ML20260H245

From kanterella
Jump to navigation Jump to search
Topical Report MUAP-07001-NP-A, Revision 7, the Advanced Accumulator, Part 1 of 4
ML20260H245
Person / Time
Site: 05200021
Issue date: 08/31/2020
From:
Mitsubishi Heavy Industries, Ltd
To:
Office of Nuclear Reactor Regulation
Shared Package
ML20260H241 List:
References
UAP-HF-20002 MUAP-07001-NP-A, Rev. 7
Download: ML20260H245 (77)


Text

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

THE ADVANCED ACCUMULATOR Non-Proprietary Version August 2020

© 2020 Mitsubishi Heavy Industries, LTD.

All Rights Reserved Mitsubishi Heavy Industries, LTD.

June 24, 2020 Mr. Takayuki Mori, Engineering Manager Global Nuclear Project Department Mitsubishi Heavy Industries, Ltd.

1-1, Wadasaki-Cho 1-Chome Hyogo-Ku Kobe 652-8585 Japan

SUBJECT:

FINAL SAFETY EVALUATION FOR UNITED STATES - ADVANCED PRESSURIZED WATER REACTOR ADVANCED TOPICAL REPORT SAFETY EVALUATION FOR TOPICAL REPORT MUAP-07001-NP, REVISION 7, THE ADVANCED ACCUMULATOR

Dear Mr. Mori:

In a May 2018 submittal (Agencywide Documents Access and Managemement System (ADAMS) Accession No. ML18178A258), Mitsubishi Heavy Industries, Ltd. (MHI), submitted Revision 7 to Topical Report MUAP-07001-NP, The Advanced Accumulator. By letter dated July 29, 2019 (ADAMS Accession No. ML19154A122), the U.S. Nuclear Regulatory Commission (NRC) staff sent you a safety evaluation (SE) with no open items for Topical Report MUAP-07001-NP, Revision 7. The proprietary version of this SE was sent to the Advisory Committee on Reactor Safeguards (ACRS) Subcommittee in advance of a September 19, 2019, meeting.

Following the September 19, 2019, Subcommittee meeting, the ACRS Full Committee meeting discussed the SE for this topical report in their November 6 - 8, 2019, meeting and found the NRC staffs safety findings to be acceptable. Subsequent to the ACRS Full Committee meeting, the ACRS issued a letter dated November 26, 2019 (ADAMS Accession No. ML19331A036), in which they recommended, in part, that the NRC staff issue the SE.

In accordance with the guidance provided on the NRCs TR Web site (http://www.nrc.gov/about-nrc/regulatory/licensing/topical-reports.html), the staff requests that MHI publish an accepted version of this TR within three months of receipt of this letter. The accepted version shall incorporate this letter and the enclosed SE between the title page and the abstract. It must be well indexed such that information is readily located. Also, it must contain in its appendices historical review information such as questions and accepted responses as well as original report pages that were replaced. The accepted version shall include an "-A" (designated accepted) following the report identification symbol.

T. Mori If the NRCs criteria or regulations change so that its conclusion in this letter (that the TR is acceptable) is invalidated, MHI and/or the applicant referencing the TR will be expected to revise and resubmit its respective documentation or submit justification for the continued applicability of the TR without revision of the respective documentation.

Should you have any questions, please do not hesitate to call. I can be reached at 1+301-415-1494 or via electronic mail at George.Wunder@nrc.gov.

Sincerely,

/RA/

George F. Wunder, Senior Project Manager New Reactor Licenising Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket No.: 52-021

Enclosure:

As stated cc w/o encl.: See next page

PKG: ML20055F683 LETTER: ML20055F976 SER: ML20055F978 *via e-mail NRR-106 OFFICE NRR/DNRL/NRLB: PM NRR/DNRL/NRLB: LA NRR/DNRL/NRLB: BC NAME GWunder CSmith MDudek DATE 02/24/2020 02/25/2020 06/15/2020 OFFICE NRR/DNRL/NRLB: PM NAME GWunder (signed)

DATE 06/24/2020 DC Mitsubishi - US APWR Mailing List w/o Enclosure Email acpasswater@aol.com (Al Passwater)

APH@NEI.org (Adrian Heymer) atsushi_kumaki@mhi.co.jp (Atsushi Kumaki) awc@nei.org (Anne W. Cottingham) bgattoni@roe.com (William (Bill) Gattoni))

CumminWE@Westinghouse.com (Edward W. Cummins) cwaltman@roe.com (C. Waltman) david.hinds@ge.com (David Hinds) david.lewis@pillsburylaw.com (David Lewis)

DeLaBarreR@state.gov (R. DeLaBarre) donald.woodlan@luminant.com (Donald Woodlan) eliza.seedcoalition@gmail.com (Elza Brown) erg-xl@cox.net (Eddie R. Grant) erin_wisler@mnes-us.com (Erin Wisler) ewallace@nuscalepower.com (Ed Wallace) gcesare@enercon.com (Guy Cesare) hiroki_nishio@mhi.co.jp (Hiroki Nishio) james1.beard@ge.com (James Beard) jerald.head@ge.com (Jerald G. Head)

Joseph_Hegner@dom.com (Joseph Hegner) joseph_tapia@mnes-us.com (Joseph Tapia) jrappe@nuscalepower.com (Jodi Rappe) jrund@morganlewis.com (Jonathan Rund) karlg@att.net (Karl Gross) kevin_lynn@mnes-us.com (Kevin Lynn)

KSutton@morganlewis.com (Kathryn M. Sutton) kwaugh@impact-net.org (Kenneth O. Waugh) lchandler@morganlewis.com (Lawrence J. Chandler) lon.burnam@house.state.tx.us (Lon Burnam) m.goto@mnes_us.com maria.webb@pillsburylaw.com (Maria Webb) mark.a.giles@dom.com (Mark Giles) masanori_onozuka@mnes-us.com (Masanori Onozuka) masatoshi_nagai@mnes-us.com (Masatoshi Nagai) matias.travieso-diaz@pillsburylaw.com (Matias Travieso-Diaz) media@nei.org (Scott Peterson) michael_melton@mnes-us.com (Michael Melton)

MSF@nei.org (Marvin Fertel) nirsnet@nirs.org (Michael Mariotte)

Nuclaw@mindspring.com (Robert Temple) patriciaL.campbell@ge.com (Patricia L. Campbell) paul.gaukler@pillsburylaw.com (Paul Gaukler)

Paul@beyondnuclear.org (Paul Gunter)

Page 1 of 2

DC Mitsubishi - US APWR Mailing List pbessette@morganlewis.com (Paul Bessette) plarimore@talisman-intl.com (Patty Larimore) rebecca_steinman@mnes-us.com (Rebecca Steinman)

RJB@NEI.org (Russell Bell) ryan_sprengel@mnes-us.com (Ryan Sprengel) sabinski@suddenlink.net (Steve A. Bennett) sfrantz@morganlewis.com (Stephen P. Frantz) stephan.moen@ge.com (Stephan Moen) strambgb@westinghouse.com (George Stramback)

Tansel.Selekler@nuclear.energy.gov (Tansel Selekler) tgilder1@luminant.com (Tim Gilder) tmatthews@morganlewis.com (T. Matthews) tom.miller@hq.doe.gov (Tom Miller)

Tony.Robinson@areva.com (Tony Robinson) trsmith@winston.com (Tyson Smith)

Vanessa.quinn@dhs.gov (Vanessa Quinn) vijukrp@westinghouse.com (Ronald P. Vijuk)

Wanda.K.Marshall@dom.com (Wanda K. Marshall) whorin@winston.com (W. Horin) yoshiki_ogata@mhi.co.jp (Yoshiki Ogata)

Page 2 of 2

OFFICIAL USE ONLY - PROPRIETARY INFORMATION DRAFT SAFETY EVALUATION BY THE OFFICE OF NEW REACTORS TOPICAL REPORT MUAP-07001, REVISION 7 THE ADVANCED ACCUMULATOR MITSUBISHI HEAVY INDUSTRIES, Ltd DOCKET NO.52-021 Table of Contents

1.0 INTRODUCTION

............................................................................................................... 2

2.0 REGULATORY EVALUATION

.......................................................................................... 3

3.0 TECHNICAL EVALUATION

.............................................................................................. 4 3.1 Evaluation of Accumulator Performance ........................................................................ 7 3.1.1 Principle of Flow Damper ........................................................................................ 9 3.1.2 Performance of Anti-Vortex Cap ............................................................................. 9 3.1.3 Water Level Transient in Standpipe during Flow Switching .................................... 9 3.1.4 Performance of Flow Damper during Large Flow and Small Flow Phases ........... 10 3.1.5 Water Level at Flow Switching .............................................................................. 10 3.1.6 Effect of Dissolved Nitrogen .................................................................................. 11 3.2 Characteristics Equations for Advanced Accumulator (ACC) ....................................... 12 3.3 Uncertainty in ACC Characteristic Equations ............................................................... 14 3.3.1 Experimental Uncertainty in Characteristic Equations........................................... 14 3.3.1.1 Estimate of Experimental Uncertainty ............................................................ 14 3.3.1.2 Combining Uncertainties ................................................................................ 17 3.3.2 Uncertainty in Switching Level .............................................................................. 17 3.3.3 Uncertainty due to Dissolved Nitrogen Effect ........................................................ 18 3.4 Pre-Operational Test of Accumulator Performance ...................................................... 19 4.0

SUMMARY

OF EVALUATION ........................................................................................ 19

5.0 REFERENCES

................................................................................................................ 21 6.0 LIST OF ACRONYMS ..................................................................................................... 22 OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

1.0 INTRODUCTION

In support of the application for the design certification (DC) for the United States - Advanced Pressurized Water Reactor (US-APWR), Mitsubishi Heavy Industries, Ltd. (MHI), hereinafter referred to as the applicant, submitted Topical Report MUAP-07001-P, Revision 7, The Advanced Accumulator (ML18178A267). The US-APWR design uses advanced accumulators (ACC) as a part of the emergency core cooling system (ECCS) design. The US-APWR ACC design is built on the operating experience of a conventional accumulator used for mitigating the consequences of loss-of-coolant accidents (LOCAs) in pressurized water reactors (PWR).

Similar to the conventional accumulators used in the operating PWR plants, the ACC is an accumulator tank partially filled with borated water and pressurized with nitrogen. The ACC is attached to the primary system with a series of check valves and an isolation valve and is aligned during operation to allow flow into the primary coolant system if the primary system pressure drops below the pressure of the accumulator. The US-APWR ACC design differs from the conventional accumulators in that it incorporates a flow damper in the accumulator tank to provide a passive flow control. The flow damper is an inherently reliable passive fluidic device to achieve a desired reactor coolant injection flow profile without the need for any moving parts.

Emergency core cooling during a LOCA is one of the primary functions of the ECCS. In a conventional PWR, the ECCS consists of accumulators, high-head safety injection system (SIS), and low-head SIS to accomplish these ECCS functions. During a large break LOCA (LBLOCA), the fuel cladding temperature increases due to a lack of liquid in and around the core. An LBLOCA generally includes blowdown, refill, reflood, and long-term cooling phases.

After the initial blowdown, the ECCS is required to inject water into the core to limit the rise of fuel temperature in three steps. In the refill phase, the accumulators quickly inject water at a high flow rate to fill the lower plenum and downcomer of the reactor vessel. Subsequently, the core is reflooded by the water head in the downcomer, and the high-head and low-head SIS inject flow to keep high water level in the downcomer to reflood the core. In the long-term cooling phase after core reflood is completed, the low-head injection system provides water to remove decay heat and maintain the core in a flooded state.

As described in more detail in the technical evaluation section of this report, in the US-APWR ECCS design, the ACC switches its flow rate from large-flow injection to small-flow injection automatically and passively after the ACC injection reduces the water level in the tank below the top entrance of the large-flow standpipe. According to the applicant, the combination of the ACC and the high-head injection system performs the function of the low-head injection system in the reflood and long-term cooling phases, and therefore, eliminates the need for the low-head injection system. Also, during an LBLOCA, it is necessary to start the ECCS pumps prior to the end of accumulator injection to the reactor vessel. The ACC injects water longer than a conventional accumulator, thereby allowing more time to start the ECCS pumps. The applicant asserts that this will allow the US-APWR to use gas turbine generators as opposed to the emergency diesel generators.

The ACC design simplifies the ECCS design by the elimination of low-head safety injection (SI) pumps and increases the amount of time available to start backup emergency power system.

The applicant expects that the use of ACCs rather than the low-head SI pumps in the US-APWR design will reduce the net maintenance and testing workload at nuclear facilities.

OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION Topical Report MUAP-07001-P, Revision 7, describes the ACC design, the principles of operation and important design features of the ACC, the empirical characteristic correlations of the ACC, and experimental programs to prove the concept and develop the correlations. The application indicates that the flow characteristics of the ACC have been verified by a full-scale qualification testing and can be fully described as a function of dimensionless numbers.

Empirical flow rate coefficients have been developed from the test results and will be used in an integrated thermal hydraulic model of the US-APWR Reactor Coolant and ECCS systems to assure the US-APWR meets or exceeds all regulatory requirements.

2.0 REGULATORY EVALUATION

The staffs review of MUAP-07001-P, Revision 7, evaluates the applicants compliance with the following regulatory requirements:

  • General Design Criterion (GDC) 35, Emergency core cooling, in Appendix A to Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Domestic Licensing of Production and Utilization Facilities, as it relates to the requirement for a system to provide abundant emergency core cooling to satisfy the ECCS safety function of transferring heat from the reactor core following any loss of reactor coolant at a rate such that (1) fuel and clad damage that could interfere with continued effective core cooling is prevented, and (2) clad metal-water reaction is limited to negligible amounts.
  • Section 50.46 (10 CFR 50.46), Acceptance criteria for emergency core cooling systems for light-water nuclear power reactors, as it relates to the requirement for an ECCS designed with a calculated cooling performance for a spectrum of postulated piping breaks within the reactor coolant pressure boundary to assure that cooling performance for the most severe postulated LOCAs is calculated. The ECCS cooling performance following postulated LOCAs must be calculated in accordance with an acceptable evaluation model to demonstrate conformance to the following acceptance criteria set forth in 10 CFR 50.46(b):
  • The calculated maximum fuel element cladding temperature does not exceed 1200 oC (2200 oF).
  • The calculated total local oxidation of the cladding does not exceed 17 percent of the total cladding thickness before oxidation.
  • The calculated total amount of hydrogen generated from the chemical reaction of the cladding with water or steam does not exceed one percent of the hypothetical amount that would be generated if all of the metal in the cladding cylinders surrounding the fuel, excluding the cladding surrounding the plenum volume, were to react.
  • Calculated changes in core geometry are such that the core remains amenable to cooling.

OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

  • After any calculated successful initial operation of the ECCS, the calculated core temperature is maintained at an acceptably low value and decay heat is removed for the extended period of time required by the long-lived radioactivity remaining in the core.
  • Section 50.46 (10 CFR 50.46(a)(1)(i)) also requires that for the realistic analysis of the ECCS cooling performance, the uncertainties in the analysis method and input must be identified and assessed so that the uncertainty in the calculated results can be estimated and accounted.

The US-APWR ECCS design, including the ACCs, must comply with GDC 35, and the cooling performance will be evaluated through the safety analyses of LOCAs for the full spectrum of break sizes (including LBLOCA and small-break LOCA (SBLOCA)) to demonstrate that the above acceptance criteria are met.

The staffs evaluation of the ACC topical report includes the evaluation of the ACC characteristic equations and uncertainties and applicability of the characteristic equations to US-APWR as part of the LOCA evaluation models for the calculation of the US-APWR ECCS capability, as required by 10 CFR 50.46 and GDC 35.

3.0 TECHNICAL EVALUATION

The US-APWR ECCS system configuration includes four ACCs connected to the reactor coolant system (RCS) cold legs. In addition, four high head injection subsystems inject directly into the reactor vessel downcomer following accumulator injection.

The ACC topical report describes the system as consisting of a tank partially filled with borated water and pressurized with nitrogen, and a flow damper inside the tank. The flow damper consists of a vortex chamber located near the bottom of the accumulator tank, a standpipe connected to a large-flow pipe attached radially to the vortex chamber, a side entry small-flow pipe tangentially connected to the vortex chamber, and a reducer-diffuser nozzle connected to the outlet port of the vortex chamber and the injection pipe. A pressure equalizing pipe is connected across the vortex chamber. The standpipe and the small flow inlet pipe also include anti-vortex caps. The configuration and operation principle of the ACC design is shown in Figure 2.2.1-1, Principle of Advanced Accumulator Operation, and the detailed structure of the flow damper is shown in Figure 3.3-1, Overview of the Flow Damper, of the Topical Report MUAP-07001-P, Revision 6, Agencywide Document Access and Management System (ADAMS) Accession No. ML17040A160. The staff noted an inconsistency in the description of the outlet piping on Page 3-3 of the topical report and Figure 3.2-1 and requested the applicant to clarify the location of the outlet piping in its request for additional information (RAI) 9305, Question No. 1. In its response to RAI 9305, Question No.1, dated February 1, 2018 (ML18037A649), the applicant corrected the location description of the outlet piping relative to the flow damper. The staff finds the above response acceptable because the revised description is consistent with Figure 3.2-1 and based on this response, RAI 9305, Question No.

1 was previously tracked as a Confirmatory Item. The staff verified that the markups have been incorporated into Revision 7 of the topical report. Therefore, the staff considers RAI 9305, Question No. 1, resolved and closed.

OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION If a LOCA occurs and pressure in the reactor vessel decreases below the ACC pressure, the check valves in the injection pipe open to permit the injection of the ACC cooling water into the reactor vessel. With the initial water level in the accumulator tank higher than the elevation of the inlet of the standpipe, water flows into the vortex chamber through both the large-flow rate and small-flow rate pipes. These flows collide with each other at a design facing angle between the large flow and small flow inlet pipes at the vortex chamber to cancel angular momentum.

This prevents vortex formation in the vortex chamber as the staff observed in a video of the test as described in more detail below. The ACC topical report indicates that the equalizing pipe is provided to ensure prevention of vortex formation during large flow injection. Consequently, the flow resistance in the vortex chamber is small, resulting in a large flow rate. The flow through the flow damper is essentially the usual pipe flow without a strong vortex. The flow through the outlet nozzle dominantly experiences a pressure reduction in the reducer and a pressure recovery in the diffuser. The throat of the outlet nozzle is the critical section to determine the ACC flow rate.

The staff noted that Table 3.3-1, provides the bases for all flow damper dimensions, except for the equalizing pipe. In RAI 9305, Question No. 3, the staff requested the applicant to provide the dimensions of the equalizing pipe and its basis. In response to RAI 9305, Question No. 3 dated February 1, 2018 (ML18037A649), the applicant stated that the purpose of the equalizing pipe is to equalize the pressure across the vortex chamber during large flow injection. The pipe size was selected to efficiently accomplish this, by canceling any pressure differential across the vortex chamber and this was demonstrated during full scale testing. The applicant proposed to revise the topical report to add the equalizing pipe dimension and the basis for the selection in Table 3.3-1, The Basis for the Flow Damper Dimension. The staff finds the above response and the revision to the topical report acceptable because it provides a complete list of all flow damper dimensions, including the equalizing pipe and based on this response, RAI 9305, Question No. 3, was previously tracked as a Confirmatory Item. The staff verified that the markups have been incorporated into Revision 7 of the topical report. Therefore, the staff considers RAI 9305, Question No. 3, resolved and closed.

The large-flow injection phase continues until the water level in the accumulator tank falls below the inlet level of the standpipe, and the flow in the standpipe almost comes to a stop. The flow from the small-flow pipe enters the vortex chamber tangentially, which creates a strong vortex in the vortex chamber. The vortex flow in the chamber creates a large pressure drop, and therefore, results in a small-flow injection rate. The switching from the large-flow to small-flow injection phase is thus accomplished passively without any moving parts. The topical report stated that [t]he equalizing pipe is provided to ensure prevention of a vortex formation during large flow injection. In RAI 9305, Question No. 2, the staff requested the applicant to discuss the effect of the equalizing pipe during small flow where the vortex formation is needed to achieve the desired flow rate. In its response to RAI 9305, Question No. 2, dated February 1, 2018 (ML18037A649), the applicant stated that the pressure difference between the points where equalizing pipe is attached is insignificant since these points are on the same circumference. Therefore, flow characteristics during small flow injection are not affected by the equalizing pipe since vortex formation is not interrupted. The flow in this short cylindrical vortex chamber depends on the intensity of the incoming tangential velocity and it is not impacted.

This flow behavior was confirmed during full-scale qualification testing when the acceptance OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION criterion for small flow injection was satisfied. The applicant proposed to revise the topical report to address the effect of the equalizing pipe during small flow injection consistent with its response. The staff finds the above response and the revision to the topical report acceptable because the design and qualification testing demonstrated that the equalizing pipe does not affect small flow injection and based on this response, RAI 9305, Question No. 2, was previously tracked as a Confirmatory Item. The staff verified that the markups have been incorporated into Revision 7 of the topical report. Therefore, the staff considers RAI 9305, Question No. 2, resolved and closed.

The US-APWR ACC is designed with two performance objectives: (1) immediately after the reactor coolant blowdown during an LBLOCA, the ACC injects water at a large flow rate for a limited duration to refill the reactor vessel lower plenum and downcomer, and (2) after the refill period, it injects water at a relatively small flow rate to establish the core reflooding condition by maintaining the downcomer water level. To achieve these performance objectives, Section 2.3.4, Design Requirements for the ACC, of the report describes the determination of the design parameters for the large flow and small flow injection phases, respectively, based on an LBLOCA sensitivity analysis. The water volume above the top of the standpipe in the ACC is the large flow injection water volume needed to refill the reactor vessel lower plenum and downcomer during the refill phase of a LOCA. The injection flow rates for the large-flow and small-flow injection phases, respectively, are to refill the lower plenum and downcomer as rapidly as possible and to provide sufficient reflood rate to assure the peak cladding temperature is within the acceptance criteria during the worst case LOCA.

The flow resistance coefficient of the ACC injection flow path for the large flow phase is calculated based on the refill injection rate, the ACC pressure, and the characteristics of the RCS depressurization transient. The application used the flow rate ratio at the point the flow regime switches from large flow to small flow to determine the ratio of the flow resistance coefficients of the total ACC system injection line during the large-flow and small-flow injection phases. The flow damper flow resistance coefficients for the large-flow and small-flow phases, respectively, are obtained by subtracting the injection pipe resistance coefficient from the corresponding total ACC system injection line resistance coefficients. In the application, the ratio of the flow damper flow resistance coefficient for the small flow injection to the large flow injection is calculated to be The application indicates further that the small flow injection water volume is determined based on the need for the duration of small flow injection from the ACC, followed by the injection from the SI pump, in the reflood phase to maintain the downcomer water level through the core quench. In all, the LBLOCA sensitivity study establishes the target flow damper flow resistance coefficients, and water injection volumes for the large-flow and small-flow injection phases, respectively. The design specifications of the ACC as summarized in Table 3.1-1, Specifications for the ACC, of the topical report include additional margins from the results of the sensitivity analysis. Section 3.1, ACC Design Basis and Specifications, of the topical report presents the detailed design of the as installed ACC with the structure of the flow damper depicted in Figure 3.3-1, Overview of the Flow Damper, and Figure 3.3-2, Outline Drawing of the Flow Damper, of the topical report.

Although the ACC topical report does not include the Chapter 15 accident analysis, it should be noted that the LBLOCA sensitivity analysis used in establishing the ACC design requirements OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION was performed using the 10 CFR Part 50, Appendix K, ECCS Evaluation Models, with the Japanese decay heat model. The decay heat level of the Japanese model is different from that of the American Nuclear Society (ANS) 1971 decay heat model required in the Appendix K model, and therefore the core reflood rate would be different from the results if the ANS-1971 decay heat model was used. However, the sensitivity analysis was performed solely for the purpose of establishing the values of the ACC design parameters. There are margins added to the final design specifications of the ACC. The applicants analysis of the ECCS acceptance criteria is presented in the LOCA safety analyses described in US-APWR Design Control Document (DCD) Section 15.6.5, Loss-of-Coolant Accidents Resulting from Spectrum of Postulated Piping Breaks within the Reactor Coolant Pressure Boundary. The adequacy of the credited injection flow rate will ultimately be confirmed by the ECCS performance analysis using the WCOBRA/TRAC code with ASTRUM methodology for the LBLOCA, and the M-RELAP5 code with the Appendix K requirements, including the ANS-1971 decay heat model, for the SBLOCA. The applicant used the Japanese decay heat model in the LOCA sensitivity analysis solely to establish the ACC design parameters. Since the Japanese decay heat model was not used in the safety analysis in the US-APWR DCD, its use in the sensitivity analysis is acceptable.

3.1 Evaluation of Accumulator Performance The applicant conducted three types of scaled tests: 1/8.4, 1/3.5 and 1/5-scale model tests.

These tests used visualization to confirm flow rate switching, vortex formation, and the prevention of significant gas entrainment into the vortex chamber at the end of the large flow stage of injection. The injection test provides the performance data needed for quantitative evaluation of ACC flow. The applicant verified the flow characteristics of the ACC by full-scale qualification testing, and these flow characteristics can be fully described as a function of dimensionless numbers. The applicant developed empirical flow rate coefficients from the test results and these coefficients will be used in an integrated thermal hydraulic model of the US-APWR Reactor Coolant and ECCS systems to assure the US-APWR meets or exceeds all US safety standards. The full-scale qualification test included a modification to the flow damper that installed a pressure equalizing pipe across the vortex chamber. The details of the test objectives, test apparatus, and test results for these tests are described in Section 4, Testing Program for the ACC, of the topical report.

The 1/8.4 scale tests were flow visualization tests conducted to examine the basis of operation of the ACC and to understand the injection flow characteristics. The tests confirmed the basic operational characteristics of the flow damper in the ACC, and showed the flow switching from the large flow injection to small flow injection. The vortex chamber for this test was in an upright position, compared to a horizontal vortex chamber in the actual design. Since the sole purpose of the test was to demonstrate vortex cancellation and flow switching, the test configuration does not affect the results.

The 1/3.5 scale tests were visualization tests conducted to confirm that the anti-vortex cap at the top of the standpipe prevents vortex formation at the standpipe inlet and promotes quick and smooth flow switching at the end of the large-flow injection. For the test, the anti-vortex cap that is at the top of the standpipe was made of transparent acrylate such that the flow can be observed at the standpipe inlet.

OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION The 1/5 scale visualization tests were conducted to confirm the operational characteristics of the flow damper by observing the flow in the flow damper during large-flow injection, flow switching, and small-flow injection. The flow damper with a wall made of transparent acrylic resin was installed outside the test tank. The flow in the vortex chamber was recorded with a video camera. The characteristics in the vortex chamber were observed using blue ink as a flow tracer. The 1/5 scale test was not repeated with the modified flow damper, which included a pressure equalizing pipe across the vortex chamber. In RAI 9305, Question No.4, the staff requested the applicant to discuss the basis for not repeating the confirmatory test with a modified vortex chamber with flow equalizer piping. In its response to RAI 9305, Question No. 4, dated February 1, 2018 (ML18037A649), the applicant stated that confirmatory tests were performed during the development phase to observe the operational principles and function of each targeted part. The applicant indicated that the operational principle of the equalizing pipe is simply to equalize pressure across the vortex chamber. The applicant also indicated that the equalizing pipe does not affect any operational function such as direct flow to the outlet during large flow injection, sharp flow switching, and strong vortex formation during small flow injection. Therefore, the applicant concludes that confirmatory testing with a modified vortex chamber was not necessary. The applicant proposed to revise the topical report by adding a description of the equalizing pipe and the basis for not repeating the confirmatory test with a modified vortex chamber. The staff finds the above response and the revision to the topical report acceptable because it clarifies that the equalizing pipe does not affect any operational function and based on this response, RAI 9305, Question No. 4, was previously tracked as a Confirmatory Item. The staff verified that the markups have been incorporated into Revision 7 of the topical report. Therefore, the staff considers RAI 9305, Question No. 4, resolved and closed. Additionally, in its responses to RAI 9305, Question Nos. 5, 6, and 7, dated February 1, 2018 (ML18037A649), the applicant addressed the staffs observation of various changes in Revision 6 of the topical report, and proposed an appendix to explain the updates from topical report Revision 5 to Revision 6. The staff finds the above responses and the revision to the topical acceptable in clarifying the changes in the latest revision of the topical report and based on this response, RAI 9305, Question Nos. 5, 6, and 7, were tracked as Confirmatory Items. The staff verified the markups have been incorporated into Revision 7 of the topical report. Therefore, the staff considers RAI 9305, Question Nos. 5, 6, and 7, resolved and closed.

