC Event No. 55897) ML22154A4382022-07-11011 July 2022 Cover Letter - Framatome Inc. - Request to Amend License and Approve Criticality Safety Methods - License Amendment 18 (Enterprise Project Identification Number L-2021-LLA-0218) ML22187A1892022-06-29029 June 2022 Framatome-Richland - Inspection Schedule for Calendar Year 2023 ML22187A0392022-06-28028 June 2022 Framatome Documentation Request - 2022-003 PMT ML22137A1282022-06-23023 June 2022 Cover Letter - Framatome- DFP Info and Form 327 Proprietary Review ML22166A3432022-06-10010 June 2022 Framatome Lnc., Submittal of Quality Assurance Program, FS1-0011462, Revision 8.0, 10 CFR 71, Subpart H Quality Assurance Program Description for Packaging and Transportation of Radioactive Materials for Us Fuel ML22132A2292022-05-12012 May 2022 Framatome, Inc., Submittal of NRC Form 327 ML22132A2952022-05-12012 May 2022 Framatome, Inc., Submittal of Triennial Update to Decommissioning Funding Plan (DFP) for the Richland Nuclear Fuel Fabrication Facility ML22087A1212022-03-31031 March 2022 Cover Letter Framatome Inc., - Request for Additional Information Regarding License Amendment Request for Approval of Criticality Safety Methods (Enterprise Project Identification Number L-2021-LLA-0218) ML22059A7582022-03-0303 March 2022 Framatome, Inc., Licensee Performance Review (Nuclear Regulatory Commission Inspection Report 0701257/2022005) ML22060A1262022-03-0101 March 2022 60-day Report to January 4, 2022 Incident Reported Under 10 CFR 70 Appendix a Concurrent Report (NRC Event No. 55686); Framatome Richland Facility; License No. SNM-1227; Docket No. 70-1257 ML22066B2732022-02-28028 February 2022 Framatome, Inc. - Required Reporting of Effluents Per 10 CFR 70.59 for July-December 2021 ML22033A1722022-01-27027 January 2022 Framatome, Inc. Richland Washington Fuel Fabrication Facility Submittal of Update to Integrated Safety Analysis (ISA) ML22025A3902022-01-25025 January 2022 60-day Report to January 4, 2022 Incident Reported Under 10 CFR 70 Appendix a Concurrent Report (NRC Event No. 55686); Framatome Richland Facility ML22024A2152022-01-25025 January 2022 Framatome, Inc. - Richland, U.S. Nuclear Regulatory Commission Integrated Inspection Report 07001257/2021004 ML22024A4832022-01-24024 January 2022 60-Day Report to December 20, 2021 Incident Concurrently Reported Per 10 CFR 70 Appendix A(C) (NRC Event No. 55666); Framatome Richland Facility ML22007A3592022-01-0707 January 2022 Framatome, Inc., 30-Day Report to December 8, 2021 Incident Reported Under 10 CFR 70.50(b)(3) (NRC Event No. 55634) ML21335A3282021-12-23023 December 2021 Response to Framatome Request of 11-1-21 for Withholding Due to Proprietary Information ML21336A7572021-12-0202 December 2021 Framatome, Inc., Richland Facility, 30-day Report to October 12, 2021 Incident Reported Under 10 CFR 70.50(b)(1) (NRC Event No. 55517) 2024-01-31
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 29, 2022 Timothy Tate, Manager Environmental, Safety, Health and Licensing Framatome Inc.
2101 Horn Rapids Road Richland, WA 99354-5102
SUBJECT:
COMPLETION OF REVIEW OF FRAMATOMES TRIENNIAL UPDATE TO DECOMMISSIONING FUNDING PLAN - ENTERPRISE PROJECT IDENTIFIER L-2021-DFA-0000
Dear Timothy Tate:
By letter dated November 16, 2021 (Agencywide Documents Access and Management System (ADAMS) Accession Number ML21293A253), the U.S. Nuclear Regulatory Commission (NRC) approved the financial information in the update to your 2021 Framatome Decommissioning Funding Plan (DFP). However, the approval of the DFP indicated that there were two discrepancies to correct before the NRC review was completed. These discrepancies were as follows:
A. the total amount needed for the financial assurance instrument needed to be corrected, and B. the signature of the Framatome corporate representative needed to correspond to the 2021 information.
The NRC staff received your update to the DFP, E10-05-001, by letter dated May 12 ,2022, (ML22132A295). This version of the DFP included the correct total amount needed for financial assurance as well as the signature from your corporate officer corresponding with the information provided in your 2021 DFP submittal dated August 12, 2021 (ML21166A200). Our financial review team identified that they have the signed original documents.
The NRC staff has completed its review of the 2021 triennial DFP. The NRC staff has determined that the updated DFP is acceptable and, therefore, is approved. This letter closes all efforts under Enterprise Project Identification No. L-2021-DFA-0000.
In accordance with Title 10 of the Code of Federal Regulations, Section 2.390, Public inspections, exemptions, requests for withholding, of the NRCs Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room (PDR), or from ADAMS. The PDR is open by appointment only. You may submit your request to the PDR via email at PDR.Resource@nrc.gov or call 1-800-397-4209 between 8:00 a.m. and 4:00 p.m. (EST), Monday through Friday, except Federal holidays.
The ADAMS database is accessible from the NRC website at: http://www.nrc.gov/reading-rm/adams.html.
T. Tate 2 If you have any questions regarding this communication, please contact me by phone at (301) 415-6201, or via email to Richard.Jervey@nrc.gov.
Sincerely, Richard A. Jervey, Project Manager Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 70-1257 License No. SNM-1227 cc: framatome@listmgr.nrc.gov