Letter Sequence RAI |
|---|
|
|
MONTHYEARML20344A3862020-12-0707 December 2020 Westinghouse, Submittal of WCAP-18124-NP-A Revision 0 Supplement 1-P and WCAP-18124-NP-A Revision 0 Supplement 1-NP, Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Materials, Revision 0 Project stage: Request ML20344A3882020-12-31031 December 2020 WCAP-18124-NP-A, Revision 0, Supplement 1-NP, Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Materials Project stage: Request ML21015A4212021-01-21021 January 2021 Prop Withholding Determination Form Westinghouse Topical Report WCAP-18124-NP-A, Revision 0, Supplement 1-P and WCAP-18124-NP-A, Revision 0, Supplement 1-NP Project stage: Other ML21015A4232021-01-21021 January 2021 Completeness Determination Form Westinghouse Topical Report WCAP-18124-NP-A, Revision 0, Supplement 1-P and WCAP-18124-NP-A, Revision 0, Supplement 1-NP Project stage: Other ML21165A1792021-06-21021 June 2021 Email Request for Additional Information Westinghouse Topical Report WCAP-18124-NP-A, Rev 0, Suppl 1-P and WCAP-18124-NP-A, Rev 0, Suppl 1-NP, Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Project stage: RAI ML21228A0772021-08-11011 August 2021 Enclosure 3: Westinghouse Responses to NRC Request for Additional Information on WCAP-18124-NP-A, Revision 0, Supplement 1-P/NP, Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Materials (Non-Proprietary) Project stage: Supplement ML21228A0762021-08-11011 August 2021 Submittal of Westinghouse Responses to NRC Request for Additional Information on WCAP-18124-NP-A, Revision 0, Supplement 1-P/NP, Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Materials, EPID: L-2020-TOP Project stage: Supplement ML22014A1052022-02-15015 February 2022 Transmittal Email for Draft SE for Westinghouse Topical Report WCAP-18124-NP-A, Rev. 0, Supplement 1 P and WCAP-18124-NP-A, Rev. 0, Suppl. 1-NP, Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Materials Project stage: Draft Approval ML22091A2312022-04-13013 April 2022 NRC 897 Form Prop Withholding Determination Form Westinghouse Topical Report WCAP-18124-NP-A, Rev. 0, Suppl. 1-P and WCAP-18124-NP-A, Revision 0, Suppl. 1-NP, Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltli Project stage: Other ML22200A0292022-07-21021 July 2022 NRC 896 Form for the U.S. Nuclear Regulatory Commission Staff -A Verification of the Topical Report WCAP-18124-NP-A, Revision 0, Supplement 1-P/NP-A Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Materia Project stage: Other ML22203A0242022-07-25025 July 2022 Withholding Determination NRC 897 Form Westinghouse Electric Company Topical Report WCAP-18124-NP-A, Revision 0, Supplement 1-P/NP-A Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Materials Project stage: Other 2021-08-11
[Table View] |
Text
From:
Lenning, Ekaterina To:
Zozula, Camille T.
Cc:
Smith, James D; Morey, Dennis
Subject:
U.S. NRC Request for additional information (RAI) questions for Topical Report WCAP-18124-NP-A, Rev. 0, Suppl.
1-P and WCAP-18124-NP-A, Rev. 0, Suppl. 1-NP, Fluence Determination with RAPTOR-M3G and FERRET -
Supplement for Extended Beltline Materials" Date:
Monday, June 21, 2021 4:26:00 PM Ms. Camille Zozula Manager, Infrastructure & Facilities Licensing Westinghouse Electric Company Ms. Zozula, I have placed an electronic version of the request for additional information (RAI) questions for Topical Report WCAP-18124-NP-A, Revision 0, Supplement 1-P and WCAP-18124-NP-A, Revision 0, Supplement 1-NP, Fluence Determination with RAPTOR-M3G and FERRET - Supplement for Extended Beltline Materials, in the box.com folder and have given you access to it. This email serves as the formal transmittal of those RAI questions.
The U.S. Nuclear Regulatory Commission (NRC) staff has not redacted any proprietary information from the RAI questions so the file in the Agencywide Documents Access and Management System (ADAMS) and box.com are marked as proprietary. The RAI questions have also been placed in ADAMS as nonpublic so they can be declared an Official Agency Record.
When responding to the RAI questions, please provide a proprietary and nonproprietary version of both the RAI questions and the responses. Your formal response, provided via letter under authorized signature, will generate the public version of the RAI questions as well as the responses.
In order to support the NRC staffs review schedule, please provide your responses no later than August 20, 2021. This date was provided by you.
If you have any questions or would like to discuss the RAI questions with the NRC staff to ensure you understand them, please let me know.
This email will also go in ADAMS and will be declared public.
If you have any questions, please feel free to contact me at 301-415-3151 or by email at Ekaterina.Lenning@nrc.gov.
Sincerely, Ekaterina Lenning Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 99902038