ML20235D406

From kanterella
Jump to navigation Jump to search
Insp Repts 50-498/87-48 & 50-499/87-48 on 870705-0904. Violations Noted.Major Areas Inspected:Site Tours,Followup on 10CFR21 repts,post-tensioning Sys,Reactor Vessel & Internals,Structural Concrete & HVAC
ML20235D406
Person / Time
Site: South Texas  
Issue date: 09/21/1987
From: Constable G, Garrison D, Clay Johnson
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20235D290 List:
References
50-498-87-48, 50-499-87-48, IEIN-83-72, NUDOCS 8709250215
Download: ML20235D406 (9)


See also: IR 05000498/1987048

Text

_.

.

_

_

_

._- ._

- _ _ _ -

_ _ _ - - -

-

-.

.

.,

,

j,

APPENDIX B

U. S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Inspection Report:

50-498/87-48

Construction Permits:

CPPR-128

50-499/87-48'.

CPPR-129

Dockets: -50-498

50-499

Licensee:

Houston Lighting & Power Company (HL&P)

P. O. Box 1700

Houston, Texas 77001

Facility Name:

South Texas Project, Units 1 and 2 (STP)

Inspection At:

STP, Matagorda County, Texas

' Inspection Conducted:

July 5 through September 4, 1987

Inspectors:

1 /ff#[

'C. E. Jo fnson, Senior Resident Inspector

Dhty

roject dection C, Reactor Projects Branch

6?Waalv

9/dn

D.L.Garr/ison,ResidentInspector, Project

ghtp

Section C, Reactor Projects Branch

f

?

,

Approved:

)

b

)rV. L.UConstable, Chief, Project Section C

Date

f(a

Reactor Projects Branch

<

p

0

L

_-__-_ __________________.

_ _ - _ _ _ - -

.

..

-,

2

Inspection Summary

. Inspection Conducted July 5 through September 4, 1987 (Report 50-498/87-48;

50-499/87-48)

Areas Inspected:

Routine, unannounced inspection including:

site tours;

followup on 10 CFR Part 21 reports; post-tensioning system; reactor vessel and

internals (records); structural concrete (records); and heating, ventilating,

and air conditioning (HVAC).

Results: Within the six areas inspected, one violation (failure to follow

procedure, paragraph 7.b) was identified.

- _ - _ - - _ _ _ _ - _ _

_ _ - . __. ____ -

___

- _ _ . _ _ _

.4

-.

.

3

DETAILS

1.

Persons Contacted

Principal Licensee Employees

  • J. E. Geiger, General Manager, Nuclear Assurance
  • J. Johnson, Quality Assurance Supervisor
  • A. Mikus, General Supervisor
  • M.- Bunner, Principal Engineer
  • T. J. Jordan, Project Quality Assurance Manager
  • W. P. Evans, Project Compliance Engineer
  • J. Phelps, Project Compliance Supervisor
  • S. Dew, Operations Support Manager
  • J. T. Westermeier, Project Manager

.

  • J. Sabinski, Quality Control Supervisor

Bechtel Power Corporation (Bechtel)

'*L. Hurst,. Project Quality Assurance Manager

  • R. Medina, Lead Quality Absurance Engineer

Ebasco Service Inc. (Ebasco)

  • R. Bedford, Construction. Superintendent

Westinghouse

C. Hahn, Construction Site Manager

Prescon

W. Schneider, Quality Supervisor

In addition to the above, the NRC inspector also held discussions with

other members of the HL&P, Bechtel, Prescon, Westinghouse, and Ebasco

staffs.

  • Denotes those individuals attending the exit interview conducted on

September 4,1987.

l

2.

' Site Tour

l

l

The NRC resident inspectors made routine site tours in order to observe

ongoing work activities and the condition of installed safety-related

equipment and plant status.

These site tours were performed primarily

during normal working hours and on the weekend and backshift periods.

The

following areas for both units were inspected:

fuel handling

,

_

__ -___ ___ _ _

_ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

1

e *

,

4

building (FHB), mechanical and electrical auxiliary building (MEAB),

diesel generator building (DGB), and reactor containment building (RCB).

Within the areas inspected, no violations or deviations were identified.

3.

Followup on 10 CFR Part 21 Reports

The following Part 21 report is considered closed since the item does not

apply to STP.

The subject of the report was environmental qualification

of certain types of circuit breakers which was also reported in

IE Notice (IEN) 83-72 as equipment environmental qualification Notice

<l

'

No. 19.

The NRC inspector verified by review of qualification documents

that this item does not apply to the project.

NRC Log No.

Reporting Vendor

Letter Date

8400551

Rockwell/ITE Gould

031187

IEN 83-72 was closed in NRC Inspection Report 50-498;499/87-40.

4.

