ML20234E692

From kanterella
Jump to navigation Jump to search
Insp Rept 50-285/87-13 on 870501-31.Violations Noted:Failure to Control Special Processes During Installation of Seismic Wall Supports
ML20234E692
Person / Time
Site: Fort Calhoun 
Issue date: 06/30/1987
From: Gilbert L, Harrell P, Hunter D, Ireland R, Mullikin R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20234E655 List:
References
50-285-87-13, NUDOCS 8707070649
Download: ML20234E692 (29)


See also: IR 05000285/1987013

Text

.

i

APPENDIX B

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Inspection Report:

50-285/87-13

License:

DPR-40

Docket:

50-285

Licensee: Omaha Public Power District (0 PPD)

1623 Harney Street

Omaha, Nebraska 68102

Facility Name:

Fort Calhoun Station (FC)'

Inspection At:

Fort Calhoun Station, Blair, Nebraska

Inspection Conducted:

May 1-31, 1987

WM

M

!l[!$7

Inspectors:

.

P. H. Harrell, Senior Resident Reactor

Date

Inspector

12 f W A -

wirdn

R. P. Mullikin, Project Inspector, Reactor

Date ~

Project Section B

Sf/WV7

L. DI Gi4bert, Reactor Inspector, Engineering

Date

'

Section

Other

3

Accompanying

1

Personnel:

V. Ferranini, NRC Consultant

'

Approved:

/ Mf/tjImmau;#-

4// 7/F7

g' R. E. Ireland, Chief, Engineering Section

Ddte '

Reactor Safety Branch

Y

hko

7

,

pD: R. Hunter, Chief, Reactor Project

Fate /

'/

Section B, Reactor Projects Branch

8707070649 870630

gDR

ADOCK 05000285

PDR

,

,

2

i

Inspection Summary

Inspection Conducted May 1-31, 1987 (Report 50-285/87-13)

Areas Inspected:

Routine., unannounced inspection including operational safety

verification, maintenance, s. surveillance, plant tours, safety related system

walkdown, security observations, radiological protection observations,

in-office review of periodic and special reports, followup on previously

identified items, followup on allegations related to welding, review of the

program for installation of heat-shrinkable tubing, review of licensee actions

related to reactor vessel transient protection, verification of containment

integrity, review of modification testing for a containment equipment storage

platform, review of the licensed operator training program, and containment

local leak rate testing.

Results: Within the 16 areas inspected, 1 violation (failure to control

special processes during installation of seismic wall supports, paragraph 11)

was identified.

!

l

'

'

]

4

3-

l

1

l

DETAILS

l

l

i

1.

Persons Contacted

  • + W. Gates, Plant Manager
  • + C. Brunnert, Supervisor, Operations Quality Assurance

M. Butt, Electrical Engineer

M. Core, Supervisor, Maintenance

+D. Dale, Quality Control Inspector

T. Dexter, Supervisor, Security

  1. J. Fluehr, Supervisor, Station Training
  • J. Foley, Supervisor, I&C and Electrical Field Maintenance
  1. J. Gasper, Manager, Administrative and Training Services

J. Kecy, Acting Reactor Engineer

+R. Kotan, Engineer, Generating Station Engineering

L. Kusek, Supervisor, Operations

  • +# D. Munderloh, Plant Licensing Engineer
  • + T. McIvor, Supervisor, Technical
  • + rs . Mueller, Plant Engineer

i

G. Roach, Supervisor, Chemical and Radiation Protection

l

+J. Skiles, Contract Welding Engineer, Sargeant and Lundy

S. Willrett, Supervisor, Administrative Services and Security

i

The NRC inspector also contacted other plant personnel, including operators,

technicians, and administrative personnel.

  • Denotes attendance at an exit interview given in the areas of

low-temperature overpressure protection and installation of

heat-shrinkable tubing by R. Mullikin on May 8,1987.

+ Denotes attendance at an exit interview given in the area of followup on

j

welding allegations by L. Gilbert on May 29, 1987.

