ML20236D399

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Feb 1989 for Oyster Creek Nuclear Generating Station
ML20236D399
Person / Time
Site: Oyster Creek
Issue date: 02/28/1989
From: Baran R, Fitzpatrick E, Sedar J
GENERAL PUBLIC UTILITIES CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 8903230086
Download: ML20236D399 (7)


Text

,

7 i

MONTHLY OPERATING REPORT FEBRUARY 1989 The following Licensee Event Reports were submitted during the month of February 1989:

LER 88-001:

POSSIBLE LOSS OF MAIN STEAM LINE ISOLATION CAPABILITY DUE TO EXCESSIVE MAIN STEAM ISOLATION VALVE CONTROL AIR LEAXAGE

)

i In response to NRC Generic Letter 88-14, " Instrument Air Supply System Problems Affecting Safety-Related Equipment",. and concerns identified during the E0P inspection and internal review of the air system, testing was performed on the Main Steam Isolation Valve (MSIV) control air system on January 3,1989. The purpose of the testing was to check the MSIV accumulators for water and to test control air check valve leak tightness.

The testing plan could not be completed due to excessive air leakage from control air piping connections.

This condition was determined reportable on January 11, 1989. The MSIV control air system leakage is attributed to the system construction.

The MSIV control air piping is made from threaded brass pipe assemblies which are prone to leakage due to the material used, method of assembly, and maintenance performed on the system over the life of the plant.

This condition could have prevented the fulfillment of the safety function of reactor and/or primary containment isolation in the event of an accident condition. Corrective actions include replacing the control air system piping with stainless steel pipe to eliminate leakage. Corrective actions to address MSIV leakage are being evaluated and will be submitted in a followup LER.

In addition, future testing of air accumulators and related piping will be performed in accordance with the testing program developed by GPUN in response i

to Generic Letter 88-14.

This event is reportable based on 10CFR50.73(a)(2)(v)(C&D).

LER: 89-002:

POSSIBLE FUEL POOL GATE MOVEMENT AB0VE IRRADIATED FUEL This is a voluntary report to document an occurrence at the site.

This event has been determined to be not reportable, however, this report does contain information of interest to the industry.

On January 14 and 15,1989, a Fuel Pool Gate (FPG) may have been moved over irradiated fuel stored in the fuel pool.

Technical Specifications state that no object in excess of the weight of one fuel assembly may be moved over stored irradiated fuel. Although no one could state conclusively that this did occur, observation of one of the moves by a licensed Control Room Operator (CRO) and post event analysis indicate that this may have occurred. 'The cause of this incident is personnel error. The contractor maintenance personnel moving the FPG failed to adequately monitor the gate's movement to ensure it did not pass over the irradiated fuel.

Water being sprayed on the gate to prevent airborne contamination also restricted the contractor personnel's ability to observe the gate location in relation to the fuel.

Personnel were not required by procedure to specifically monitor the path of the FPG movement. Corrective action included relocating spent fuel to provide additional clearance for any path that the gates may have to transverse, and assignment of a monitor specifically charged with monitoring any fuel pool gate movements to preclude recurrence.

This requirement will be incorporated into the fuel pool gate movement procedure.

.Fz s 8903230086 890228

/

PDR ADOCK 05000219

[

R PDC

_v AlWlELY OPERATING REFORT - FEBRUARY 1989 l

Throughout the report period, Oyster Creek remained shut down for the j

Cycle 12 Refueling Outage.

i I

l, l

l l

l l

i l

l 3032g

w 1

7 1ATING DATA REPORT

)

4 -

PERATfNG' STATUS'

]

1.

DOCKET:

50-219 2.

REPORTING PERIOD: 02/69 3.

UTILITY CONTACT:

JOHN H. SEDAR, JR.

609-971-4698 4

4.

LICENSED THERMAL POWER (MWt):

1930 5.

NAMEPLATE RATING (GROSS MWe):

687.5 X 0.8 = 550 I

6.

DESIGN ELECTRICAL RATING (NET "t

650 7.

MAXIMUM DEPENDABLE CAPACITY (GROSS MWe):

642 8.

MAXIMUM DEPENDABLE CAPACITY (NET MWe):

620 9.

IF CHANGES OCCUR AB0VE SINCE LAST REPORT, GIVE REASONS:

NONE q

10. POWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe):
11. REASON FOR RESTRICTION, IF ANY:

NONE MONTH YEAR CUMULATIVE 12.

REPORT PERIOD HRS 672.0 1416.0 168192.0

13. - HOURS RX CRITICAL 0.0 0.0 106245.4 14.

RX RESERVE SHTDWN HRS 0.0 0.0 91 8. 2

15. HRS GENERATOR ON-LINE 0.0 0.0 103543.5 16.

UT RESERVE SHTDWN HRS 0.0 0.0 1208.6

17. GROSS THERM ENER (MWH) 0 0

173520889

18. GROSS ELEC ENER (MWH) 0 0

58604184

19. NET ELEC ENER (MWH)

-4036

-7049 56252819 20.

UT SERVICE FACTOR 0.0 0.0 61. 6 21.

UT AVAIL FACTOR 0.0 0.0 62.3 22.

UT CAP FACTOR (M)C NET) 0.0 0.0 53.9

23. UT CAP FACTOR (DER NET) 0.0 0.0 51. 5
24. UT FORCED OUTAGE RATE 0.0 0.0 11.5

- 25.