In addition, the applicant conducted a qualification test using a full-scale test facility to verify the following items:

1. ACC performance during large flow and small flow phases,
2. Flow switching in the ACC without need of any moving parts, and
3. The effect of dissolved nitrogen gas on the performance of the ACC.

The staff observes that the three-small scale confirmatory tests described above measure separate effects that are not affected by the scale of the tests. Accordingly, the staff finds that these tests are adequate for their intended purposes, which the staff evaluates below. For the tests where the validity of the results depends on scale, the applicant used a full-scale facility, and the staff therefore finds that there were no scaling effects on the test results.

OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION 3.1.1 Principle of Flow Damper The flow damper is designed to act as a diode where flow decreases rapidly as the water level in the tank decreases below the standpipe entrance, leading to a vortex formation in the vortex chamber. The applicant performed tests at three scales, i.e., 1/8.4, 1/3.5 and 1/5, to demonstrate the intended operation.

As described in the topical report, the results of these tests showed that a vortex is not formed when the tank water level is above the standpipe. When the water level in the tank falls below the inlet of the standpipe, a vortex is formed in the vortex chamber, leading to a large pressure drop in the vortex chamber and a rapid decrease of flow rate. This is the intended characteristic of the ACC and the staff finds that these tests support the principle of passive flow switching from a large flow rate to a small flow rate.

3.1.2 Performance of Anti-Vortex Cap An anti-vortex cap is installed at the entrance of the standpipe, as shown in Figure 3.3-1, Overview of the Flow Damper, of the topical report. The purpose of the anti-vortex cap is to prevent any ingress of nitrogen from the top of the tank into standpipe. Without an anti-vortex cap at the entrance, it is possible to have vortex formation near the standpipe entrance where nitrogen can be entrained as the level in the tank decreases. The anti-vortex cap will prevent this mechanism. There is another anti-vortex cap at the inlet of the small flow pipe, which is connected to the vortex chamber near the bottom of the ACC. However, by the time the water level approaches the level of the small flow pipe inlet, the ACC water is close to the dead volume, and the high head SI provides needed ECCS flow. Therefore, the effectiveness of the anti-vortex cap at the small flow entrance is not of particular interest.

The results of the tests at three test scales, 1/8.4, 1/3.5 and 1/5 scales, respectively, showed the effectiveness of the anti-vortex cap in preventing ingress of nitrogen through the standpipe.

The 1/3.5 scale test results showed that in the case of the standpipe inlet without an anti-vortex cap, there was a creation of vortex at the standpipe entrance as the water level decreased to the standpipe entrance, and subsequent entrainment of nitrogen as the water level further decreased. In the case of standpipe with the anti-vortex cap, a slight disturbance appeared on the water surface as the water level decreased from just above the upper end of the cap to the lower end of the cap. However, no vortex occurred, and the flow rate switched from high to low much more quickly than the case without the anti-vortex cap.

3.1.3 Water Level Transient in Standpipe during Flow Switching During the switching of flow from the large-flow to the small-flow injection phase, the water level in the standpipe undergoes a transient due to inertial effects. Water level goes down and then recovers. If the level goes down too much, there is a possibility of entrainment of nitrogen from the standpipe to the vortex chamber. The staff reviewed the data from the full-scale test and confirmed that when the test tank water level was reduced to the flow switching level, the standpipe water level temporarily dropped, recovered, and then continued to drop gradually during the small flow injection period but remained high enough to preclude any entrainment of OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION nitrogen into the vortex chamber. (Refer to MUAP-07001-P, Revision 7, Fig. 4.2.2-3(1/2) Full Scale Test Results (Case 1) (1/2)).

3.1.4 Performance of Flow Damper during Large Flow and Small Flow Phases During a LOCA, there is initially large flow injection from the accumulator when the check valve in the injection pipe opens in response to the fall of the RCS pressure below the accumulator pressure. The flow decreases as the water level in the accumulator tank decreases and the level reaches near the entrance to the standpipe. In the large flow injection phase, the flow is the combination of flow from the standpipe and the flow from the small-flow side entry. The net flow is radial in the vortex chamber, and there is no vortex so that the flow resistance is small.

As the flow in the standpipe decreases, there is vortex formation in the vortex chamber with a large increase in flow resistance and correspondingly lower flow. This small-flow phase is equivalent to operation of the low head injection pump in the ECCS of a conventional PWR.

The safety analysis credits the ACC design with a large flow injection phase for approximately of operation, and then an order of magnitude less flow in the small-flow phase. The head losses in the small-flow phase should be about a factor of (as discussed in Section 3.0, Technical Evaluation, of this report) greater than in the large-flow phase.

The applicant used the full-scale tests to confirm that the flow magnitude and timing of switching between the large flow and the small flow credited in the safety analysis can be achieved. A total of seven test cases were conducted with various test accumulator tank pressures and exhaust tank pressures. The staff verified that that test conditions, including the injection pipe resistance, initial water level in the accumulator tank, and the initial accumulator pressure are comparable to the actual plant values. However, Test Case 7 was a low-pressure test for anticipated preoperational test conditions. Test Case 5 was conducted with water saturated with nitrogen to evaluate the effect of dissolved nitrogen gas. During the tests, the applicant measured the water levels in the tank and the standpipe; pressures in the accumulator, injection pipe, and exhaust tank; and water temperatures in the test tank. The applicant used these data, excluding data from Test Cases 5 and 7, to develop the flow characteristic equations.

The applicant used commonly accepted statistical methods to develop the characteristic equations from the test data, specifically, the least squares fit method. The staff finds that application of the least squares fit method to the data is an appropriate use of that method, and accordingly, the characteristic equations are acceptable. The staffs evaluation of the applicants treatment of uncertainty is in Section 3.3 of this safety evaluation (SE).

3.1.5 Water Level at Flow Switching The ACC is designed such that the flow switching from the large-flow rate to the small-flow rate takes place when the water level drops to the lower end of the anti-vortex cap at the entrance of the standpipe. For the full-scale tests, the applicant plotted the accumulator flow rates and the accumulator water level for each test as a function of time. The water level at the switching of flow rates from large-flow to small-flow was defined as the intersecting point of two curves of water levels for large flow injection and small flow injection. As shown in Table 4.2.2-2, Flow Switching Water Level, of the topical report, the data from the full-scale tests showed that the water level for the flow rate switching is within a small range of uncertainty of OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION from the expected flow-switching water level at the lower end of the anti-vortex cap installed at the inlet of the standpipe. In view of the above, the staff concludes that flow switching occurs as predicted within the measured uncertainties. The uncertainty in the switching level and its treatment in the safety analysis are described in Section 5.2, Estimation of Potential Uncertainties of Water Level for Switching Flow Rates, of the topical report and in Section 3.3.2, Uncertainty in Switching Level, of this report.

3.1.6 Effect of Dissolved Nitrogen Fluid in the accumulator is in contact with nitrogen and, over time, nitrogen will dissolve into and diffuse throughout the liquid phase. In the limiting case, water could be saturated with nitrogen and there could be equilibrium between gas phase and liquid phase. There could be a potential impact of dissolved gas on the performance of the flow damper. As the fluid particles move through the flow damper, subject to decreasing pressure, the dissolved nitrogen gases will emerge and potentially affect the flow resistance of the flow damper.

To evaluate the effect of dissolved nitrogen gas in the accumulator water, the applicant conducted a test (Test Case 5) with nitrogen-saturated water in the full-scale facility. In Test Case 5, water in the ACC tank was forced to be saturated with nitrogen by compulsorily bubbling and showering with nitrogen. The applicant conducted this nitrogen-saturated water test case with boundary conditions similar to those of Test Case 1, in which nitrogen gas was passively charged so that it was not in equilibrium. A comparison of the test results between Test Cases 1 and 5, as shown in Figure 4.2.2-7 of the topical report, showed lower cavitation factor and flow coefficient for the large flow phase and a delay of approximately in the switchover from the large-flow rate to small-flow rate phase for Test Case 5. Lower flow coefficient, or higher flow resistance, during the large flow injection phase due to the effect of the dissolved nitrogen resulted in a lower accumulator flow rate, and a longer period of the large flow injection phase.

The applicant did not consider the flow coefficient data points from Test Case 5 in developing the accumulator characteristic equations as documented in Section 5.1, Flow Rate Characteristics for Safety Analysis, of the topical report. This is because the test condition in Test Case 5 with saturated nitrogen is much more limiting than the actual conditions in the accumulators, and therefore, using the Test Case 5 data will result in evaluating a flow coefficient smaller than that of the actual accumulator. Rather, the Test Case 5 result of a delay of flow rate switching was used to address the effect of the dissolved nitrogen. As discussed in Section 3.3.3 of this report, the applicant will incorporate an increase in the accumulator injection pipe flow resistance coefficient in the LOCA analyses.

3.1.7 Summary Based on the foregoing, the staff finds that the three sets of different scaled confirmatory tests and the full-scale qualification test conducted by the applicant demonstrated the ACC performance principles. The tests confirmed the principle of the flow damper performance to switch the ACC flow from large flow injection to small flow injection caused by vortex formation in the vortex chamber during the small flow injection phase. The tests demonstrated that installation of an anti-vortex cap at the standpipe inlet prevents nitrogen ingress through the OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION standpipe at the end of the large-flow injection phase, and that, at the time of flow rate switching, the water level in the standpipe remains high enough above the vortex chamber to preclude any entrainment of nitrogen into the vortex chamber. The tests also showed that the flow rate switch water level is within a small uncertainty range of the standpipe inlet, and that the dissolved nitrogen has minimal effect on the ACC flow injection. Both the uncertainties of the flow rate switching water level and dissolved nitrogen effect are accounted for in the safety analysis. Accordingly, the staff concludes that the applicants use of the full-scale tests results to develop the ACC characteristic equations for the large-flow and small flow injection phase is acceptable, as further discussed in the following section.

3.2 Characteristics Equations for Advanced Accumulator (ACC)

The ACC provides SI in response to pressure drop in the primary system. For the calculation of the ACC flow rate, the applicant developed two ACC flow characteristic equations, Equations 5-1 and 5-2, for the large-flow and the small-flow injection phases, respectively, as described in Section 5.1.1, Characteristic Equations of Flow Rates for the Safety Analysis, of the topical report. These characteristic equations describe the flow coefficient, Cv, as a function of cavitation factor, v, which are defined below. The transition from the large-flow characteristic equation to the small-flow characteristic equation takes place based on the water level in the accumulator. When the water level decreases below the inlet of the standpipe, no flow enters the large flow standpipe and a vortex is formed in the vortex chamber thereby decreasing flow rate.

The applicant developed these characteristic equations, along with switching criteria between the two equations, based on data from the full-scale ACC tests.

Test Case 7 was conducted with lower tank pressure of and not representative of reactor operating conditions. The water temperature varied as shown in Figures 4.2.2-3 to 4.2.2-9 of the topical report and discussed in response to Question No.1 of the U.S. Nuclear Regulatory Commission (NRC)

RAI 9448, dated April 26, 2018 (ML18121A126). The effect of water temperature is included in the cavitation factor since it is defined as a function of vapor pressure. In addition, the cavitation factor and flow coefficients also include density in the dynamic pressure terms, although this term is less temperature dependent than vapor pressure.

OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION The flow rate coefficient, Cv, and the cavitation factor, v, as defined below, for each test are obtained from the test data.

(PA + gH ) + N 2 g ( H 1 H )) (PD + wVD2 / 2 + w gH ' )

KD =

VD2 / 2 1

Cv =

KD PD + Patm Pv + w gH ' + wVD2 / 2 wVm2 / 2 v =

(

(PA + w gH + N 2 g ( H1 H )) PD + wVD2 / 2 + w gH ' )

Where, Cv Flow rate coefficient v Cavitation factor KD Resistance coefficient of flow damper PA Test tank pressure [gage]

w Density of water N2 Density of nitrogen gas g Acceleration of gravity H Vertical distance between test tank water level and vortex chamber H1 Vertical Distance between test tank pressure gage and vortex chamber H Vertical distance between outlet pipe and vortex chamber Pat Atmospheric pressure Pv Vapor pressure of water PD Static pressure of flow damper outlet piping [gage]

VD Velocity in the flow damper outlet piping Vm Velocity at the model piping diameter The applicant plotted the test data (flow coefficient vs. cavitation factor) in a log-log curve. The data for the large-flow and small-flow phases collapse into two distinct curves as shown in Figure 5.1-1, The Flow Characteristics of the Flow Damper, of the topical report. The ACC characteristic equations shown in Equations 5-1 and 5-2 of the topical report for the large-flow and small-flow phases, respectively, are obtained by the least square fits of the test data.

The flow switches from low resistance to high resistance flow path when the level in accumulator reaches the entrance of the standpipe. When the flow resistance becomes high, the ACC characteristic equation changes from the large-flow to the small-flow equation.

Uncertainties in the characteristic equations are addressed in Section 5.1.2, Estimation of Uncertainty of the Characteristic Equations of Flow Rates, of the topical report and in Section 3.3, Uncertainty in ACC Characteristic Equations, of this report.

OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION 3.3 Uncertainty in ACC Characteristic Equations The characteristic equations developed from the full-scale test data will be used in the safety analyses. There are uncertainties in the characteristics equations that have to be factored into the safety analyses either as conservative bias or as a distribution in statistical analyses for determining overall uncertainty.