  1. Denotes attendance at an exit interview given in the area of

licensed-operator training by P. Harrell on May 30, 1987.

Denotes attendance at the monthly exit interview given by P. Harrell on

June 1, 1987.

2.

Followup on Previously Identified Items

a.

(0 pen) Unresolved item 285/8624-03:

Failure to provide a preplanned

lecture serier en energency operating procedures (EOP).

The NRC insp&ctor reviewed the schedule of the lectures given by the

licensee's t eining department to determine if a lecture series was

given on E0Ps in 1985 or 1986.

The schedule indicated that no

lecture series had been given.

_ _-_

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __

.-

-

_

_

.

.

4

Subsequent to the issuance of this unresolved item, the licensee

provided

actures on some, but not all E0Ps, during simulator

training given in the early part of 1987.

During discussion of this

item with licensee personnel, they stated that a series of lectures

would be given during the next training rotation.

This item remains open pending completion of a series of lectures on

E0Ps and the establishment of a program by the licensee to ensure

that E0P lectures are given in each 2 year requalification training

cycle.

b.

(Closed) Unresolved Item 285/8624-04:

Remedial training not given

for licensed operators failing weekly quizzes.

The NRC inspector reviewed selected weekly quizzes given during 1986

to identify any individuals failing to pass a quiz.

During the

review, two individuals were identified.

In both cases,.the licensee

provided objective evidence that the individuals had been given

remedial training.

Discussions by the NRC inspector with the

individuals involved confirmed that they had received the remedial

training.

c.

(0 pen) Deviation 285/8702-01:

Administrative control of containment

isolation valves.

A review was performed to verify that the valves (MS-101, MS-103,

CH-517. CH-518, CH-535, SI-375, AC-1133, AC-1134, AC-857, and AC-858)

.

identified in NRC Inspection Report 50-285/87-02 were placed under

administrative control.

In addition to the valves. listed above, the

NRC inspector also identified, in subsequent reviews after issuance

of NRC Inspection Report 50-285/87-02, additional valves -(VD-504,

VD-505, WD-1060, and 51-185) that provided containment isolation and

should also be placed under administrative controls.

To ensure that the valves had been physically locked or seal-wired

shut prior to plant startup, the NRC inspector performed a walk down

to determine the status of all the valves.

The results of the

walkdown confirmed that the valves were either locked or seal-wired

shut.

The NRC inspector reviewed various procedures and drawings to verify

that the valve status (i.e., locked or seal-wired shut) had been

correctly provided in the appropriate documentation.

A list of the

dot.umentation reviewed is provided below.

j

Reactor Startup Locked Valves (Procedure OI-RC-2B-CL-D,

j

.

Revision 47)

i

High-Pressure Safety Injection System Startup Valve Checklist

.

(Procedure 01-SI-1-CL-B, Procedure Change 20432)

- _ _ _ _ _ _ _ _ - _ - -

.

.

Component Cooling Water Valve Lineup (Procedure 01-CC-1-CL-A,

j

.

Revision 21)

Chemical and Volume Control System Valve Lineup

4

.

(Procedure 01-CH-1-CL-A, Revision 29)

{

Main Steam System Valve Lineup (Procedure OI-MS-1-CL-A,

.

Revision 12)

Waste Disposal System Startup Valve Checklist

.

(Procedure 01-WDL-1-CL-G, Procedure Change 20434)

Safety Injection and Containment Spray System

i

.

(Drawing E-23866-210-130, Sheet'1, Revision 40)

Steam Flow Diagram (Drawing M-252, Revision 46)

.

Chemical and Volume Control System Diagram

.

.

(Drawing E-23866-210-120, Sheet 2, Revision 21)

4

Waste Disposal System Flow Diagram (Drawing M-6, Revision 29)

a

.

Auxiliary Coolant Component Cooling System Diagram

.

