WISCONSIN Electnc powra coursur 231 W. MICHIG AN, P.O. BOX 2046, MILWAUKEE, WI 53201 (414)221 2345 VPNPD-89-256 NRC-89-051 April 27, 1989 U. S. NUCLEAR REGULATORY COMMISSION Document Control Desk Mail Station P1-137 Washington, D.
C.
20555 Gentlemen:
DOCKETS 50-266 AND 50-301 OFFSITE DOSE CALCULATION MANUAL AND ENVIRONMENTAL MANUAL (TACs 69805/69806 and 61628/61629)
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 As requested in your April 14, 1989 letter, the current l
revisions of the Point Beach Plant Offsite Dose Calculation Manual, Revision 3, and Environmental Manual, Revision 6, are enclosed.
Changes which Wisconsin Electric previously committed to have been incorporated into these current i
revisions.
These changes were originally prepared by our engineering staff in February for inclusion with the Semiannual Monitoring Report.
However, due to other conflicting adm2.nistrative and clerical work efforts (including preparation fcr the Unit 1 outage), we were unable to complete typing, assembly, and approval of the ODCM in time for transmittal along with the Semiannual Monitoring Report.
Please contact us if you have any questions concerning this submittal.
1 Very truly yours, i
p/
hlc/
C. W.
Fay Vice President Nuclear Power Ac a c
Copies to NRC Regional Administrator, Region III NRC Resident Inspector
/
R.
S.
Cullen, PSCW 8905040133 890427 hDR ADOCK 05000266 PDC