2017 Perry Retake Exam Es 301-2 SRO-u
ML22146A186
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 06/27/2017
From: Randy Baker
NRC/RGN-III/DRS/OLB
To:
Baker R
Shared Package
ML17142A152 List:
References
Download: ML22146A186 (1)


Text

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 NUREG 1021, Rev. 10 Page 1 of 1 FENOC Facsimile Facility:

Perry Date of Examination: Jul 2017 Exam Level: SRO-U Operating Test No.: 01a Control Room Systems:* 8 for RO; 7 for SRO-I; 2 or 3 for SRO-U System / JPM Title Type Code*

Safety Function

a. Residual Heat Removal System OT-3701-E12_506 Initiate SDC after loss of SDC A, D, S, E, L, EN 4
b. Suppression Pool Makeup System OT-3037-G43_001 Initiate Suppression Pool Makeup D,S,E 5
c. Plant Ventilation System OT-3701-M25_502 Shift CR HVAC to Normal N, A, S, EN 9
d.
e.
f.

g h

In-Plant Systems@ (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)

i.

Emergency Service Water System OT-3701-D51_303 Assess earthquake damage D, E 2

j.

Fire Protection System OT-3701-P54_003 Initiate Main Transformer Deluge N, R, E 8

k.

All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all five SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.

  • Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path (C)ontrol room (D)irect from bank (E)mergency or abnormal in-plant (EN)gineered safety feature (L)ow-Power / Shutdown (N)ew or (M)odified from bank including 1(A)

(P)revious 2 exams (R)CA (S)imulator 4-6 / 4-6 / 2-3 9 / 8 / 4 1 / 1 / 1 1 / 1/ 1(control room system) 1 / 1 / 1 2 / 2 / 1 3 / 3 / 2 (randomly selected) 1 / 1 / 1