(Drawing M-40, Sheet 1, Revision 18)

During review of the documentation listed above, the~ NRC inspector

noted that the licensee had not completed procedure and/or drawing

f

changes to reflect the required locked or seal-wired shut position

for all the valves identified above prior to the end of this

i

I

inspection period.

Licenses personnel stated that the documentation

'

l

changes would be made in the near future.

This item remains open pending completion of documentation changes.

d.

(Closed) Open Item 285/8702-04:

Ultrasonic testing (UT) of

Dalance-of plant (BOP) piping.

The licensee established an aggressive program for performance of UT

l

on the B0P piping for detection of pipe wall thinning.

The program

I

requirements were provided in Procedure PM-PIPE-1, " Ultrasonic

l

Inspection of Station Piping," which specified that a total of 186

locations be inspected.

The locations were selected by engineering

personnel in single- and two phase system piping where thinning would

most likely occur.

!

The results of the UT performed by the licensee indicated that 15

locations were identified where the pipe wall had thinned below the

minimum acceptable wall thickness.

In addition, the licensee also

identified three additional locations where the licensee opted to

1

_ _ _ _ - _

_ _ _ - _ - _ _ _ _

_ - - _ _ _ _ _ _ .

. - _ _ - _ _ .

.

.

--

.

.

6

l

l

replace the piping even though the piping was not below the minimum

l

acceptable wall thickness.

The licensee replaced the piping at the

18 locations during the current refueling outage.

i

The areas identified were located in ti.e feedwater pump discharge and

recirculation piping, heater drain pump discharge piping, feedwater

,

heater drain and vent piping, and steam extraction piping.

The

I

thinning occurred in straight pipe runs and in piping elbows,

and in

I

single- and two phase systems.

There did not appear to be a common

j

set of plant operating conditions or a pipe configuration that would

1

pinpoint where pipe thinning might occur.

'

By performance of this testing, the licensee established a baseline

for the pipe thickness at the various locations inspected.

By

establishing a baseline, the licensee will be able to determine the

actual thinning rate when the locations are retested during the next

i

refueling outage.

This information will enable the licensee to more

accurately predict which piping will require replacement.

!

The NRC inspector reviewed the results of the ilT inspections

performed by the licensee.

It appeared that the licensee had

,

performed an inspection that identified piping where excessive

thinning had occurred.

e.

(Closed) Open Item 285/8703-02:

Licensed operators not reviewing

licensee event reports (LER) in a timely manner.

The licensee established a program to ensure that LERs are reviewed

by licensed operators in a timely manner.

This program required that

LERs related to plant operations be distributed to all licensed

operators upon receipt in the training department by using the

established training hot-line system.

Each operator receives a copy

of the LER, reads it, signs the hot-line form, and then returns the

form to the training department.

The training department records the

receipt of the hot-line form for verification that the LER was

reviewed by each operator.

l

The NRC inspector reviewed the status of the hot lines issued and

l

returned for selected LERs to verify that the LERs were being

reviewed by the operators in a timely manner.

No problems were

noted.

p

l

f.

(Closed) Unresolved Item 285/8710-04:

The surveillance test

performed on the trisodium phosphate dodecahydrate (TSP.) did not meet

i

the requirements stated in the Technical Specifications (TS).

The licensee performed another test of the 1SP in the containment

baskets.

The test was performed on May 31, 1987, using a new

l

revision to Procedure ST-CHEM-2-F.3, " Phosphate Basket Inspection."

'

'

The results of the retest indicated that the TSP was chemically

capable of performing its intended safety function.

I

,

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ . . _ _ _ _ _ _ _ . . _ _ _ _ _ _ _ _

_ _ _ _ _ _

__

!

.

.

7

As mentioned above, the licensee revised Procedure ST-CHEM-2-F.3 to

provide additional clarification on how to properly test the TSP.

The clarifications provided specific step-by-step instructions to

ensure that the variables used in performing future tests are within

the allowable limits provided in the TS.

The NRC inspector reviewed the results of the retest and the

procedural changes made by the licensee.

