ML21286A506

From kanterella
Jump to navigation Jump to search

Exemption - Palisades Dtf Exemption -
ML21286A506
Person / Time
Site: Palisades Entergy icon.png
Issue date: 12/13/2021
From: Brian Wittick
NRC/NRR/DORL/LPL3
To:
Wall S, NRR/DORL/LPL3, 415-2855
Shared Package
ML21286A581 List:
References
EPID L-2020-LLE-0240
Download: ML21286A506 (10)


Text

NUCLEAR REGULATORY COMMISSION

Docket No. 50-255

Holtec Decommissioning International, LLC

Palisades Nuclear Plant

Exemption

I. Background.

The Palisades Nuclear Plant (PNP) is a pressurized-water reactor located in Van Buren

County, Michigan. Entergy Nuclear Operations, Inc. (ENOI) and Entergy Nuclear Palisades,

LLC (ENP) hold the U.S. Nuclear Regulatory Commission (NRC, the Commission) license for

PNP, Renewed Facility Operating License No. DPR-20. This license is subject to the rules,

regulations, and orders of the NRC. Operation of PNP is scheduled to permanently cease by

May 31, 2022.

By application dated December 23, 2020 (Agencywide Documents Access and

Management System (ADAMS) Accession No. ML20358A075), ENOI, on behalf of itself, ENP,

Holtec International (Holtec), and Holtec Decommissioning International, LLC (HDI), requested

that the NRC consent to (1) the indirect transfer of control of Renewed Facility Operating

License No. DPR-20 for PNP, the general license for the PNP Independent Spent Fuel Storage

Installation (ISFSI), Facility Operating License No. DPR-6 for Big Rock Point Plant (Big Rock

Point), and the general license for the Big Rock Point ISFSI (referred to collectively as the Sites

and the licenses) to Holtec; and (2) the transfer of ENOIs operating authority (i.e., its authority

to conduct licensed activities at the Sites) to HDI.

In support of the license transfer application, by letter dated December 23, 2020

(ADAMS Accession No. ML20358A232), HDI provided to the NRC a post-shutdown

decommissioning activities report (PSDAR) and site-specific decommissioning cost estimate

(SSCE) for PNP. These documents reflected HDIs proposal to decommission PNP over a period (inclusive of 2022) of 20 years if the license transfer application is approved and the

proposed license transfer transaction is consummated. Specifically, the decommissioning of

PNP would begin following the permanent cessation of power operations in 2022 and the

majority of license termination activities would be completed by 2040 (i.e., releasing for

unrestricted use the entirety of the PNP site with the exception of the ISFSI). HDI would then

remove the fuel and Greater than Class C waste from the site, decommission the ISFSI,

terminate the NRC license, and release the remainder of the site for unrestricted use in 2041.

II. Request/Action.

In support of the license transfer application, in addition to providing a PSDAR and an

SSCE, by letter dated December 23, 2020 (ADAMS Accession No. ML20358A239), HDI also

submitted to the NRC a request for exempt ion from specific requirements of

sections 50.82(a)(8)(i)(A) and 50.75(h)(1)(iv) of title 10 of the Code of Federal Regulations (10

CFR). The exemption from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) would permit

HDI to make withdrawals from the PNP Decommissioning Trust Fund (DTF) for spent fuel

management and site restoration activities at PNP, in accordance with the HDI SSCE. The

exemption from 10 CFR 50.75(h)(1)(iv) would also permit HDI to make these withdrawals

without prior notification to the NRC, similar to withdrawals for decommissioning activities made

in accordance with 10 CFR 50.82(a)(8). The exemption would only apply to HDI if and when the

proposed license transfer transaction is consummated.

As part of its exemption request, HDI provided Table 1, which shows the annual cash

flows for the PNP DTF while conducting deco mmissioning activities under the proposal to

decommission PNP discussed in the HDI PSDAR. The table contains the projected withdrawals

from the PNP DTF needed to cover the estimated costs for PNP for radiological

decommissioning, spent fuel management, and site restoration activities in accordance with the

HDI SSCE. By letter dated March 25, 2021 (ADAMS Accession No. ML21084A811), pursuant

to 10 CFR 50.75(f)(1), ENOI reported to the NRC the balance of the PNP DTF as of

2 December 31, 2020. The NRC staff considered all of this information in its review of the

exemption request.