Containment Building Post-Tensioning (Unit 2)

l

A field inspection of the ongoing construction activities of the

post-tensioning contractor (Prescon Corporation) was performed in order to

assess the effectiveness of the work and quality control program.

This

inspection included only work on the vertical tendons.

a.

Work Observation

The NRC inspector performed an inspection in the tendon access

gallery and observed the completed and partially completed

installations.

There are 96 vertical tendons that extend over the

dome and are anchored at two points 180 degrees apart.

Seventy-three

vertical tendons have been installed, stressed, greased and covered;

nine are placed in sheaths and 14 are yet to be delivered.

The NRC inspector inspected 146 installed vertical covers for damage,

gasket seating, leaking grease, and grease plugs.

Twenty tendons

which had shop and field-made ends were inspected for buttonheading

and protective greasing.

Two tendons had rusted due to water

intrusion.

These were identified by the licensee and will be handled

according to the disposition of the nonconformance report (NCR) which

was issued describing the condition.

Forty-eight tendon can covers were inspected in the laydown area for

damage,

b.

Records

Six record packages for vertical tendons were randomly selected from

the Prescon files and reviewed for completeness in accordance with

. _ _ _ - _

1

a

l

l

5

l

1

the Prescon procedures.

The reports reviewed were:

receiving

inspection, installation inspection, cutoff inspection,

l

buttonheading, stressing, grease can installation, and greasing

inspection.

The records inspected were for Tendons 2V101, 2V201, 2V213, 2V107,

2V135, and 2V233.

l

The records were complete and in accordance with the procedure from

which they were generated.

c.

Grout Injection

The 1RC inspector and licensee have previously observed water coming

out of some tendon sheaths on the east side of the tendon gallery

which is part of the base mat.

The mat is approximately 18 feet

thick and 186 feet in diameter with a construction joint in the

horizontal plane about 4 feet above the gallery ceiling.

The seepage

is suspected to originate in the construction joint.

Core holes have

been drilled in the area to find the source of water and provide an

entry for pressure injection of chemical grout.

The NRC inspector

witnessed part of the remedial work and determined that the effort

was in accordance with contract Technical Specification FSC061.

The

specification requires the pumping of AC400 chemical grout under the

supervision of Bechtel engineers.

The grout sets up as a semi-hard

gel.

No problems were observed in the repair operation.

This item

is being tracked on hCR BC-03936.

No violations or deviations were identified.

5.

Reactor Vessel and Internal (Records) (Unit 2)

1

The NRC inspector reviewed three traveler packages generated by

Westinghouse pertaining to the reactor vessel internals.

Work performed

I

under these packages included installation of the lift rods, the internal

disconnect device (IDD) pressure housing (including the seal weld), and

'

machining of the upper internal lift rod disconnect assembly.

Records confirmed that the required inspections were performed and

)

inspection hold points were observed.

Records also confirmed that required material certification,

nondestructive tests, and other specification requirements were met.

I

Receipt and storage inspection records were also available in the

traveler.

The records were complete and well formatted for ease of review.

The

record packages reviewed were:

T-THX-262 " Installation of Upper Internal Lifting Rods and Upper

.

Internal Vessel Head and Alignment Pins"

l

- - - _ - - - - - - - - - -

1

,:. .. . .;

t

.-

,

a

T-THX-317 " Internal Disconnect Device Pressure Housing"

.

T-THX-316 " Machining'of the Upper Internal Lift Rod Disconnect

.

Assembly"

No violations ~or deviations were identified.

6.

Structural Concrete (Records) (Unit 2)

The NRC inspector reviewed the structural concrete records of.the

auxiliary feedwater storage tank. . Ten concrete traveler packages were

reviewed.

a.

Installation Inspection Records'

The records confirmed that concrete control, such as production,

placement and the installation of structural components were

performed as specified and that the required inspections (before and

after form removal) were performed.

Essential acceptance criteria

was'also defined.

Cadweld.(a method for joining reinforcing bar ends) records were

available for review and documented for location.

Production cadweld

test results quantitatively indicate that the test results and

acceptance criteria were in accordance with specifications.

The concrete records also confirmed that required weather, physical

protection, and curing conditions were provided and properly

L

monitored during and after the placement.

The NRC inspector also reviewed the concrete cylinder compressive

strength test results, design mix, and the replacement and

post placement inspection records.

b.

Nonconformance/ Deviation Records

Review of the concrete traveler packages indicate that NCRs were

included and adequately addressed by appropriate personnel.

The NCRs

,

were legible, complete, reviewed and signed off by quality control

and engineering personnel.

In conclusion, the structural concrete records reflect work

accomplishments consistent with procedures and specifications.

They

l~

also indicate that the licensee's system for preparing, reviewing,

.and maintaining records is functioning properly. -Concrete records

packages reviewed.were-

CCP-9-AF-S-032-203

CCP-9-AF-W-045-201

.

.