The overall uncertainties of the ACC characteristic equations are attributed to experimental uncertainty that includes the manufacturing error (tolerances) of the test model, instrumentation uncertainty for data acquisition, and the dispersion uncertainty of the least-square fit equation to the test data. Section 5.1.2, Estimation of Uncertainty of the Characteristic Equations of Flow Rates, of the topical report provides an analysis of the full-scale test characteristic equation uncertainties, and the staff evaluation is described in Section 3.3.1, Experimental Uncertainty in Characteristic Equations, of this report.

In the large break LOCA analysis, the total uncertainty is treated as a statistical parameter in the Automated Statistical Treatment of Uncertainty Method (ASTRUM), WCAP-16009-P-A (ML050910157) analysis and the value is randomly sampled from the normal distribution within 4 standard deviations. In the small break LOCA analysis and the mass and energy release analyses, the total uncertainty is treated as a negative bias of one-sided 95% confidence level.

There are additional uncertainties in the modeling parameters such as water level for the switchover from the large-flow to small-flow injection phase, and the dissolved nitrogen effects.

The uncertainties of the ACC water level for switching flow rates is described in Section 5.2, Estimation of Potential Uncertainties of Water Level for Switching Flow Rates, of the topical report, and the staff evaluation is described in Section 3.3.2, Uncertainty in Switching Level, of this report. The treatment of the dissolved nitrogen effect is discussed in Section 5.3, Treatment of Dissolved Nitrogen Gas Effect in the Safety Analysis, of the topical report, and the staffs evaluation is described in Section 3.3.3, Uncertainty due to Dissolved Nitrogen Effect, of this report.

3.3.1 Experimental Uncertainty in Characteristic Equations As discussed above, the applicant predicted the ACC flow rate coefficient using two characteristic equations: one for the early large flow phase when the water level is above the entrance of the standpipe, and the other for the small flow phase when the water level is below the standpipe entrance. These two characteristic equations were derived from the data obtained from the full-scale test facility. In addition, information about the water level in the tank at the time of switch is also obtained from these tests. This section describes the evaluation of the uncertainties associated with the full-scale test characteristic equations.

3.3.1.1 Estimate of Experimental Uncertainty There are three sources of uncertainty. The first source of uncertainty is dispersion deviation, which is the uncertainty due to curve fitting the data to obtain the characteristic equations. The second is instrument uncertainty, which is the uncertainty in the measurement of different OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION parameters that are used to compute flow rate coefficients and cavitation factors. The third is the manufacturing error in different components of the test setup.

Section 5.1.2, Estimation of Uncertainty of the Characteristic Equations of Flow Rates, of the topical report, identifies these sources of uncertainties and the values associated with dispersion deviations, instrument uncertainties, and manufacturing errors. In quantifying the uncertainty associated with the full-scale test, the applicant has employed a methodology according to the Guide to the Expression of Uncertainty in Measurement (GUM) found in the International Organization for Standardization / International Electrotechnical Commission (ISO/IEC) Guide 98-3 (Reference 5). This methodology is different from the methodology used in Revision 5 of the topical report; i.e., ANSI/ASME PTC19.1-1985 (Reference 6). In RAI 9448, Question No. 1, the staff requested the applicant to discuss the differences between the methodologies, to justify the change in its approach, and to discuss the overall impact of the full-scale test on the estimation of uncertainty of the characteristic equations of flow rates. In its response to RAI 9448, Question No.1, dated April 26, 2018 (ML18121A126), the applicant stated that GUM ISO/IEC Guide 98-3 was incorporated into the MHIs current quality manual as an uncertainty evaluation standard. The applicant further explained that in recent years, GUM ISO/IEC Guide 98-3, is recognized as the standard method for uncertainty evaluations, and it is accepted by several international standardization authorities such as IEC and ISO. With the exception of the methodology change, the staff finds that the uncertainties of the full-scale test are appropriately evaluated according to the GUM ISO/IEC Guide 98-3 because they are essentially the same as those obtained in the full height 1/2 scale test. The staff approved the uncertainties obtained in the full height 1/2 scale test in its SE for Revision 5 of the topical report (ML14030A383). There the applicant evaluated the uncertainties with ANSI/ASME PTC19.1-1985 which is acceptable to the NRC staff.

The dispersion deviation is computed by estimating departure of the characteristic equation from the measurement as described in Section 5.1.2 of the topical report. For the full-scale tests, the applicant calculated the relative difference between the flow coefficients from the test data and the flow coefficient calculated with the characteristic equation, and the dispersion deviation of the test is the standard deviation of the relative differences of the data points in the tests. Equation 5-4 of the topical report is used to calculate the dispersion deviation of all full-scale tests used in the development of the flow characteristic equation. Table 5.1-1, Dispersion of the Data from the Experimental Equations, summarizes the standard deviation of the relative differences of the flow rate coefficient calculated from the test data and the characteristic equations, respectively, of individual tests and combined over all the five tests. The standard deviation for the dispersion deviation for the large-flow phase equation is and is for the small-flow equation when averaged over all the five tests. The staff finds this to be a standard curve fitting procedure and acceptable.

The instrument uncertainty relates to the uncertainties associated with the measurement of those parameters in the experiment pertaining to the determination of the flow characteristics of the accumulator. Table 5.1-2, Instrument Uncertainties, of the topical report summarizes the standard deviation of the relative differences of the flow rate coefficient calculated from the test data and the characteristic. In RAI 9448, Question No. 3, the staff noted that the results in Revision 6 of the topical report are different from the results in Revision 5 and requested the OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION applicant to explain the difference in approach and resulting instrument uncertainty associated with the flow rate coefficient. In its response to RAI 9448, Question No.3, dated April 26, 2018 (ML18121A126), the applicant explained the difference between the method used to calculate the instrument uncertainty for the full height 1/2 scale test and full-scale test as follows.

The staff finds the instrument uncertainty values acceptable because the values represent accurate maximum uncertainty values within the respective cavitation ranges.

The third source of uncertainty is due to manufacturing tolerance of the flow damper dimensions. In its response to RAI 9448, Question No.1, dated April 26, 2018 (ML18121A126),

the applicant confirmed that the manufacturing error remains the same for both the full height 1/2 scale test and the full-scale test because this estimation is independent of test data and utilizes the same methodology. In its response to Question No. 18, dated July 20, 2007 (ML070280342), the applicant described that the effect for flow rate coefficient due to manufacturing error is considered separately for the large-flow and small-flow injection phases.

The applicant explained as follows:

For the large-flow injection phase, the parameters with dominant effect on the flow rate coefficient are the vortex chamber outlet nozzle throat diameter and the facing angle between the large-flow and small-flow inlet pipe at the vortex chamber. The outlet nozzle throat has the minimum flow area in the flow damper and is therefore the dominant dimension for flow damper performance. The facing angle of the large and small flow inlet pipes is the angle at which flows from the large and small flow inlet pipe collide. Since a goal of the design is to set this angle such that angular momentum of the two flows cancel each other and eliminate any vortex in the vortex chamber, the error in this collision angle would cause some OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION vortexing during large-flow injection and affect the flow damper performance.

3.3.1.2 Combining Uncertainties The characteristic equations are incorporated into the computer codes such as WCOBRA-TRAC as best estimate values. However, there is a need for estimates of the aggregate of all uncertainties as bias and distribution. This is described in Section 5.1.2 of topical report MUAP-07001, Revision 7.

The standard deviation of the combined uncertainty is calculated by the SRSS of the standard deviations for instrument, dispersion and manufacturing error, respectively.

The total experimental uncertainty in the characteristic equation is expressed in terms of standard deviation for the flow rate coefficient and is summarized in Table 5.1-3, Total Uncertainty of Flow Rate Coefficient (Experimental Equations) for Safety Analysis of US-APWR, of MUAP-07001, Revision 7. In the LBLOCA analysis (ML111230038), the total uncertainty is treated as a statistical parameter in the ASTRUM analysis and the value is randomly sampled from the normal distribution within four standard deviations. In the SBLOCA analysis (ML13346A162) and the mass and energy release analyses, the total uncertainty is treated as a negative bias of the one-sided 95 percent confidence level. The staff has determined that these uncertainty treatment approaches to be acceptable in the above cited SBLOCA and LBLOCA analyses.

3.3.2 Uncertainty in Switching Level The ACC model implementation uses the logic of switching from the large flow characteristic equation to the small flow characteristic equation. The uncertainty in this model is described in Section 5.2 of the topical report. The data from the full-scale tests, excluding Test Case 5, indicate that switching level deviation with respect to the standpipe entrance varies OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

. Consideration of the + side error is equivalent to a decrease in the volume available for large flow injection. Thus, the maximum flow switching level is taken into account for the safety analysis to result in the shortest duration of the large flow injection. The applicant conservatively chose the bounding value of Test Case 3 as the flow switch level uncertainty, and the staff verified that this case represents the highest level of switchover. The staff finds this to be conservative. With addition of instrument uncertainty, the uncertainty in the switchover water level is The water level uncertainty is accounted for in the safety analyses by converting it into the initial ACC water volume uncertainty; i.e., decreasing the initial water volume in the accumulator by the + side error of the water level uncertainty range. This will result in earlier switching to the small-flow phase and will result in shorter duration of the large flow injection phase. Since the important function of the ACC is to fill up the reactor vessel lower plenum promptly during the refill period, and then simultaneously raise the water level in the downcomer, the shorter duration of the large flow injection phase will result in a slower increase in the downcomer water level. Thus, the staff finds that it is conservative and acceptable to treat the switchover water level uncertainty by reducing the initial water level in the accumulator.

For the LBLOCA analysis, which uses the realistic analysis with the ASTRUM statistical treatment of uncertainties methodology, the flow rate switching water level uncertainty is included in the initial ACC water volume uncertainty and used in the ASTRUM analysis, as described in Section 3.5.1.4, Uncertainty, of Topical Report MUAP-07011-P, Large Break LOCA Code Applicability Report for US-APWR, (ML111230038). For the SBLOCA analysis, which uses the Appendix K to 10 CFR 50 approach, the switching water level uncertainty will be treated as a bounded value to reduce the initial water volume in the accumulator, as described in Section D.4, Treatment of Uncertainty, of Topical Report MUAP-07013-P, Small Break LOCA Methodology for US-APWR, Revision 3 (ML13346A162). The staff has determined that these uncertainty treatment approaches to be acceptable in the above cited analyses.

3.3.3 Uncertainty due to Dissolved Nitrogen Effect As stated in Section 3.2 of this report, the characteristic equations were developed from the full-scale test data. The data from Test Case 5, was not included in the database for the characteristic equations because it was performed with accumulator water saturated with nitrogen. Section 3.1.6, Effect of Dissolved Nitrogen, of this report describes the effect of dissolved nitrogen on the ACC performance. The liquid in the actual accumulators will have dissolved nitrogen, which may be less than liquid saturated with nitrogen as in Test Case 5.

However, as a conservative approach, the applicant proposed to increase the accumulator injection line piping resistance to compensate for the dissolved nitrogen effect.

In its response to RAI 34, dated September 16, 2009 (ML092650198), the applicant performed a sensitivity analysis of LBLOCA with the accumulator injection line resistance varied within . The results showed that a change of the injection pipe loss coefficient will delay the onset of transition from the large-flow injection phase to the small-flow phase by , which encompasses the delay observed in Test Case 5. In Section 5.3 of the topical report, it is stated that although the dissolved nitrogen in Test Case 5 greatly exceeds that expected in the actual accumulator tank, OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION the slightly longer flow switching delay due to the dissolved nitrogen effect is included in all the LOCA safety analysis by increasing the injection piping resistance by . The staff finds that the increase of the ACC injection line piping resistance in the LOCA analysis adequately account for the flow switching delay caused by the dissolved nitrogen effect, and is, therefore, acceptable.

3.4 Pre-Operational Test of Accumulator Performance Section 6.0, Characteristic Equations in the Pre-Operational Test, of the topical report provides the calculation for acceptable ranges of the flow resistances of the flow damper. The accumulator flow resistance is the inverse of the square of the flow damper flow coefficient. The acceptable flow resistance ranges for the large-flow and small-flow injection phases, respectively, are therefore based on the flow coefficients calculated from the characteristic equations and the uncertainties associated with the flow characteristic equations. The staff evaluation of the uncertainties in the characteristic equations is described in Section 3.3 of this report.

In the US-APWR DC application DCD Tier 1 information, Section 2.4.4, Emergency Core Cooling System (ECCS), Table 2.4.4-5, Emergency Core Cooling System Inspections, Tests, Analyses, and Acceptance Criteria [ITAAC], lists ITAAC items for the ECCS system.

Item 7.b.i.b requires that tests and analyses of the as-built accumulator system be performed for the as-built accumulator system to calculate and demonstrate the resistance coefficient of the as-built accumulator system meets the acceptance criteria shown in Table 2.4.4-6, Requirement for Accumulator System Resistance Criteria. The acceptance criteria specified in Table 2.4.4-6 are consistent with the acceptable resistance ranges of the large-flow and small-flow injection modes of the accumulator flow damper described in Section 6.0 of the topical report. Therefore, the staff finds that the ITAAC test provides acceptable verification that the performance of the as-built advanced accumulator system is within the ACC flow characteristic equations within the acceptable uncertainty range, as will be credited in the safety analysis.

4.0

SUMMARY

OF EVALUATION The staff reviewed US-APWR Topical Report MUAP-07001, Revision 7, The Advanced Accumulator (ML18178A267), along with the responses to the staffs requests for additional information. As a result of its review and for the reasons stated above, the staff concludes as follows:

a) The applicants data and analysis are sufficient to support the concept of a vortex damper to passively switch the accumulator injection flow from a large flow to a small flow injection.

b) The applicants data and analysis are sufficient to establish that an anti-vortex cap will prevent formation of a vortex at the entrance of the standpipe.

c) The applicants data is sufficient to validate the two characteristic equations that correlate flow rate coefficient with cavitation factor for the large flow and small OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION flow injection phases, which will be used to estimate the accumulator flow rate coefficient for the safety analysis.

d) The characteristic equations developed from the full-scale test facility are applicable to the full-scale accumulator with additional uncertainties and bias, which are described in Section 3.3.1 of this report.

e) Cavitation is predicted in the outlet nozzle for both large and small flow phases.

