MONTHYEARML20236F3081987-10-21021 October 1987 Ack Receipt of Util Transmitting Proposed Amend to Plant Physical Security Plan,In Response to Miscellaneous Amends & Search Requirements.Comments on Physical Security Changes Encl.Response Requested within 30 Days Project stage: Other ML20147E7201988-01-14014 January 1988 Forwards Rev 22 to Security Plan.All Amend Items Will Be Implemented Upon Receipt of NRC Approval Notification W/ Listed Exceptions.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20151L3551988-04-18018 April 1988 Forwards Rev 23 to Security Plan.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20154A9381988-05-11011 May 1988 Forwards Rev 24 of Security Plan for Plant.Rept Withheld (Ref 10CFR73.21) Project stage: Other ML20151A3311988-07-14014 July 1988 Forwards Rev 25 to Security Plan.Encl Withhled (Ref 10CFR73.21) Project stage: Other ML20155A4881988-09-26026 September 1988 Forwards Rev 26 to Security Plan.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20245J2481989-04-25025 April 1989 Forwards Rev 27 to Security Plan.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20245B1231989-06-20020 June 1989 Forwards Rev 28 to Plant Security Plan.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20005E1751989-12-22022 December 1989 Forwards Rev 29 to Security Plan.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20043D3151990-06-0101 June 1990 Forwards Rev 30 to Security Plan.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20065P5341990-10-30030 October 1990 Forwards Rev 31 to Security Plan,Adding 10CFR26 to App B Section.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20091B7761991-07-17017 July 1991 Forwards Rev 32 to Security Plan,Reflecting Current chain-of Command for Security Mgt Organization,Type of Weapons Onsite & Change to Shotgun Qualification Requirements.Rev Withheld (Ref 10CFR73.21) Project stage: Other ML20079H3451991-09-27027 September 1991 Forwards Rev 33 to Security Plan,Per 10CFR50.4.Plan Withheld (Ref 10CFR73.21) Project stage: Other ML20094J3311995-11-0606 November 1995 Requests Exemption from Certain Requirements of 10CFR73.55, Requirements for Physical Protection of Licensed Activities in NPR Against Radiological Sabotage for Plant.Encl Withheld Project stage: Other ML20094J0611995-11-0606 November 1995 Forwards Three Copies of Rev 44 of Plant Security Plan.Encl Withheld Project stage: Other 1989-12-22
[Table View] |
Similar Documents at Byron |
|---|
|
Text
_ _ - - _
4A.
'( '
. C:mminw;cith Edis:n
'I One First National Plaza, Chicago, lihnois Address Reply to: Post Office Box 767 l-V Chicago, Illinoic 60690
'.f I
June 20, 1989
{
U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C.
20555
Subject:
Byron Nuclear Power Stations Units 1 and 2 Byron Station Security Plan NRC Docket Nos. 50-454 & 50-455 TAC Nos. 65282/65283 I
Referencess Letter dated April 24, 1987 from W. L. Axelson to Dennis L. Farrar Letter dated May 11, 1989 from L. Robert Greger to Thomas J. Kovach i
Enclosed are the original and three (3) copies of Revision 28 of the Byron Nuclear Power Station Security Plan. This revision is in reply to the unacceptable portion of Revision 21 as identified in the referenced correspondence. The letter dated April 24, 1987, was inadvertently overlooked and Commonwealth Edison regrets any difficulty this omission may have caused.
Pursuant to 10CFR 50.4, the signed original and three copies of the security plan revisions are being provided to your office. A copy of this letter and two copies of the security plan revisions are being sent to i
Region III.
He have corcluded that these changes do not decrease the safeguards effectiveness of tht plan. These enclosures contain Safeguards Information which must be protected from public disclosure pursuant to 10CFR 73.21.
Sincerely, M
/ Tho s J. Kovach Nuclear Licensing Manager ces A. B. Davis (w/two encls.)
THE ENCLOSURE CONTAINS SAFEQUARDS INFORMATION Upon separation, this pace is decontrolled P"D Nella[