Notice of Violation from Insp on 880111-890112.Violation Noted:Chemistry Technician Did Not Verify Use of Latest Procedure Rev for Performing Reactor Coolant Chemistry Sampling
ML20235S799
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 02/16/1989
From: Zimmerman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML13316B994 List:
References
50-206-88-28, NUDOCS 8903080020
Download: ML20235S799 (2)


Text

. - -

'. A

?..

APPENDIX A a

NOTICE OF VIOLATION s

~

Southern California Edison Company Docket No. 50-206 t San Onofre Unit 1 License No. DPR-13 b

During an NRC. inspection conducted on November 18, 1988'through January 7'and Janua ry 12,.1989, a violation of NRC requirements was identified. !In accor-

' dance with 10 CFR Part 2, Appendix C, " General Statement of Policy and Procedure for NRC Enforcement Actions," 53 Fed. Reg. ~40019 (October 13, 1988),

the violation is listed below: .

Technical Specification 6.8.1 requires that applicable procedures recom-mended in Appendix A of Regulatory Guide 3.33, Revision 2', February 1978, be established and implemented.

  • Section 10 of Appendix A of Regulatory Guide 1.33, Revision 2, states that procedures should be provided for periodic chemistry sampling of plant systems.

Station procedure S0123-III-1.6.1, Revision 3 (Normal Operation of the Reactor Sampling System), defines the requirements for periodic sampling of the reactor coolant system for proper concentrations of boron for core reactivity control. Step 3.1 of this procedure requires that prior to use of the. procedure, the user must verify that the latest revision of L ,

the procedure is being used.

Contrary to the above, between November 30 and December 24, 1988, a Unit 1 chemistry technician did not verify use of the latest procedure revision for performing reactor coolant chemistry sampling. In particular, the technician used a Revision 2 procedure which did not include the latest requirements for sampling a depressurized reactor coolant system. ,

}

This.is a Severity Level IV violation (Supplement I). l Pursuant to the provisions of 10 CFR 2.201, Southern California Edison Company is hereby required to submit a written statement or explanation to the U.S.

Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC  ;

20555 with a copy to the Regional Administrator, Region V, and a copy to the f NRC Senior Resident Inspector, San Onofre, within 30 days of the date of the letter transmitting this Notice. This reply should be clearly marked as a

" Reply to a Notice of Violation" and should include for each violation:

(1) the reason for the violation if admitted, (2) the corrective steps that have been taken and the results achieved, (3) the corrective steps that will be taken to avoid further violations, and (4) the date when full compliance will be achieved. If an adequate reply is not received within the time S903080020 89021 PDR ADOCK 05000i06 C' PDC )

o h ., .

h

~

specified in this Notice, an order may .be issued to show cause why the license' should not be modified, suspended, or revoked or why such other action'as may be proper should not be taken. Consideration may be.given to extending the' >

response time for good cause shown. ,

FOR,THE NUCLEAR REGULATORY C'OMMISSION O e g R. P. Zimmerman, Chief y.

Reactor Projects Branch Dated at Walnut Creek, California this MD ay d of 60kru Ar(A ,1989 d