The requirements of 10 CFR 50.82(a)(8)(i)(A) restrict the use of DTF withdrawals to

expenses related to legitimate decommissioning activities consistent with the definition of

decommissioning that appears in 10 CFR 50.2, Definitions. The definition of decommission

in 10 CFR 50.2 is:

to remove a facility or site safely from service and reduce residual radioactivity to a level that permits

(1) Release of the property for unrestricted use and termination of the license;

or

(2) Release of the property under restricted conditions and termination of the license.

This definition does not include activities associated with spent fuel management and site

restoration activities. The requirements of 10 CFR 50.75(h)(1)(iv) also restrict the use of DTF

disbursements (other than for ordinary administrative costs and other incidental expenses of the

fund in connection with the operation of the fund) to decommissioning expenses until final

radiological decommissioning is completed. Therefore, an exemption from

10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) is needed to allow HDI to use funds from

the PNP DTF for spent fuel management and site restoration activities at PNP. The

requirements of 10 CFR 50.75(h)(1)(iv) further provide that, except for withdrawals being made

under 10 CFR 50.82(a)(8) or for payments of ordinary administrative costs and other incidental

expenses of the fund in connection with the operation of the fund, no disbursement may be

made from the DTF without written notice to the NRC at least 30 working days in advance.

Therefore, an exemption from 10 CFR 50.75(h)(1)(iv) is also needed to allow HDI to use funds

from the PNP DTF for spent fuel management and site restoration activities at PNP without prior

NRC notification.

3 III. Discussion.

Pursuant to 10 CFR 50.12, the Commission may, upon application by any interested

person or upon its own initiative, grant exemptions from the requirements of 10 CFR Part 50

(1) when the exemptions are authorized by law, will not present an undue risk to the public

health and safety, and are consistent with the common defense and security; and (2) when any

of the special circumstances listed in 10 CFR 50.12(a)(2) are present. These special

circumstances include, among others:

(ii) Application of the regulation in the particular circumstances would not serve the underlying purpose of the rule or is not necessary to achieve the underlying purpose of the rule; and

(iii) Compliance would result in undue hardship or other costs that are significantly in excess of those contemplated when the regulation was adopted, or that are significantly in excess of those incurred by others similarly situated.

A. Authorized by Law

The requested exemption from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv)

would allow HDI to use a portion of the funds from the PNP DTF for spent fuel management and

site restoration activities at PNP without pr ior notice to the NRC in the same manner that

withdrawals are made under 10 CFR 50.82(a)(8) for decommissioning activities. As stated

above, 10 CFR 50.12 allows the NRC to grant exemptions from the requirements of

10 CFR Part 50 when the exemptions are authorized by law. The NRC staff has determined, as

explained below, that granting HDIs proposed exemption will not result in a violation of the

Atomic Energy Act of 1954, as amended, or the Commissions regulations. Therefore, the

exemption is authorized by law.

B. No Undue Risk to Public Health and Safety

The underlying purpose of 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) is to

provide reasonable assurance that adequate funds will be available for the radiological

decommissioning of power reactors. Based on the HDI SSCE and the cash flow analyses, use

4 of a portion of the PNP DTF for spent fuel management and site restoration activities at PNP will

not adversely impact HDIs ability to complete radiological decommissioning within 60 years and

terminate the PNP license. Furthermore, an exemption from 10 CFR 50.75(h)(1)(iv) to allow

HDI to make withdrawals from the PNP DTF for spent fuel management and site restoration

activities at PNP without prior written notification to the NRC will not affect the sufficiency of

funds in the DTF to accomplish radiological decommissioning, because such withdrawals are

still constrained by the provisions of 10 CFR 50.82(a)(8)(i)(B) - (C) and are reviewable under

the annual reporting requirements of 10 CFR 50.82(a)(8)(v) - (vii).

Based on the above, there are no new accident precursors created by using the PNP

DTF in the proposed manner. Thus, the probability of postulated accidents is not increased.

Also, based on the above, the consequences of postulated accidents are not increased. No

changes are being made in the types or amounts of effluents that may be released offsite.

There is no significant increase in occupational or public radiation exposure. Therefore, the

requested exemption will not present an undue risk to public health and safety.