CCP-9-AF-S-023-201

CCP-9-AF-W-056-201

1

.

.

CCP-9-AF-S-023-203

CCP-9-AF-W-069-201

{

.

.

CCP-9-AF-S-032-201

CCP-9-AF-W-020-201

.

.

!

l

i

,

i

!

o--_

.

.

j

.

.--

- -

-

-

.-

. _ _ _ _

_ - _ _ _ _ - _ _ _ _ -

_ _ _ - - _ _ .

_ _ _ _ _ _

. _ _ _ - -

__

_

-

-

- _ _ _ _ _ _ _ _ _ - - _

p

1'

.c

.

..

7

~

CCP-9-AF-W-023-201

CCP-9-AF-W-020-203

.

.

L

CCP-9 AF-S-034-201

CCP-9-AF-W-022-001

.

.

CCP-9-AF-W-022-203

.

No violations or deviations were identified.

7.

Heating, Ventilating and Air Conditioning (HVAC) (Unit 2)

The NRC inspectors through dimet observation, interviews, and independent

evaluation of work performance, and work in progress have determined that

the work on safety-related HVAC systems is generally accomplished in

accordance with licensee procedures and engineering specifications.

a.

Personnel Interviews

The NRC inspector interviewed three craft personnel in order to

assess their qualifications in the area of installation of HVAC

supports and duct work.

Discussions with these craft indicated that

they were trained in the installation requirements to perform their

given task.

The foreman was knowledgeable of the inspection

requirements, installation requirements and hold points.

The welders

were qualified to the weld procedure used.

b.

,Iy tallation Activities

The NRC inspector witnessed inprogress work on HVAC

Support 2-6-0128-S071 in HVAC equipment Room No. 206 and portions of

the control room envelope system (HB01) in the electrical auxiliary

building (EAB).

Inspection of Support 2-6-0128-S071 indicated that

the craft were using the latest drawing revision and work procedure

for installation.

Work completed was in accordance with installation

drawings and field change request (FCR).

Inspection of duct sections

of the control room envelope system indicated that orientation and

configuration was in accordance with the drawings; however, the

installation of bolts was not in accordance with the applicable

specification, 5V279VS1003, Revision 7, paragraph 3.12 as reference

by Procedure SSP 38.

The specification states, " Bolts and nuts for

galvanized ductwork shall be hot-dipped galvanized, cadmium plated,

or electromagnetic zinc-coated.

Hot-dipped galvanized nuts shall

only be used with hot-dipped galvanized bolts.

This is because the

galvarized bolts are sized differently than the other bolts and

proper fastening cannot be assured when the nuts and bolts are

improperly matched.

Cadmium plated, and electromagnetic zinc-coated

nuts may be used with either cadmium plated or electromagnetic

zinc-coated bolts."

The NRC inspector fousd that galvanized nuts were interchanged with

(;1ectromagnetic zinc-coated bolts, and galvanized bolts with

electromagnetic zinc-coated nuts.

This is an apparent violation of

the procedure / specification (499/8748-01).

It was noted that this

problem had been brought to the attention of HL&P in NRC Inspection

1

l

i

_

_ - _- ____- _____ , _ _

_ _ _ -

- _ _ - - - _ - _ _ - _ .

. _ _ - _ _ _ -

  • &

,

,

8-

Report ~50-498/86-31 at which time prompt but apparently incomplete

'

corrective action was taken.

In conjunction with the above observations, the NRC inspector also

reviewed the following traveler packages:

2658200/55-S133

2-6-0055-202

.-

.

2658200/55-5093

. .

2-6-0055-S056

.

2658200/55-P206

2658200/55-S056

.

.

2658200/55-P207

.

. 2658200/55-5058

.

2658200/55-P208

2658200/55-S134

..

.

2-6-055-973-

2-6-0055-5097

.

.

2658200/55-P203

.

c.

HVAC Fabrication Shop

The NRC inspector performed an inspection of the HVAC fabrication

shop to determine if fabrication practices were properly. followed.

The inspector reviewed three traveler packages.for the duct sections

inspected. These were inspected for workmanship, size, shape,-

drawing detail, and weld quality. The fabrication travelers examined;

for these sections were:

2-6-055-985

.

'2-6-0144-294

.

.-

2-6-0144-144

Except' as noted above no violations or deviations were identified.

~

'8.

Exit Interview

The NRC inspectors met with the licensee (denoted in paragraph 1) on

September 4, 1987, and summarized the scope and findings of this

inspection.

/

,

3

0.'

_ - _ _ _

_ _ ,

._

. -

.

. .. ..

.

.

. s.

,

s.

.

'

.

&

,

i

r

.

.

,

,

.

,

l

El O tr tji d3S W

,

I

l

S0-38Ngn

'

s

.

i

1

(

..

_ - - - - - - - - - - - -

-

.