The location and impact of losses have been correctly addressed.

f) The effect of dissolved nitrogen will be accounted for through an increase in the loss coefficient by in the accumulator discharge pipe. Accounting for dissolved nitrogen in the analysis will be an additional loss to the already existing loss coefficient for the accumulator injection pipe.

OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

5.0 REFERENCES

1. The Advanced Accumulator, MUAP-07001-P, Revision 7, May 31, 2018 (ADAMS Accession No. ML18178A267).
2. Response to NRCs Questions for Topical Report MUAP-07001-P, Revision 6, The Advanced Accumulator (Proprietary), UAP-HF-18001, February 1, 2018 (ADAMS Accession No. ML18037A649).
3. Response to NRCs Questions for Topical Report MUAP-07001-P, Revision 6, The Advanced Accumulator (Proprietary), UAP-HF-18003, April 26, 2018 (ADAMS Accession No. ML18121A126).
4. Realistic Large Break LOCA Evaluation Methodology Using the Automated Statistical Treatment of Uncertainty Method (ASTRUM), WCAP-16009-P-A, Revision 0, March 11, 2005 (ML050910157).
5. ISO/IEC Guide 98-3: 2008 Uncertainty of measurement - Part 3, Guide to the expression of uncertainty in measurement (GUM: 1995).
6. ANSI/ASME PTC19.1-1985.
7. United States Advanced Pressurized Water Reactor Final Topical Report Safety Evaluation for Topical Report MUAP-07001-P, Revision 5, THE ADVANCED ACCUMULATOR, February 5, 2014 (ADAMS Accession No. ML14030A383).
8. MHIs Responses to NRCs Requests for Additional Information on Advanced Accumulator for US-APWR Topical Report MUAP-07001-P, Revision 2, UAP-HF-09239, May 20, 2009 (ADAMS Accession No. ML091420551).
9. Large Break LOCA Code Applicability Report for US-APWR, MUAP-07011-P-A, Revision 4, March 2014 (ML111230038).
10. Small Break LOCA Methodology for US-APWR, MUAP-07013-P-A, Revision 3, December 5, 2013 (ML13346A162).
11. Amended MHIs Responses to NRCs Requests for Additional Information on Advanced Accumulator for US-APWR Topical Report MUAP-07001-P, Revision 2, UAP-HF-09453, September 16, 2009 (ADAMS Accession No.ML092650198).
12. Response to NRCs Questions for Topical Report MUAP-07001-P, Revision 1, The Advanced Accumulator (Proprietary), UAP-HF-07086, July 20, 2007 (ADAMS Accession No. ML072080342).

OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION 6.0 LIST OF ACRONYMS ACC Advanced Accumulator ANS American Nuclear Society ASTRUM Realistic Large Break LOCA Evaluation Methodology Using Automated Statistical Treatment of Uncertainty Method BLC Boundary Layer Coefficient BPG Best Practice Guidelines CFR Code of Federal Regulations DCD Design Control Document ECCS Emergency Core Cooling System GCI Grid Convergence Index GDC General Design Criteria GUM Guide to the Expression of Uncertainty in Measurement ISO/IEC International Organization for Standardization / International Electrotechnical Commission LOCA Loss-of-Coolant Accident MHI Mitsubishi Heavy Industries, LTD NRC U. S. Nuclear Regulatory Commission PCT Peak Cladding Temperature PWR Pressurized Water Reactor RAI Request for Additional Information RCS Reactor Coolant System RSM Reynolds Stress Model SRSS Square-Root-Sum-of Square SS Schnerr and Sauer US-APWR United States-Advanced Pressurized Water Reactor OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

OFFICIAL USE ONLY - PROPRIETARY INFORMATION ZGB Zwart-Gerber-Belamri OFFICIAL USE ONLY - PROPRIETARY INFORMATION Enclosure

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Revision History Revision Page Description 0 All Original issued 1

The followings items are revised in accordance with the revision of the proprietary scopes; Flow diagram of 1/3.5 Scale Test Apparatus is deleted.

4.2.2-2 In accordance with the deletion above, the information of test components is added to Outline Drawing of 1/3.5 Scale Test Apparatus (Fig.4.2.2-1).

The photograph of 1/3.5 Scale Test Apparatus is deleted Overview of 1/5-Scale Test Apparatus and Block Diagram is deleted.

4.2.3-2 In accordance with the deletion above, the information of test components is added to Outline Drawing of the Visualization Test Apparatus (Fig. 4.2.3-1).

The photograph of 1/5-Scale Test Apparatus is deleted.

4.2.3-8 The photographs of 1/5-scale test results are changed with non-proprietary photographs.

The photograph of Full-Height 1/2-Scale Confirmation Test Facility is deleted.

In accordance with these revisions from item 1 to 8 above, figure numbers, photo numbers, lists of figures and photos, and relevant descriptions are revised.

2 ABSTRACT The name of part vortex damper is fixed to the correct name vortex chamber.

3-2 Maximum design pressure of ACC is fixed correctly [

(Table 3.1-1) ], and Maximum design temperature of ACC is fixed correctly [

].

3-6 The position of leader line for (7) width of small flow pipe is fixed to (Fig.3.3-2) correct position.

Mitsubishi Heavy Industries, LTD.

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Revision History (Cont.)

Revision Page Description 2 3-6 The distance between the center of vortex chamber and the center line of small flow pipe, which is in parenthesis in inches

[ ], is fixed to the correct value [ ].

The height of standpipe (the distance between the bottom of anti-vortex cap and the top of vortex chamber), which is in parenthesis in inches [ ], is fixed to the correct value

[ ].

4.2.2-3 (standpipes diameter) is deleted from explain of L reflecting the response to RAI 15 of MHIs Response to NRCs RAI on Advanced Accumulator for US-APWR Topical Report MUAP-07001-P (R1), UAP-HF-08174-P/NP (R0).

4.2.4-3 The height of test tank [ ] mm is converted to [ ] inches (Fig.4.2.4-2) and added.

4.2.4-4 The distance between the center line of injection pipe and the top (Fig.4.2.4-3) of vortex chamber, which is in parenthesis in inches [ ],

is fixed to the correct value [ ].

4.2.4-5 The distance between the center of standpipe inner section and (Fig.4.2.4-4) the center of vortex chamber of actual flow damper, which is in parenthesis in inches [ ], is fixed to the correct value

[ ].

The distance between the throat and diffuser end of actual flow damper, which is in parenthesis in inches [ ] is fixed to the correct value [ ].

The inner diameter of outlet port of test flow damper, which is in parenthesis in inches [ ], is fixed to the correct value

[ ].

The radius value at the top of standpipe of test flow damper;

[ ] mm is converted to [ ] inch and added.

Mitsubishi Heavy Industries, LTD.

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Revision History (Cont.)

Revision Page Description 2 5.3 The title, text, and Table 5.2-2 are corrected appropriately Instrument reflecting the response to Question 17-C in Response to Uncertainties NRCs Questions for Topical Report MUAP-07001-P(R1)

ADVANCED ACCUMULATOR, UAP-HF-07086-P/NP(R0).

And other scribal errors are corrected in whole report.

3 1.0 Description is corrected because the DCD has already been submitted.

2.4 Equation (2-8) is corrected because of typographical error.

4.3-1 through 4 Section 4.3 is revised to reflect based on the discussion with the NRC.

7.0 REFERENCES

7.0 REFERENCES

is added Appendix A Appendix A is added to reflect the modification of Section 4.3.

4 General Editorial Collections and modifications for readability 4.3 Validity and Section 4.3 and Appendix A is revised to reflect based on the Scalability of discussion with the NRC.

Flow Rate Characteristics 5.0 Concept of Chapter 5 is revised to describe the total uncertainty of the the Safety advanced accumulator used for the safety analyses.

Analysis Model 7.0 References Reference document is revised in Chapter 7.0 5 General Editorial Collections and modifications for readability.

3.0 Detailed Fig. 3.2-1 and Fig. 3.3-2 are revised to incorporate DCD RAI 941 Design of the response as-installed ACC 4.3 Validity and Section 4.3 is revised to incorporate RAI 84 and 85 discussions.

Scalability of Flow Rate Characteristics Mitsubishi Heavy Industries, LTD.

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Revision History (Cont.)

Revision Page Description 5.0 Concept of the Chapter 5 is revised to incorporate RAI 94 discussion.

5 Safety Analysis Discussion regarding combination of uncertainty is removed.

Model 6.0 Characteristic Discussion regarding pre-operational test is added. The Equations in the numbers of Chapters are changed due to new Chapter 6 Pre-operational Test addition.

General This revision incorporates the design modification (installation 6 of equalizing pipe) and qualification tests results performed by full-scale test facility.

Description about Full-Height 1/2-scale model test and scalability are deleted, and full-scale qualification test results are added.

ABSTRACT Descriptions are revised as deleting the Full-Height 1/2-scale model test and adding the full-scale qualification test.

1.0 INTRODUCTION

qualification is added to include the qualification testing performed by full-scale test facility.

2.0 CHARACTERISTICS Contents of Section 4.3.1 and 4.3.2 of previous revision are OF THE ADVANCED described in Section 2.2.2.

ACCUMULATOR (ACC) 3.0 DETAILED DESIGN OF THE Title is changed. (as-installed is removed)

ACC Fig. 3.2-1, Fig. 3.3-1 and Fig. 3.3-2 are revised to reflect the design modification (equalizing pipe).

4.0 TESTING PROGRAM FOR Title is changed. (confirmatory is removed)

THE ACC Descriptions about joint study and scalability are deleted.

Descriptions are detailed as separating confirmatory tests performed by scale models during development phase (Section 4.2.1) and qualification test performed by full-scale test facility (Section 4.2.2).

Mitsubishi Heavy Industries, LTD.

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Revision History (Cont.)

Revision Page Description 5.0 CONCEPT OF Experimental equations of flow rate characteristics are 6 THE SAFETY updated according to the qualification test performed by ANALYSIS MODEL full-scale test facility.

6.0 Contents of uncertainty evaluations are updated.

CHARACTERISTIC EQUATIONS IN THE Experimental equations of flow rate characteristics are PRE-OPERATIONAL updated according to the qualification test performed by TEST full-scale test facility.

7.0

SUMMARY

Descriptions are updated based on the qualification test.

8.0 REFERENCES

Reference 4.3-1, 4.3-4 and 4.3-5 of previous revision are deleted.

APPENDICES Appendix-B is deleted.

Attachment 1 and 2 are deleted.

7 3.2 ACC Dimensions The word flow damper was changed to vortex chamber to and Structure clarify the meaning of the statement. (Reflection of the response to RAI 1098-9305, UAP-HF-18001) 3.3 Structure of the Further descriptions about equalizing pipe were added.

Flow Damper (Reflection of the response to RAI 1098-9305, UAP-HF-18001)

Fig. 3.3-2 The equalizing pipe inner diameter was shown in Fig. 3.3-2 Table 3.3-1 and the basis of the dimension was described in Table 3.3-1 as new item numbered (11). (Reflection of the response to RAI 1098-9305, UAP-HF-18001) 4.2.1.3 1/5-Scale Note to explain the basis for not repeating the confirmatory Test test with a modified vortex chamber was added. (Reflection of the response to RAI 1098-9305, UAP-HF-18001)

APPENDICES Appendix B was added to explain the updates from the topical report revision 5. (Reflection of the response to RAI 1098-9305, UAP-HF-18001)

Mitsubishi Heavy Industries, LTD.

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

© 2020 MITSUBISHI HEAVY INDUSTRIES, LTD.

All Rights Reserved This document has been prepared by Mitsubishi Heavy Industries, Ltd. (MHI) in connection with the U.S. Nuclear Regulatory Commissions (NRC) licensing review of MHIs US-APWR nuclear power plant design. No right to disclose, use or copy any of the information in this document, other than by the NRC and its contractors in support of the licensing review of the US-APWR, is authorized without the express written permission of MHI.

This document contains technology information and intellectual property relating to the US-APWR and it is delivered to the NRC on the express condition that it not be disclosed, copied or reproduced in whole or in part, or used for the benefit of anyone other than MHI without the express written permission of MHI, except as set forth in the previous paragraph.

This document is protected by the laws of Japan, U.S. copyright law, international treaties and conventions, and the applicable laws of any country where it is being used.

Mitsubishi Heavy Industries, Ltd.

2-3, Marunouchi 3-Chome, Chiyoda-ku Tokyo 100-8332 Japan Mitsubishi Heavy Industries, LTD.

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Table of Contents List of Tables i List of Figures ii List of Photographs iv List of Acronyms v ABSTRACT vi

1.0 INTRODUCTION

1-1 2.0 CHARACTERISTICS OF THE ADVANCED ACCUMULATOR (ACC) 2-1 2.1 ECCS Performance During a LOCA 2-1 2.2 Principles of ACC Operation 2-4 2.2.1 Concept and Principle of Flow Switching 2-4 2.2.2 Expected Phenomena 2-7 2.3 Performance Requirements for the ACC 2-14 2.3.1 Performance Requirements for Large Flow Injection 2-14 2.3.2 Performance Requirements for Small Flow Injection 2-14 2.3.3 Expected ECCS Function for Various Break Sizes 2-17 2.3.4 Design Requirements for the ACC 2-19 2.4 Expected Performance of the ACC 2-23 3.0 DETAILED DESIGN OF THE ACC 3-1 3.1 ACC Design Basis and Specifications 3-1 3.2 ACC Dimensions and Structure 3-3 3.3 Structure of the Flow Damper 3-5 4.0 TESTING PROGRAM FOR THE ACC 4.1-1 4.1 Purpose of the ACC Testing 4.1-1 4.2 Detailed Description of the Test and Results 4.2.1-1 4.2.1 Confirmatory Testing 4.2.1-1 4.2.2 Qualification Testing 4.2.2-1 5.0 CONCEPT OF THE SAFETY ANALYSIS MODEL 5-1 5.1 Flow Rate Characteristics for Safety Analysis 5-1 5.1.1 Characteristic Equations of Flow Rates for the Safety Analysis 5-1 5.1.2 Estimation of Uncertainty of the Characteristic Equations of Flow Rates 5-3 5.2 Estimation of Potential Uncertainties of Water Level for Switching Flow Rates 5-9 5.3 Treatment of Dissolved Nitrogen Gas Effect in the Safety Analysis 5-11 5.4 LOCA Analytical Model and Computational Procedure for Characteristic Equations 5-12 6.0 CHARACTERISTIC EQUATIONS IN THE PRE-OPERATIONAL TEST 6-1 7.0

SUMMARY

7-1

8.0 REFERENCES

8-1 Appendix-A A-1 Appendix-B B-1 Appendix-C C-1 Mitsubishi Heavy Industries, LTD.