C. Consistent with the Common Defense and Security

The requested exemption would allow HDI to use funds from the PNP DTF for spent fuel

management and site restoration activities at PNP. Spent fuel management under

10 CFR 50.54(bb) is an integral part of the planned HDI decommissioning and license

termination process and will not adversely affect HDIs ability to physically secure the site or

protect special nuclear material. This change to enable the use of a portion of the funds from

the DTF for spent fuel management and site restoration activities has no relation to security

5 issues. Therefore, the common defense and security is not impacted by the requested

exemption.

D. Special Circumstances

Special circumstances, in accordance with 10 CFR 50.12(a)(2)(ii), are present whenever

application of the regulation in the particular circumstances is not necessary to achieve the

underlying purpose of the regulation.

The underlying purpose of 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv), which

restrict withdrawals from DTFs to expenses fo r radiological decommissioning activities, is to

provide reasonable assurance that adequate funds will be available for radiological

decommissioning of power reactors and license termination. Strict application of these

requirements would prohibit the withdrawal of funds from the PNP DTF for activities other than

radiological decommissioning activities at PNP, such as for spent fuel management and site

restoration activities, until final radiological decommissioning at PNP has been completed.

The PNP DTF contained $553.84 million as of December 31, 2020. HDIs analyses

project the total radiological decommissioning costs at PNP to be approximately $443,215,000

(in 2020 dollars), including the costs for decommissioning the ISFSI. As required by

10 CFR 50.54(bb), HDI estimated the costs associated with spent fuel management at PNP to

be approximately $166,122,000 (in 2020 dollars).

The NRC staff performed independent cash flow analyses of the PNP DTF over the

proposed 20-year decommissioning period (assuming an annual real rate of return of 2 percent,

as allowed by 10 CFR 50.75(e)(1)(ii)) and determined the projected earnings of the DTF. The

NRC staff confirmed that the current funds in the DTF and projected earnings provide

reasonable assurance of adequate funding to complete all NRC-required radiological

decommissioning activities at PNP and also to pay for spent fuel management and site

restoration activities. Therefore, the NRC staff finds that HDI has provided reasonable

assurance that adequate funds will be available for the radiological decommissioning of PNP,

6 even with the disbursement of funds from the DTF for spent fuel management and site

restoration activities. Consequently, the NRC staff concludes that application of the

requirements of 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv), that funds from the DTF

only be used for radiological decommissioning activities and not for spent fuel management and

site restoration activities, is not necessary to achieve the underlying purpose of the rule. Thus,

special circumstances are present supporting approval of the exemption request.

In its submittal, HDI also requested exemption from the requirement of

10 CFR 50.75(h)(1)(iv) concerning prior written notification to the NRC of withdrawals from

DTFs for activities other than radiological decommissioning. The underlying purpose of

notifying the NRC prior to such withdrawals of funds from DTFs is to provide an opportunity for

NRC intervention, when deemed necessary, if the withdrawals are for expenses other than

those authorized by 10 CFR 50.75(h)(1)(iv) and 10 CFR 50.82(a)(8) that could result in there

being insufficient funds in the DTFs to accomplish radiological decommissioning.

By granting the exemption to 10 CFR 50.75(h)(1)(iv) and 10 CFR 50.82(a)(8)(i)(A), the

NRC staff considers that withdrawals consistent with HDIs submittal dated December 23, 2020,

are authorized. As stated previously, the NRC staff determined that there are sufficient funds in

the DTF to complete radiological decommissioning activities, as well as to conduct spent fuel

management and site restoration activities, consistent with HDIs PSDAR, SSCE, and

December 23, 2020, exemption request. Pursuant to the requirements in 10 CFR 50.82(a)(8)(v)

and (vii), licensees are required to monitor and annua lly report to the NRC the status of the DTF

and the licensees funding for spent fuel management. These reports provide the NRC staff

with awareness of, and the ability to take action on, any actual or potential funding deficiencies.