FORCED OUTAGE HRS 0.0 0.0 13510.7 26.

SHUTDOWNS SCHEDULED 0VER NEXT 6 MONTHS (TYPE, DATE, DURATION):

Currently shutdown for refueling outage which started September 30, 1988, 27.

IF CURRENTLY SHUTDOWN ESTIMATED STARTUP TIME:

March 16,1989.

- 19658/0045X

a 0yster Creek Station #1 Docket No. 50-219 REFUELING INFORMATION - FEBRUARY,1989 Name of Facility: Oyster Creek Station #1 Scheduled date for next refueling shutdown:

Current outage started 9/30/88 Scheduled date for restart following refueling: March 16,1989 Will refueling or resumption. of operation thereafter require a Technical 1

Specification change or other license amendment?

Yes

~

l l

Scheduled date(s) for submitting proposed licensing action and supporting l

information:

l Technical Specification Change Request No.166 was approved l

in November 1988.

l

\\

Important -licensing considerations associated with-~ refueling, e.g.,

new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures:

j

1. General Electric Fuel Assemblies - fuel design and performance analysis rathods have been approved.by the NRC.

1

2. Exxon Fuel Assemblies - no major changes have been made nor are l

there any anticipated.

The number of fuel assemblies (a) in the core 560

=

(b) in the spent fuel storage pool

= 1595 (c) in dry storage 16

=

The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies:

Present licensed capacity: 2600

- The projected date' of the last refueling that can be discharged to the spent fuel pool assuming the present licensed capacity:

Reracking of the fuel pool 'is in progress.

Nine (9) out of ten (10) racks have been installed to date.

When reracking is completed, discharge capacity to the spent fuel pool will be available until 1994 refueling outage.

1619B l

i.

D h-

_..-______m_-

j AVERAGE DAILY POWER LEVEL NET MWe i'

DOCKET f........

50219-UNIT...-....... 0YSTER CREEK #1 REPORT DATE....... March 8, 1989 COMPILED BY....... JO HN H. S ED AR JR.

TELEPHONE #.......609-971-4698 l

l MONTH FEBRUARY, 1989 DAY MW DAY MW I

1.

0 17 0

2.

0 18 0

3.

0 19 0

4.

0 20 0

5.

0 21 0

6.

0 22 0

7.

0 23 0

i 8.

0 24 0

l 9.

0 25 0

10.

0 26 0

11.

0 27 0

l l

12.

0 28 0

13.

0 14.

0 15.

0 16.

0

o 9

o 8

r 9

o c

1 n 0 t n a 4 w

9 r

. r 6 eo 1

o h

a 4 dd e 2

+

c B S

e ath T

g mut c

r 1

0 y a

. 7 N

a h

5 n M R 9 F

t s st a

u a

r as O

wea a

ht n

e nt s c

c o

/

O E E Y E S

n i oo N M T B N N

a stt A A n

i D O O

e ct e T

N D H

T t

end I

E E

P K T T

C n

d ea E

A i

um E

L a

e q X'

N L

E I

M v es M U P E V

i sa M T I

I T

d t b w O

C n

a u C

E a

r S n R

t o.

R l

s i e e

i

.sg O

u n nia C

f i wct e

m oeu R

dd dO at S

R ueR N

2 nh h2 O

9 1

A st1 I

8 T

9 C

1

)2 U

D N R

(

Y W O R E

E R

FOR W R

A ODO f

DG C P T O R

R E

R ON A G D W F

HI T E N 2

F T TR X O I

E C

UE U P

A I

D HH D l

R N D iT ST E E N N

R P A O

P S

M A NW T

)

R 0

O O

N D

P O

T E

S C

U R

A H

E R

S T

I N

N

)

U O S 8

R I

0 TA U 5

R O 3

U (H 3

D D

E D

L E

U EC PR D YO E H

S T F C S

F S

8 E

8 T

/

A 0

D 3

/

Y 9

R a

m O

0 N

7 88

i GPU Nuclear Corporation

)

Nuclear

=:r 88 F ked March 14,1989 4 do" 6997

{

Writer's Direct Dial Number:

U.S. Nuclear Regulatory Commission I

ATTN: Document Control Desk I

Wa s hi ngton, ' D.C.

20555

Dear Sir:

j

Subject:

Oyster Creek Nuclear Generating Station i

Docket No. 50-219 Montbly 0perating Report i

In accordance with the Oyster Creek Nuclear Generating Station Operating

{

License No. DPR-16, Appendix A' Section 6.9.1.C, enclosed are two (2) copies of the Monthly Operating Data (gray book information) for the Oyster Creek Nuclear Generating Station.

If you should have any questions, please contact Kathy Barnes, Oyster Creek Licensing at (609)971-4390.

Very truly yours, E

r Vice President and Director Oyster Creek i

EEF:KB:aa (0841 A:2)

Enclosures cc:

Director (10)

Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, DC 20555 Mr. William T. Russell, Administrator Region I U.S. Nuclear Regulatory Commission 475 Allendale Avenue King of Prussia, PA 19406 4

Mr. Alexander W. Dromerick, Project Manager U.S. Nuclear Regulatory Commission Division of Reactor Projects I/II I

Washington, DC 20555 I

NRC Resident Inspector Oyster Creek Nuclear Generating Station GPU Nuclear Corporation is a subsidiary of the General Public Utilities Corporation