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

List of Tables Table 3.1-1 Specifications for the ACC 3-2 Table 3.3-1 The Basis for the Flow Damper Dimension 3-7 Table 4.2.1.2-1 Test Conditions 4.2.1-12 Table 4.2.1.2-2 Summary of Test Results 4.2.1-13 Table 4.2.1.3-1 Visualization Test Conditions 4.2.1-25 Table 4.2.1.3-2 Visualization Test Results 4.2.1-26 Table 4.2.2-1 Test Conditions of Full-Scale Test 4.2.2-5 Table 4.2.2-2 Flow Switching Water Level 4.2.2-9 Table 5.1-1 Dispersion of the Data from the Experimental Equations 5-4 Table 5.1-2 Instrument Uncertainties 5-5 Table 5.1-3 Total Uncertainty of Flow Rate Coefficient (Experimental 5-8 Equations) for Safety Analysis of US-APWR Table 5.2-1 Uncertainty of Water Level for Switching Flow Rates 5-10 Mitsubishi Heavy Industries, LTD.

i

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

List of Figures Fig. 2.1-1 ECCS Performance During a Large LOCA 2-2 Fig. 2.1-2 System Configuration of the US-APWR ECCS 2-3 Fig. 2.2.1-1 Principle of Advanced Accumulator Operation 2-4 Fig. 2.2.1-2 Flow Damper 2-5 Fig. 2.2.2-1 Flow Structure under Large Flow Injection 2-9 Fig. 2.2.2-2 Example of Water Level Transient in Standpipe 2-10 Fig. 2.2.2-3 Flow Structure under Small Flow Injection 2-11 Fig. 2.3.2-1 Basic Concept for Calculation of the Required ECCS 2-15 Injection Flow Rate (Core Reflooding Phase)

Fig. 2.3.2-2 Required ECCS Injection Flow Rate 2-16 Fig. 2.3.3-1 RCS Pressure Transients and ECCS Injection Flow for 2-18 Various Break Sizes Fig. 2.3.4-1 RCS Pressure Transient during Large Break LOCA 2-21 Fig. 2.3.4-2 Large Flow Injection Transient during Large Break LOCA 2-21 Fig. 2.3.4-3 Overall View of the Accumulator System 2-22 Fig. 2.4-1 Expected Performance of the ACC 2-24 Fig. 3.1-1 Basis of the Small Flow Injection Water Volume 3-2 Fig. 3.2-1 Outline Drawing of Advanced Accumulator 3-4 Fig. 3.3-1 Overview of the Flow Damper 3-5 Fig. 3.3-2 Outline Drawing of the Flow Damper 3-6 Fig. 4.2.1.1-1 1/8.4 Scale Test Apparatus 4.2.1-2 Fig. 4.2.1.2-1 Outline Drawing of 1/3.5 Scale Test Apparatus 4.2.1-10 Fig. 4.2.1.2-2 Test Flow Characteristics without Anti-Vortex Cap (T. No. 4.2.1-18 1-1)

Fig. 4.2.1.2-3 Test Flow Characteristics with Anti-Vortex Cap (T. No. 1-2) 4.2.1-19 Fig. 4.2.1.2-4 Test Flow Characteristics without Anti-Vortex Cap (T. No. 4.2.1-20 2-1)

Fig. 4.2.1.2-5 Test Flow Characteristics with Anti-Vortex Cap (T. No. 2-2) 4.2.1-21 Fig. 4.2.1.3-1 Outline Drawing of the Visualization Test Apparatus 4.2.1-23 Mitsubishi Heavy Industries, LTD.

ii

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

List of Figures (Cont.)

Fig. 4.2.2-1 Schematic Drawing of the Full-Scale Test Facility 4.2.2-2 Fig. 4.2.2-2 Outline Drawing of the Full-Scale Test Facility 4.2.2-3 Fig. 4.2.2-3 (1/2) Full-Scale Test Results (Case 1) 1/2 4.2.2-10 Fig. 4.2.2-3 (2/2) Full-Scale Test Results (Case 1) 2/2 4.2.2-11 Fig. 4.2.2-4 (1/2) Full-Scale Test Results (Case 2) 1/2 4.2.2-12 Fig. 4.2.2-4 (2/2) Full-Scale Test Results (Case 2) 2/2 4.2.2-13 Fig. 4.2.2-5 (1/2) Full-Scale Test Results (Case 3) 1/2 4.2.2-14 Fig. 4.2.2-5 (2/2) Full-Scale Test Results (Case 3) 2/2 4.2.2-15 Fig. 4.2.2-6 (1/2) Full-Scale Test Results (Case 4) 1/2 4.2.2-16 Fig. 4.2.2-6 (2/2) Full-Scale Test Results (Case 4) 2/2 4.2.2-17 Fig. 4.2.2-7 (1/2) Full-Scale Test Results (Case 5) 1/2 4.2.2-18 Fig. 4.2.2-7 (2/2) Full-Scale Test Results (Case 5) 2/2 4.2.2-19 Fig. 4.2.2-8 (1/2) Full-Scale Test Results (Case 6) 1/2 4.2.2-20 Fig. 4.2.2-8 (2/2) Full-Scale Test Results (Case 6) 2/2 4.2.2-21 Fig. 4.2.2-9 (1/2) Full-Scale Test Results (Case 7) 1/2 4.2.2-22 Fig. 4.2.2-9 (2/2) Full-Scale Test Results (Case 7) 2/2 4.2.2-23 Fig. 5.1-1 The Flow Characteristics of the Flow Damper 5-2 Mitsubishi Heavy Industries, LTD.

iii

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

List of Photographs Photo. 4.2.1.1-1 1/8.4 Scale Test Apparatus 4.2.1-3 Photo. 4.2.1.1-2 Flow in the Standpipe and the Vortex Chamber during 4.2.1-6 Large Flow Photo. 4.2.1.1-3 Flow in the Vortex Chamber during Large Flow 4.2.1-6 Photo. 4.2.1.1-4 Flow Just before Large/Small Flow Switching 4.2.1-7 Photo. 4.2.1.1-5 Flow Shortly after Large/Small Flow Switching 4.2.1-7 Photo. 4.2.1.1-6 Flow during Small Flow 4.2.1-8 Photo. 4.2.1.1-7 Flow in the Vortex Chamber during Small Flow 4.2.1-8 Photo. 4.2.1.2-1 (1/2) Visualization of Flow without Anti-Vortex Cap (T. No. 4.2.1-14 1-1) 1/2 Photo. 4.2.1.2-1 (2/2) Visualization of Flow without Anti-Vortex Cap (T. No. 4.2.1-15 1-1) 2/2 Photo. 4.2.1.2-2 (1/2) Visualization of Flow with Anti-Vortex Cap (T. No. 1-2) 4.2.1-16 1/2 Photo. 4.2.1.2-2 (2/2) Visualization of Flow with Anti-Vortex Cap (T. No. 1-2) 4.2.1-17 2/2 Photo. 4.2.1.3-1 Large Flow 4.2.1-27 Photo. 4.2.1.3-2 Switching Flow Rate 4.2.1-27 Photo. 4.2.1.3-3 Small Flow 4.2.1-27 Mitsubishi Heavy Industries, LTD.

iv

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

List of Acronyms ACC Advanced Accumulator A/D converter Analog to Digital Converter APWR Advanced Pressurized Water Reactor ASME American Society of Mechanical Engineers CFR Code of Federal Regulations CRT Cathode-Ray Tube ECCS Emergency Core Cooling System GT/G Gas Turbine Generator GUM Guide to the Expression of Uncertainty in Measurement IEC International Electrotechnical Commission ISO International Organization for Standardization LOCA Loss-of-Coolant Accident MHI Mitsubishi Heavy Industries, Ltd NQA Quality Assurance Program Requirements for Nuclear Facilities PCT Peak Clad Temperature PRZ Pressurizer PWR Pressurized Water Reactor QA Quality Assurance RCS Reactor Coolant System RCP Reactor Coolant Pump R/V (RV) Reactor Vessel RWSP Refueling Water Storage Pit S/G Steam Generator SI Safety Injection SIP Safety Injection Pump USNRC United States Nuclear Regulatory Commission Mitsubishi Heavy Industries, LTD.

v

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

ABSTRACT The US-APWR Advanced Accumulator (ACC) simplifies the emergency core cooling system (ECCS) design by integrating the short term large flow rate design requirements currently satisfied by conventional accumulators and the low head safety injection pumps of a conventional pressurized water reactor (PWR) into a single passive device, the ACC. Upon initiation of a loss of coolant accident (LOCA) event, all low head injection requirements are satisfied by the ACC. Following depletion of the ACCs water volume, the long-term ECCS flow requirements are met by the high head safety injection pumps thus eliminating the need for low head injection pumps. Furthermore, the immediate availability of low head flow provided by the ACC upon loss of electrical power provides additional time to permit activation of the emergency backup power supplies.

Characteristics of the passive ACC, the detailed design of the ACC, the testing program for the ACC, and the concept of the safety analysis model are discussed in this report.

The ACC has a flow damper which primarily consists of the stand pipe and vortex chamber.

When the ACC water level is above the top of the standpipe, water enters the vortex chamber through both inlets at the top of the standpipe and at the side of the vortex chamber injecting water with a large flow rate. When the water level drops below the top of the standpipe, the water enters the vortex chamber only through the side inlet and vortex formation in the vortex chamber achieves the small flow rate injection.

In the first stage of injection, the ACC provides large flow injection to refill the reactor vessel then automatically reduces the flow as the water level decreases. This small flow stage of injection in conjunction with the high head safety injection pumps provides for core reflooding thereby eliminating the conventional low-head safety injection system.

During the development of this unique design for the US-APWR, three types of scaled tests were performed: 1/8.4, 1/3.5 and 1/5-scale model tests. These tests used visualization to confirm flow rate switching, vortex formation, and the prevention of significant gas entrainment into the vortex chamber at the end of the large flow stage of injection. The injection test provides the performance data required for quantitative evaluation of ACC flow.

Major results of the tests include:

(1) From the results of the 1/8.4 scale test, it was confirmed that switching from large flow to small flow occurs smoothly and a stable level was maintained in the stand pipe.

(2) From the results of the 1/3.5 scale test, it was confirmed that a sharp flow rate switching without significant gas entrainment was achieved.

(3) From the results of the 1/5-scale test, it was confirmed that no vortex was observed during the large flow injection stage, and a stable vortex was formed in the vortex chamber during the small flow injection stage.

The ACC design will improve the overall safety of pressurized water reactors by the innovative application of the flow damper which assures the early stage of LOCA injection flow is satisfied by a highly reliable passive system. This innovation reduces the necessity of relying on maintenance sensitive components, such as low head safety injection pumps, for assuring LOCA safety injection flow. This provides sufficient relief from the need for rapid start emergency diesel generator backup power and permits use of highly reliable gas turbine generators.

Mitsubishi Heavy Industries, LTD.

vi

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

The flow characteristics of the ACC have been verified by thorough full-scale qualification testing and can be fully described as a function of dimensionless numbers. Empirical flow rate coefficients have been developed from the test results and will be used in an integrated thermal hydraulic model of the US-APWR Reactor Coolant and ECCS systems to assure the US-APWR meets or exceeds all US safety standards.

Mitsubishi Heavy Industries, LTD.

vii

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

1.0 INTRODUCTION

This report describes the Mitsubishi Heavy Industries, Ltd. (MHI) Advanced Accumulator (ACC) design that will be used in MHIs Advanced Pressurized Water Reactor (APWR), and MHIs US-Advanced Pressurized Water Reactor (US-APWR). MHI intends to seek certification of the US-APWR design from the United States Nuclear Regulatory Commission (USNRC) and offer the design to utility companies for installation in the United States. The purpose of this document is to provide the design details and confirmatory and qualification testing results of the ACC to the USNRC in order to facilitate the review of this innovation in support of the US-APWR Design Certification Application. Review and approval of this Topical Report should increase the efficiency of the US-APWR Design Certification process and any subsequent Combined Operating Licenses (COLs) which reference the US-APWR design.

The ACC is an accumulator tank with a flow damper inside the tank. The tank is partially filled with borated water and pressurized with nitrogen. It is attached to the primary system by an injection pipe fitted with a series of two check valves plus an isolation valve which is aligned during operation to allow flow into the primary coolant system if the primary system pressure drops below the pressure of the accumulator. The ACC design combines the known advantages and extensive operating experience of a conventional accumulator used for loss of coolant accident (LOCA) mitigation in pressurized water reactors with the inherent reliability of a passive fluidic device to achieve a desired reactor coolant injection flow profile without the need for any active moving parts.

Incorporation of the ACC into the US-APWR design and LOCA mitigation strategy simplifies a critically important safety system by integrating an inherently reliable passive safety component into an otherwise conventional Emergency Core Cooling System (ECCS). This design improvement will allow the elimination of the low head safety injection pumps, and increases the amount of time available for the installed backup emergency power system to actuate. It is expected that the use of ACCs rather than low head safety injection pumps in the US-APWR design will reduce the net maintenance and testing workload while maintaining a very high level of safety.

This Topical Report describes the principles of operation, the important design features, and the extensive analysis and confirmatory and qualification testing program conducted to assure that the performance of the ACC is well understood.

Mitsubishi Heavy Industries, LTD.