Additionally, 10 CFR 50.82(a)(8)(vi) requires that the annual financial assurance status report

must include additional financial assurance to cover the estimated cost of completion if the sum

of the balance of any remaining decommissioning funds, plus earnings on such funds calculated

at not greater than a 2-percent real rate of return, together with the amount provided by other

7 financial assurance methods being relied upon, does not cover the estimated cost to complete

the decommissioning. The requested exemption would not allow the withdrawal of funds from

the DTF for any other purpose that is not currently authorized in the regulations without prior

notification to the NRC. Therefore, the granting of the exemption to 10 CFR 50.75(h)(1)(iv) to

allow HDI to make withdrawals from the PNP DTF to cover authorized expenses for spent fuel

management and site restoration activities at PN P without prior written notification to the NRC

will still meet the underlying purpose of the regulation.

Special circumstances, in accordance with 10 CFR 50.12(a)(2)(iii), are present

whenever compliance would result in undue hardship or other costs that are significantly in

excess of those contemplated when the regulati on was adopted, or that are significantly in

excess of those incurred by others similarly situated. HDI states that the DTF contains funds in

excess of the estimated costs of radiological decommissioning and that these excess funds are

needed for spent fuel management and site restor ation activities. The NRC does not preclude

the use of funds from the DTF in excess of those needed for radiological decommissioning for

other purposes, such as for spent fuel management or site restoration activities.

The NRC has stated that funding for spent fuel management and site restoration

activities may be commingled in DTFs, provided that the licensee is able to identify and account

for the radiological decommissioning funds separately from the funds set aside for spent fuel

management and site restoration activities (see NRC Regulatory Issue Summary 2001-07,

Rev. 1, 10 CFR 50.75 Reporting and Recordkeeping for Decommissioning Planning, dated

January 8, 2009 (ADAMS Accession No. ML083440158), and Regulatory Guide 1.184,

Revision 1, Decommissioning of Nuclear Power Reactors, dated October 2013 (ADAMS

Accession No. ML13144A840)). Preventing access to those excess funds in DTFs because

spent fuel management and site restoration activities are not associated with radiological

decommissioning would create an unnecessary financial burden without any corresponding

safety benefit. The adequacy of the PNP DTF to cover the cost of activities associated with

8 spent fuel management and site restoration, in addition to radiological decommissioning, is

supported by the HDI SSCE. If HDI cannot use the PNP DTF for spent fuel management and

site restoration activities, it would need to obtain additional funding that would not be

recoverable from the DTF, or it would have to modify its decommissioning approach and

methods. The NRC staff concludes that either outcome would impose an unnecessary and

undue burden significantly in excess of that contemplated when 10 CFR 50.82(a)(8)(i)(A) and

10 CFR 50.75(h)(1)(iv) were adopted.

The underlying purposes of 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) would

be achieved by allowing HDI to use a portion of the PNP DTF for spent fuel management and

site restoration activities at PNP without prior NRC notification, and compliance with the

regulations would result in an undue hardship or other costs that are significantly in excess of

those contemplated when the regulations were adopted. Thus, the special circumstances in

10 CFR 50.12(a)(2)(ii) and 10 CFR 50.12(a)(2)(iii) exist and support the approval of the

requested exemption.

E. Environmental Considerations

In accordance with 10 CFR 51.31(a), the Commission has determined that granting the

exemption will not have a significant effect on the quality of the human environment (see

Environmental Assessment and Finding of No Significant Impact published in the Federal

Register on November 26, 2021 (86 FR 67503)).

IV. Conclusions.

In consideration of the above, the NRC staff finds that the proposed exemption confirms

the adequacy of funding in the PNP DTF, considering growth, to complete radiological

decommissioning of the site and to terminate the licenses and also to cover estimated spent fuel

management and site restoration activities.

Accordingly, the Commission has determined that, pursuant to 10 CFR 50.12(a), the

exemption is authorized by law, will not present an undue risk to public health and safety, and is

9 consistent with the common defense and security. Also, special circumstances are present.

Therefore, the Commission hereby grants HDI an exemption from the requirements of

10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) to allow the use of a portion of the funds

from the PNP DTF for spent fuel management and site restoration activities at PNP in

accordance with HDIs PSDAR and SSCE, dated December 23, 2020. Additionally, the

Commission hereby grants HDI an exemption from the requirement of 10 CFR 50.75(h)(1)(iv) to

allow such withdrawals without prior NRC notification.

This exemption is effective upon issuance.

Dated: December 13, 2021.

For the Nuclear Regulatory Commission.

Brian D. Wittick, Deputy Director, Division of Operating Reactor Licensing, Office of Nuclear Reactor Regulation.

10