Enclosure 3 - NRC Presentation on Nrc'S Crediting FLEX Effort
ML20289A658
Person / Time
Issue date: 10/08/2020
From: Matthew Humberstone
Office of Nuclear Regulatory Research
To:
Kichline M
Shared Package
ML20289A715 List:
References
Download: ML20289A658 (10)


Text

NRCs Crediting FLEX effort Matthew Humberstone, PhD Division of Risk Analysis, Office of Nuclear Regulatory Research 1

Objective

  • Brief History
  • Challenges
  • Completed Tasks
  • Example Areas
  • Questions 2

Project History

  • Fukushima Daiichi Accident (March 2011)
  • NRC Mitigating Strategies (MS) Order (2012)
  • Directed effort to evaluate and provide appropriate credit
  • FLEX can be utilized beyond the orders to enhance safety
  • The NRC wants to encourage safety enhancements
  • Need to provide proper regulatory footprint
  • (outages, defense-in-depth, LARs)
  • 2 Approaches taken
  • NRC evaluated areas of applications 3

FLEX OpE Data

  • FLEX data needed to develop equipment failure probabilities
  • Risk assessments that credit FLEX
  • Collecting data from the industry and developing a report
  • Report to the NRC in Feb 2020
  • NRC audit
  • March 24th - May 4th
  • Commissions PRA policy statement:

PRA evaluations in support of regulatory decisions should be as realistic as practicable and appropriate supporting data should be publicly available for review.

4

HRA challenge for FLEX

  • Current HRA methods not adequate
  • Complex FLEX actions
  • NRCs ongoing effort
  • Finalize IDHEAS - General Methodology
  • Audit Industry FLEX Data
  • Prioritized Industry Support
  • IDHEAS-ECA tool developed
  • Assess range of FLEX cases
  • Incorporated Data into SPAR Models
  • FLEX Scenarios developed (Fall 2019) Task 2
  • Workshop (Dec 2019)
  • 6 HRA experts (3 NRC, 3 Industry)
  • Issue tool and guidance RIL 2020-02
  • FLEX expert support (2 site visits) Task 3
  • Future Tasks
  • Document Workshop results
  • Release draft data report 5

Completed Tasks Review NEI 16-06 (Tier 1, Tier 2, and Tier 3)

  • Internal memo to NRR/DRA Office Director (ML17031A269) (June 2017)

NUMARC 93-01 Revision (Maintenance Rule Scoping criteria)

  • Guidance on modeling FLEX in recovery events IMC-0609 App O - Moved to App A
  • SDP for FLEX findings Rules of Engagement Guidance
  • Tiered Approach to crediting FLEX in risk assessments 6

Completed Tasks Continued SPAR model updates

  • All SPAR models have FLEX capability Working Groups
  • Updating the ROP for FLEX (DRO led)

Communications (Internal and External)

  • Several RISC Meeting Briefings
  • OEDO and RA Briefing
  • Multiple public meetings
  • Several RIC Sessions
  • NEI Risk Forums
  • Conferences
  • MIT Executive Course on risk management Monitoring and Engaging crediting FLEX activities 7

Crediting FLEX examples

  • License Amendment Requests (LARs)
  • Deterministic Applications
  • Risk-Informed Applications
  • Pumps
  • Crediting FLEX is common

Conclusions

  • The NRC is providing credit for FLEX
  • Lots of work has been accomplished
  • Resolving Remaining Challenges
  • Developing a more predictable and consistent approach to crediting FLEX 9

Questions???