1-1

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7) 2.0 CHARACTERISTICS OF THE ADVANCED ACCUMULATOR (ACC) 2.1 ECCS Performance During a LOCA Emergency core cooling during a Loss-of-Coolant Accident (LOCA) is one of the primary functions of the ECCS. During a large break LOCA, the fuel cladding temperature increases due to the significant loss of reactor coolant from the primary system. The ECCS is required to inject water into the core to limit the rise of fuel temperature as follows:

Step 1: Inject water at a high flow rate to rapidly refill the lower plenum and downcomer of the reactor vessel. (Reactor Vessel Refilling)

Step 2: Recover the core water level using the water level head in the downcomer. Small ACC flow to the reactor vessel keeps the water level in the downcomer high and quickly re-floods the core. (Core Reflooding)

Step 3: After core reflooding is completed, safety injection flow is continued in order to remove decay heat and maintain the core flooded. (Long-Term Cooling)

The performance requirements for the ECCS in a conventional nuclear plant during a large break LOCA is fulfilled using the following subsystems.

Step 1: Accumulator System Step 2: Low Head Safety Injection System and High Head Safety Injection System Step 3: Low Head Safety Injection System and High Head Safety Injection System Thus, in a conventional nuclear plant, the functions of the ECCS during a LOCA are assigned to three subsystems: the Accumulator System, the Low Head Safety Injection System, and the High Head Safety Injection System.

In the US-APWR, the ACC, which automatically shifts its flow rate from large to small, is incorporated into the safety system design. The function of the Low Head Safety Injection System is accomplished by the Accumulator System and the High Head Safety Injection System; therefore, the Low Head Safety Injection System can be eliminated to simplify the configuration of the ECCS.

The performance requirements are fulfilled by the US-APWR ECCS subsystems during a large break LOCA as described below and as shown in Fig. 2.1-1.

Step 1: Accumulator System Step 2: Accumulator System and High Head Safety Injection System Step 3: High Head Safety Injection System Mitsubishi Heavy Industries, LTD.

2-1

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Blow Down Core CoreRe - flooding Reflooding Long term cooling Long-Term Cooling

& RV Refill (Step1)

(Step 1) (Step 2)2)

(Step (Step (Step3)3)

Accumulator flow Injection Flow Requireme Requirement for nt for injection flow Safety injection pump flow Time Fig. 2.1-1 ECCS Performance During a Large LOCA During a large break LOCA, it is necessary to start the safety injection pumps prior to the end of accumulator injection to continuously inject water to the core. The ACC injects water longer than a conventional accumulator, thereby allowing more time for the safety injection pumps to start. This additional time margin allows the US-APWR to use gas turbine generators for the emergency power source if needed.

The system configuration of the US-APWR ECCS is shown in Fig.2.1-2. Four accumulators are installed and each ACC is connected to a Reactor Coolant System (RCS) cold leg. Four High Head Safety Injection Subsystems are installed and inject directly into the vessel downcomer following accumulator injection. Low Head Safety Injection subsystems are not installed.

Mitsubishi Heavy Industries, LTD.

2-2

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

GT/G GT/G GT/G RWSP S PRZ S M M M M M

SIP M SIP S/G S/G S/G S/G M M ACC ACC RCP RC RC RCP M

M MM S S R/V R/V S S M

M MM RCP RC RCP RC ACC ACC S/G S/G S/G S/G M M M

M M M

S SIP M M M M SIP S GT/G GT/G RCP: Reactor Coolant Pump ACC: Advanced Accumulator R/V: Reactor Vessel SIP: Safety Injection Pump S/G: Steam Generator GT/G : Gas Turbine Generator PRZ: Pressurizer S: Safety Injection Signal RWSP: Refueling Water Storage Pit Fig. 2.1-2 System Configuration of the US-APWR ECCS Mitsubishi Heavy Industries, LTD.

2-3

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7) 2.2 Principles of ACC Operation 2.2.1 Concept and Principle of Flow Switching The ACC is a water storage tank containing a flow damper that automatically switches the flow rate of cooling water injected into the reactor vessel from a large to a small flow rate.

The conceptual drawing of the ACC is shown in Fig. 2.2.1-1.

The ACC is a simple device with no moving parts consisting of a large tank containing a flow damper. In essence, the "flow damper" consists of the standpipe, the large flow pipe, the small flow pipe, the vortex chamber, and their corresponding connections. The outlet of the flow damper is connected to the injection pipe. There is a vortex chamber with its outlet connected to the injection piping exiting the accumulator. The small flow pipe is tangentially attached to the vortex chamber. The large flow pipe connects the bottom of the standpipe radially to the vortex chamber. The height of the standpipe inlet port is located at a tank level that corresponds to the interface between the volume of water needed for the large flow rate injection stage and the volume needed for the small flow rate injection stage.

Large Flow Water Level Small Flow Water Level Standpipe Diffuser Throat Outlet Port Large Flow Pipe Vortex Chamber Large Flow (RV Refilling) Water Levels in Accumulator Tank Small Flow (Core Reflooding)

Fig. 2.2.1-1 Principle of Advanced Accumulator Operation Mitsubishi Heavy Industries, LTD.

2-4

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

When a Loss of Coolant Accident (LOCA) occurs and pressure in the reactor coolant system decreases, the check valves along the injection pipe open to permit injection of ACC water into the reactor vessel. Since the water level in the accumulator is initially higher than the elevation of the inlet of the standpipe, water flows through both the large and small flowrate pipes. These flows collide with each other so that no vortex is formed in the vortex chamber. The angle of collision, , is determined so that the flow from the large flowrate pipe cancels out the angular momentum of the flow from the small flowrate pipe. Consequently, the overall flow resistance of the flow damper is small resulting in a large flow. Fig. 2.2.1-2 shows additional details of the flow damper.

Large Flow Pipe Small Flow Pipe Fig. 2.2.1-2 Flow Damper Mitsubishi Heavy Industries, LTD.

2-5

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

High flow continues until the water level in the accumulator decreases to the inlet level of the standpipe, and the flow into the standpipe stops. The flow in the large flowrate pipe comes to a near-stop. Without this flow from the large flow pipe, the continued flow from the small flowrate pipe forms a strong vortex in the vortex chamber. As a result of centripetal force, a large pressure drop (and the equivalent of a high flow resistance) occurs along the radius of the vortex chamber between the small flow pipe and the outlet port. Therefore, a small flow rate is achieved with a vortex rather than with moving parts.

The strength of the vortex in the chamber depends on the ratio of the diameter of the vortex chamber, D, and that of the outlet port, d. The ACC design objective was to make the ratio, D/d, as large as possible. The diameter of the vortex chamber, D, is determined by the accumulator diameter, while that of the outlet port, d, is limited by the required flow rate at large flowrate conditions. In order to satisfy these design requirements and achieve a larger ratio of large to small flow rates, a throat followed by a diffuser is employed at the outlet port of the vortex chamber.

Mitsubishi Heavy Industries, LTD.

2-6

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7) 2.2.2 Expected Phenomena

1) During Large Flow Rate Stage Mitsubishi Heavy Industries, LTD.

2-7

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Mitsubishi Heavy Industries, LTD.

2-8

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Fig. 2.2.2-1 Flow Structure under Large Flow Injection

2) During Flow Rate Switching Mitsubishi Heavy Industries, LTD.

2-9

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Fig.2.2.2-2 Example of Water Level Transient in Standpipe

3) During Small Flow Rate Stage Mitsubishi Heavy Industries, LTD.

2-10

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Fig. 2.2.2-3 Flow Structure under Small Flow Injection Mitsubishi Heavy Industries, LTD.

2-11

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Mitsubishi Heavy Industries, LTD.

2-12

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Mitsubishi Heavy Industries, LTD.

2-13

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7) 2.3 Performance Requirements for the ACC The functions of the ACC during a large break LOCA, as described in Section 2.1, are refilling the lower plenum and downcomer immediately following the reactor coolant blow down (Step 1),

and establishing the core reflooding condition by maintaining the downcomer water level after refilling the core (Step 2). In this section, these functional requirements are quantified as performance requirements and design requirements.

2.3.1 Performance Requirements for Large Flow Injection The lower plenum and downcomer of the reactor vessel shall be filled by large flow injection.

Since the time required for accomplishing large flow injection is the dominant factor for the Peak Clad Temperature (PCT), the performance requirement is that the lower plenum and the downcomer are filled with water as rapidly as possible during the refilling period.

2.3.2 Performance Requirements for Small Flow Injection

1) Basic concept It is important to keep the downcomer filled with ECCS water, in order to ensure that a water-head is maintained to force ECCS water flow into the core through the lower plenum of the reactor vessel to provide core cooling (See Fig. 2.3.2-1).
2) Required injection flow rate The required injection flowrate during the core re-flood period is determined as follows.

The required flow rate is obtained from the core reflooding flow rate calculated by the hypothetical LOCA analysis, which assumes that the downcomer is filled with sufficient water to adequately achieve safety injection flow. The conventional 4-loop plant approach of a double-ended cold leg break (with a discharge coefficient of 0.6) causing the worst-case PCT is assumed for the analysis.

The required flowrate is obtained as the sum of the injection flowrate and the product of flow area times the reflooding rate for each of the following three regions (See Fig.2.3.2-1).

(1) Core Region (2) Neutron Reflector Cooling-holes Region (3) Neutron Reflector Back Side Region The required injection flowrate obtained by this analysis is shown in Fig.2.3.2-2. According to the progression of core reflooding, the difference of water-head between the downcomer and the core is reduced gradually, and the required injection flowrate also decreases gradually.

This analysis was performed using the Appendix K ECCS model with the Japanese decay heat model. Since the decay heat level of the Japanese model is lower than that of the Appendix K model, the core reflooding rate is larger. Therefore, the Japanese decay heat model was used to obtain the conservative (larger) reflooding rate requirement.

Mitsubishi Heavy Industries, LTD.

2-14

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

The adequacy of the required injection flowrate will ultimately be confirmed by the ECCS performance analysis using the WCOBRA/TRAC code with ASTRUM methodology.

3) Required injection flow rate margin The required flowrate for the small flow injection stage will be supplied solely by the ACC as described in Fig. 2.1-1 (Section 2.1). The Safety Injection pumps will provide additional ECCS flow rate margin.

SI Assuming sufficient SI flow to maintain the downcomer filled with water.

Back side region (3)

Cooling-holes region (2) Cooling-holes region (2) Back side region (3)

ACRONYMS:

Core region (1)

SI: Safety Injection ECCS flows into the following 3 regions from the downcomer water-head (1) Core region (2) Neutron reflector cooling-holes region (3) Neutron reflector back side region Required flowrate = Sum of the injection flowrate in each region Fig. 2.3.2-1 Basic Concept for Calculation of the Required ECCS Injection Flow Rate (Core Reflooding Phase)

Mitsubishi Heavy Industries, LTD.

2-15

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Note: According to progression of core reflooding, the difference of water-head between the downcomer and the core is gradually reduced. The required flowrate also decreases gradually.

Fig. 2.3.2-2 Required ECCS Injection Flow Rate Mitsubishi Heavy Industries, LTD.

2-16

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7) 2.3.3 Expected ECCS Function for Various Break Sizes In general, high PCT is postulated to occur in two break-size ranges. One is for a large-break LOCA and the other is for a small-break LOCA.

Fig. 2.3.3-1 shows the RCS pressure transient and ECCS flow injections for various break sizes.

Large-break size:

Because of large break flow, the core would be uncovered and fuel-cladding temperature would rise. The ECCS injection capability requires core water level to be recovered quickly.

Therefore, the prompt injection during the refill period is required to be performed by the large flow rate stage of the accumulators. (See Fig. 2.3.3-1(a))

When the accumulators inject water for medium break sizes (that is, less severe large break LOCAs) the fuel-cladding temperature does not reach high values because of the lower decay heat level at the time of ACC injection and relatively quick core reflooding due to the slow accident transition compared to larger break-sizes. (See Fig. 2.3.3-1(b))

Small-break size:

Because of the loop seal and boil-off phenomena, the core would be uncovered and the fuel-cladding temperature would rise. In this case, the accumulators do not inject water for the core reflooding. The required ECCS function is the injection capability to supply the evaporated coolant in the long-term after core reflooding. Therefore, the high head safety injection pumps provide this function. (See Fig. 2.3.3-1(c))

The ECCS design will be validated by the ECCS performance evaluation analysis.

Mitsubishi Heavy Industries, LTD.

2-17

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

LARGE SMALL (a) Large Break Size (b) Medium Break Size (c) Small Break Size (less severe large break sizes)

Fig. 2.3.3-1 RCS Pressure Transients and ECCS Injection Flow for Various Break Sizes Mitsubishi Heavy Industries, LTD.

2-18

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7) 2.3.4 Design Requirements for the ACC This subsection describes specific design requirements based on the performance requirements specified in Subsections 2.3.1 and 2.3.2.

1) Design Requirements for Large Flow Injection The performance requirements for the large flow injection stage discussed in Section 2.3.1 are as follows:

Requirement The lower plenum and the downcomer are filled with water as rapidly as possible during the refilling period.

Major parameters affecting the duration of large flow injection are specified to meet this requirement as follows.

Large flow injection water volume: [ ]

Initial gas volume: [ ]

Initial gas pressure: [ ]

Resistance coefficient of the accumulator injection line in large flow injection: [ ]

The RCS pressure transient during a large break LOCA is assumed to be as shown in Fig.

2.3.4-1Note1, and the injection flow rate transient for large flow that is calculated based on the above parameters is shown in Fig. 2.3.4-2.

Note1: It is assumed that RCS pressure is reduced to [ ] in

[ ] seconds after initiation of accumulator injection based on the result of the APWR LOCA analysis.

The injection flow rate transient shown in Fig. 2.3.4-2 is obtained using the following equations. The concept is similar to that used in conventional nuclear safety analyses.

KU 2 Pgas Pinj g( Ht Hp ) (2-1) 2 Vgaso Pgas Pgaso (2-2)

Vgas dVgas A U (2-3) dt Mitsubishi Heavy Industries, LTD.

2-19

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7) where:

Pgas  : Accumulator gas pressure Pgaso  : Initial accumulator gas pressure Vgas  : Accumulator gas volume Vgaso  : Initial accumulator gas volume Pinj  : Pressure at the injection point K  : Overall resistance coefficient of accumulator injection system during large flow Ht  : Water level elevation of accumulator Hp  : Elevation of the injection point U  : Velocity in the injection pipe A  : Cross section inside of the injection pipe

Density of water g  : Gravitational acceleration constant t  : Time
Adiabatic exponent Each parameter is shown in Fig. 2.3.4-3 which provides an overall view of the Advanced Accumulator System.

