MONTHYEARML20344A3862020-12-0707 December 2020 Westinghouse, Submittal of WCAP-18124-NP-A Revision 0 Supplement 1-P and WCAP-18124-NP-A Revision 0 Supplement 1-NP, Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Materials, Revision 0 Project stage: Request ML20344A3882020-12-31031 December 2020 WCAP-18124-NP-A, Revision 0, Supplement 1-NP, Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Materials Project stage: Request ML21015A4212021-01-21021 January 2021 Prop Withholding Determination Form Westinghouse Topical Report WCAP-18124-NP-A, Revision 0, Supplement 1-P and WCAP-18124-NP-A, Revision 0, Supplement 1-NP Project stage: Other ML21015A4232021-01-21021 January 2021 Completeness Determination Form Westinghouse Topical Report WCAP-18124-NP-A, Revision 0, Supplement 1-P and WCAP-18124-NP-A, Revision 0, Supplement 1-NP Project stage: Other ML21165A1792021-06-21021 June 2021 Email Request for Additional Information Westinghouse Topical Report WCAP-18124-NP-A, Rev 0, Suppl 1-P and WCAP-18124-NP-A, Rev 0, Suppl 1-NP, Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Project stage: RAI ML21228A0772021-08-11011 August 2021 Enclosure 3: Westinghouse Responses to NRC Request for Additional Information on WCAP-18124-NP-A, Revision 0, Supplement 1-P/NP, Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Materials (Non-Proprietary) Project stage: Supplement ML21228A0762021-08-11011 August 2021 Submittal of Westinghouse Responses to NRC Request for Additional Information on WCAP-18124-NP-A, Revision 0, Supplement 1-P/NP, Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Materials, EPID: L-2020-TOP Project stage: Supplement ML22014A1052022-02-15015 February 2022 Transmittal Email for Draft SE for Westinghouse Topical Report WCAP-18124-NP-A, Rev. 0, Supplement 1 P and WCAP-18124-NP-A, Rev. 0, Suppl. 1-NP, Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Materials Project stage: Draft Approval ML22091A2312022-04-13013 April 2022 NRC 897 Form Prop Withholding Determination Form Westinghouse Topical Report WCAP-18124-NP-A, Rev. 0, Suppl. 1-P and WCAP-18124-NP-A, Revision 0, Suppl. 1-NP, Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltli Project stage: Other ML22200A0292022-07-21021 July 2022 NRC 896 Form for the U.S. Nuclear Regulatory Commission Staff -A Verification of the Topical Report WCAP-18124-NP-A, Revision 0, Supplement 1-P/NP-A Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Materia Project stage: Other ML22203A0242022-07-25025 July 2022 Withholding Determination NRC 897 Form Westinghouse Electric Company Topical Report WCAP-18124-NP-A, Revision 0, Supplement 1-P/NP-A Fluence Determination with RAPTOR-M3G and Ferret - Supplement for Extended Beltline Materials Project stage: Other 2021-08-11
[Table View] |
Text
NRC FORM 897 (12-2020)
Topical Report Withholding Determination U.S. NUCLEAR REGULATORY COMMISSION NRC FORM 897 (12-2020)
Page 1 of 1 Topical Report Information Report Number:
WCAP-18124-NP-A Rev. 0 Supplement 1-P
Title:
Fluence Determination with RAPTOR-M3G and FERRET - Supplement for Extended Beltline Materials ADAMS Accession Number:
ML20344A386 EPID:
L-2020-TOP-0063 Docket Number:
99902038 Review Information Office/Division/
Branch:
NRR/DORL/LLPB, NRR/DSS/SFNB Project Manager:
Ekaterina Lenning, NRR/DORL/LLPB Reviewers:
Benjamin Parks, NRR/DSS/SFNB Brandon Wise, NRR/DSS/SFNB Kevin Heller, NRR/DSS/SFNB Staff Withholding Determination
The NRC staff has reviewed your application and the material in accordance with the requirements of 10 CFR 2.390.
Based on the statements in the affidavit, the NRC staff has determined that the submitted information contains proprietary, commercial information and should be withheld from public disclosure.
Therefore, the submitted information marked as proprietary will be withheld from public disclosure under 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.
The NRC staff has reviewed your application and the material in accordance with the requirements of 10 CFR 2.390.
Based on our review, we have concluded that the proprietary request does not comply with the requirements of 10 CFR 2.390. Therefore, the NRC staff is denying the request to withhold the information under 10 CFR 2.390.
ADAMS Accession Numbers (Top row is for transmittal of this form)
Package: ML21015A323 E-mail: ML21015A369 This Form: ML21015A421 Incoming Letter: ML20344A386 Nonproprietary Version: ML20344A388 Basis for Denial:
Approvals Technical Branch Projects Manager Robert Lukes Digitally signed by Robert Lukes Date: 2021.01.21 12:07:58 -05'00' Ekaterina Lenning Digitally signed by Ekaterina Lenning Date: 2021.01.21 12:21:39 -05'00'