The PCT results were confirmed to be below [ ] in the APWR design stage by using these parameters for large flow injection (assuming the resistance coefficient of the accumulator injection system is [ ]). Since the resistance coefficient of the planned accumulator injection piping and valves (Kp) is approximately [ ], the resistance coefficient of the flow damper during large flow (KD) was determined to be [ ] using the following design requirement:

KD = K - Kp

=[ ]

=[] (2-4)

The resistance coefficient of the flow damper during large flow changes is based on the cavitation factor as described in Section 2.2. The design requirement above is specified as a target for the resistance coefficient of the flow damper at the end of RCS depressurization

([ ] seconds after initiation of accumulator injection), which is where the cavitation factor becomes smallest.

2) Design Requirements for Small Flow Injection The performance requirements for small flow injection during large break LOCA are described in Section 2.3.2. The required small injection flow rate following the flow transition is [ ] as shown in Fig. 2.3.2-2. Assuming 3 of the 4 accumulators are available, the required flow rate is [ ] per tank. The expected flow rate at the end of large flow injection from each accumulator is [ ], as shown in Fig. 2.3.4-2. The flow-shifting ratio from large flow to small flow necessary to meet the performance requirement is as follows:

R=[ ]

=[ ] (2-5)

Mitsubishi Heavy Industries, LTD.

2-20

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Therefore, the flow-shifting ratio of [ ], which is within the required flow-shifting ratio [ ]

from large flow to small flow, is specified as a design requirement.

Fig. 2.3.4-1 RCS Pressure Transient during Large Break LOCA Fig. 2.3.4-2 Large Flow Injection Transient during Large Break LOCA Mitsubishi Heavy Industries, LTD.

2-21

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Fig. 2.3.4-3 Overall View of the Accumulator System Note Refer to Section 3.1 Mitsubishi Heavy Industries, LTD.

2-22

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7) 2.4 Expected Performance of the ACC The major design parameters for the ACC, specified to meet the performance requirements in Section 2.3.4, are as follows:

Large flow injection water volume: [ ]

Initial gas volume: [ ]

Initial gas pressure: [ ]

Injection pipe inner diameter: [ ]

Resistance coefficient of the accumulator injection line in large flow injection: [ ]

Resistance coefficient of the flow damper in large flow injection: [ ]

Flow-shifting ratio: [ ]

The expected injection flow characteristics based on the parameters listed above are shown in Fig.2.4-1.

The calculation method used for this calculation is the same as described in Section 2.3.4.

However, the resistance coefficient of the flow damper (KD) is changed from [ ] to [ ] at the point where the water volume for large flow injection becomes zero. The rationale for the KD value of [ ] in the small flow injection stage is shown as follows:

QL R (2-6)

QS 2

K D L Kp QS R 2 (2-7)

K D S Kp QL K D L Kp KDS Kp R 2

= (2-8) where R  : Flow-shifting ratio QL  : Large injection flow rate QS  : Small injection flow rate KDL  : Resistance coefficient of flow damper during large flow injection KDS  : Resistance coefficient of flow damper during small flow injection Kp  : Resistance coefficient of injection pipe Mitsubishi Heavy Industries, LTD.

2-23

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Fig. 2.4-1 Expected Performance of the ACC Mitsubishi Heavy Industries, LTD.

2-24

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7) 3.0 DETAILED DESIGN OF THE ACC 3.1 ACC Design Basis and Specifications The performance and the design requirements for the Advanced Accumulator (ACC) were described in Section 2.3. This section describes the design basis and specifications of the ACC.

Each ACC connects to a corresponding RCS cold leg (4 ACCs in all) and has the function of injecting water into the core during the reactor vessel (RV) refilling process and also injecting water at a lower flow rate during the core reflooding process.

The goals of the above stated functions are as follows:

Refilling process (large flow injection):

Rapidly inject 2,613 ft3(74 m3) Note1 of water (equivalent to the volume of the downcomer and lower plenum of the RV) to initiate reflooding.

Reflooding process (small flow injection):

Continue injecting water for approximately 180 secondsNote2 following the refilling process to maintain downcomer water level through core quench.

Note1: The planned volume of the downcomer and lower plenum of US-APWR is approximately 2,295 ft3 (65 m3). The required value (2,613 ft3 (74 m3)) is selected to provide additional margin.

Note2: It is assumed that the duration of small flow injection from the accumulator is 180 seconds followed by the injection from the Safety Injection (SI) pumps. The duration of small flow injection is related to with the SI pump capacity. If the duration of small flow injection is short then a correspondingly larger volumetric flow rate is required from the SI pumps.

Since the water from an ACC installed on the broken loop is assumed to spill into the containment and does not contribute to core injection, only the water injected from the remaining three accumulators is available for core injection. Thus, the required volume of ACC is specified as follows:

Refilling process (large flow injection) 2,613 ft 3 a / 2/3 / 3 c 1,307 ft 3 /ACC b

(3-1)

The volume of an ACC is specified to be 1,342 ft3 (38 m3), which is the required 1,307 ft3 (37 m3) plus margin.

(a) Total volume of the downcomer and the lower plenum (ft3)

(b) Assumption based on the experience that 1/3 of injection flow is spilled from the broken loop to the containment (c) Number of ACCs assumed to inject into the core Mitsubishi Heavy Industries, LTD.

3-1

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Reflooding process (small flow injection)

The relationship between the amount of small injection flow and the duration of small flow injection with regard to the expected performance of the ACC defined in Section 2.4 is shown in Fig. 3.1-1. The expected duration of the small flow injection from the ACC is 180 seconds.

Therefore, 724 ft3 (20.5 m3) of injection water is required per ACC. Thus, 784 ft3 (22.2 m3) of injection water volume is specified giving a margin above approximately 8%. Considering the total water volume, 2,126 ft3 (60.2 m3), and adding the volume of gas space and dead water volume, the required volume of a single ACC is 3,180 ft3 (90 m3). The validity of this volume will be confirmed in the ECCS performance analysis. Specifications for the ACC are summarized in Table 3.1-1.

Table 3.1-1 Specifications for the ACC Type: Vertical cylindrical Number: 4 Volume: 3,180 ft3 (90 m3)

Maximum design pressure: 700 psig (4.83 MPa [gage])

Maximum design temperature: 300 deg F (149 deg C)

Large flow injection volume: 1,342 ft3 (38 m3)

Small flow injection volume: 784 ft3 (22.2 m3)

Fig. 3.1-1 Basis of the Small Flow Injection Water Volume Mitsubishi Heavy Industries, LTD.

3-2

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7) 3.2 ACC Dimensions and Structure An outline drawing of the ACC is shown in Fig. 3.2-1. The inner diameter of the tank is [ ] ft

[ ] and total height is [ ]. The tank inner structure includes the flow damper and the standpipe. Because the outlet piping is above the vortex chamber, the un-available dead water is less than that for an ACC design that has its outlet piping attached under the vortex chamber due to the need for increased installation space. The ACC main dimensions are shown in Fig. 3.2-1.

Mitsubishi Heavy Industries, LTD.

3-3

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Fig. 3.2-1 Outline Drawing of Advanced Accumulator Mitsubishi Heavy Industries, LTD.

3-4

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7) 3.3 Structure of the Flow Damper The structure of the flow damper is shown in Fig. 3.3-1 and Fig. 3.3-2. The flow damper consists of an anti-vortex cap, standpipe, vortex chamber, small flow pipe, and outlet pipe.

The inlet of the standpipe is set at the water level at which the flow rate switches from large flow to small flow. The anti-vortex cap installed on the standpipe inlet prevents gas entrainment just before the flow switching and improves the flow-switching characteristics. The small flow piping is connected to the vortex chamber tangentially. An anti-vortex plate is also provided at the inlet of the small flow pipe and prevents the gas in the ACC gas space from being sucked into the standpipe when the water level is reduced to the small flow inlet. During large flow injection, the flows from the standpipe and the small flow pipe collide in the vortex chamber and the resulting water stream flows out of the chamber directly without forming a vortex. The equalizing pipe is provided to ensure prevention of a vortex formation during large flow injection. By pressure equalizing across the vortex chamber, swirl flow production during large flow injection is prevented. This design ensures that the performance of the flow damper during large flow injection will be stable and consistent with the characteristics equation as described in Chapter 5 of this report. On the other hand, the equalizing pipe does not interrupt the vortex formation during small flow injection because only tangential flow enters into the vortex chamber, and the pressure difference between the points where equalizing pipe is attached is insignificant. The throat portion and diffuser are provided on the outlet pipe to increase the flow resistance during small flow, recover the pressure during large flow, and provide a smooth transition for the pipe.

The detailed dimensions, such as the inner diameters of the throat, and the vortex chamber, are determined from the tests using the ratio of Zobel diode. The basis for determining the dimensions is shown in Table 3.3-1.

Fig. 3.3-1 Overview of the Flow Damper Mitsubishi Heavy Industries, LTD.

3-5

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Fig. 3.3-2 Outline Drawing of the Flow Damper Mitsubishi Heavy Industries, LTD.

3-6

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Table 3.3-1 The Basis for the Flow Damper Dimension Regions The bases of dimension (1) Standpipe height Specified to assure the required injection water volume during small flow injection is maintained between the inlet of the standpipe and the upper end of the vortex chamber, and to prevent the water level from reducing much below the upper end of the vortex chamber.

(2) Height of standpipe Specified to be consistent with the width of the large flow pipe inner section connecting to the vortex chamber to assure the smooth flow from the standpipe to the vortex chamber.

(3) Width of standpipe Specified to limit the flow velocity just before the flow switching to inner section prevent significant entrainment of gas during the water level transient in the standpipe.

(4) Inner diameter of the The inner diameter of the throat is the dominant factor of the throat resistance of the flow damper during large flow. The inner diameter of the throat is specified to meet the required resistance of large flow.

(5) Inner diameter of the The inner diameter of the vortex chamber is determined by tests vortex chamber using the ratio of Zobel diode.

(6) Height of the vortex The inner height of the vortex chamber is determined by tests using chamber the ratio of Zobel diode.

(7) Width of small flow It is preferable that the width of the small flow pipe be as small as pipe possible to increase the flow damper resistance during small flow.

However, if the aspect ratio of the small flow pipe (height/width) is large, a stable jet flow is not formed. It is necessary that a stable jet flow is induced from the small flow pipe to the vortex chamber in order to form the stable vortex. Thus, the width of the small flow inlet pipe is specified with an aspect ratio of [ ] Note.

Note: Max. aspect ratio for a stable jet flow is acquired from experience.

(8) Width of large flow It is preferable that the width of the large flow pipe is as large as pipe possible to reduce the flow damper resistance during large flow.

Therefore, the width of the large flow pipe is specified to make it as large as practical according to the structure considering the facing angle of the large flow and small flow pipe.

(9) Facing angle of large The facing angle of the large flow and small flow pipe is specified to flow pipe and small balance the angular momentum of each other so that no vortex is flow pipe formed in the chamber during large flow considering the width of large flow pipe.

(10) Expansion angle of It is preferable that the flow area from the throat to outlet pipe the throat increases gradually in order to return the kinetic pressure to the static pressure during large flow. However, if the expansion angle is too large, the flow may strip off the pipe and cause an energy loss.

Therefore, the expansion angle is specified as [ ] degrees which is less than [ ] degrees, which prevents flow stripping based on experience.

(11) Inner diameter of the The purpose of the equalizing pipe is to equalize the pressure across equalizing pipe the vortex chamber during large flow injection. To efficiently accomplish this, a pipe with an inner diameter of [ ]

was selected as the largest optimum size to connect to the vortex chamber wall.

Mitsubishi Heavy Industries, LTD.

3-7

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7) 4.0 TESTING PROGRAM FOR THE ACC This section of the Topical Report; (1) describes the purpose and objectives of the confirmatory and qualification test program; (2) provides a detailed description of the tests and the test results.

4.1 Purpose of the ACC Testing Development of the ACC was conducted through confirmation tests using several scale models.

A qualification test was conducted in full-scale test facility to verify the overall design of the ACC.

During the development phase, the following items were tested to confirm the principles and characteristics of the flow damper:

(1) Confirmation of the principles of the flow damper:

Tests were conducted to observe the behavior of the flow in the vortex chamber of the flow damper during large flow injection, large/small flow switching, and small flow injection to confirm that their actual behavior was as expected.

(2) Confirmation of the anti-vortex function at the end of large flow injection:

As water level in the accumulator decreases after initiation of accumulator injection, it may be possible to form a vortex at the entrance to the standpipe and the nitrogen gas in the ACC gas space can be sucked into the standpipe when the water level is low. Therefore, an anti-vortex cap was designed for the large flow inlet. The tests were conducted to confirm that the anti-vortex cap prevented the vortex from forming at the standpipe inlet and that gas was not sucked into the standpipe.

A qualification test using a full-scale test facility was conducted to verify the following items:

(1) Verification of performance during large flow and small flow phases:

Tests were conducted to confirm that the performance of the flow damper, during large flow and small flow respectively, met the acceptance criteria (resistance coefficient for large and small flow injection)

(2) Verification of flow switching without need of any moving parts:

It was assumed that the injection flow rate shifts from large flow to small flow when the tank water level decreases to the lower edge of the standpipe anti-vortex cap. This design feature was verified by actual injection testing.

Moreover, the following item was confirmed by the full-scale testing:

(3) Confirmation of the effect of dissolved nitrogen gas:

Mitsubishi Heavy Industries, LTD.

4.1-1

THE ADVANCED ACCUMULATOR MUAP-07001-NP-A (R7)

Since the accumulator utilizes compressed nitrogen gas, nitrogen gas may dissolve in the water. If the water in the accumulator contains dissolved nitrogen gas, it is assumed that the gas comes out of solution and affects the flow characteristics of the flow damper.

Therefore, tests were conducted with nitrogen-rich water to confirm that the effect of nitrogen gas did not impact the ACC performance.

Mitsubishi Heavy Industries, LTD.

4.1-2