Based on this review, it

appeared that the licensee had established a program for testing of

l

TSP that would ensure future testing activities will be performed in

accordance with TS requirements.

.

g.

(0 pen) Unresolved Item 285/8710-05:

Apparent discrepancy between the

TS and the Updated Safety Analysis Report (USAR) regarding the amount

of TSP to be stored in containment.

The licensee performed a preliminary calculation prior to plant

'

,

startup from the current refueling outage to determine the amount of

TSP that was required to be stored in containment.

The calculation

i

was based on the volume of borated water used if the injection system

I

was placed in the recirculation mode.

The results of the calculation

indicated that the minimum amount of TSP needed in containment was

'

3000 pounds.

This was the value specified in the USAR.

TS 3.6(2).d.(ii) states that the minimum amount of . TSP required in

t

containment is 40 cubic feet.

Based on the preliminary calculation

performed by the licensee, it appeared that 40 cubic is

I

nonconservative.

The licensee determined that a volume of 50 cubic

feet would be required to provide approximately 3000 pounds of TSP.

The determination of the conversion factor for cubic feet of TSP to

i

pounds of TSP was based on field measurements of the TSP contained in

I

the containment baskets. The conversion factor was empirically

l

determined to be approximately 60 pounds per cubic foot.

The

i

licensee measured the amount of TSP currently stored in containment

)

and determined the value to be approximately 61 cubic feet.

The NRC inspector reviewed the preliminary calculation performed by

the licensee and determined that the calculation properly concluded

the amount of TSP presently stored in containment was adequate.

Licensee personnel stated that the final calculation package,

I

complete with supporting material, would be completed.in the near

l

future.

In addition, licensee personnel stated that an amendment to

the TS would be submitted to correct the TSP volume requirements

i

presently provided in TS 3.6(2).d.(ii).

l

'

This item will remain open pending completion of the forma)

calculation package and approval of a TS amendment by NRC

Headquarters to clarify the requirements related to storage of TSP in

containment.

l

___--_ ______ - - _-__ -

.

.

8

3.

Operational Safety Verification

The NRC inspector conducted reviews and observations of selected

activities to verify that facility operations were performed in

conformance with the requirements established under 10 CFR, administrative

procedures, and the TS.

The NRC inspector made several control room

observations to verify the following:

Proper shift staffing

.

Operator adherence to approved procedures and TS requirements

.

Operability of reactor protective system and engineered safeguards

.

equipment

Logs, records, recorder traces, annunciators, panel indications, and

.

switch positions complied with the appropriate requirements

Proper return to service of components

.

!

Maintenance orders (MO) initiated for equipment in need of

.

maintenance

Appropriate conduct of con' trol room and other licensed operators

.

Management personnel toured the control room on a regular basis

.

No violations or deviations were identified.

4.

Plant Tours

The NRC inspector conducted plant tours at various times to assess plant

and equipment conditions.

The following items were observed during the

tours:

'

Generalplantconditionb,includingoperabilityofstandbyequipment,

.

were satisfactory.

Equipment was being maintained in proper condition, without fluid

.

leaks and excessive vibration.

Plant housekeeping and cleanliness practices were observed, including

.

no fire hazards and the control of combustible matraial.

Performance of work activities was in accordarce with approved

.

procedures.

Portable gas cylinders were properly stored to prevent possible

.

missile hazards.

-

_ _ _ _ _ _ _ _ _ - - _ _ _ _ _ _ - _ _ -

- _ _ _ _ - - _ _ _ _ _ - _ _ _ - _ _ _

- _ _ .

.

.

9

Tag out of equipment was performed properly.

.

Management personnel toured the operating spaces on a regular basis.

.

The NRC inspector toured the containment building just prior to closing

the building in preparation for plant startup from a refueling outage.

No

problems were noted during the tour.

,

No violations or deviations were identified.

5.

Safety-Related System Walkdown

The NRC inspector walked down accessible portions of the following

safety-related system to verify system operability.

Operability was

determined by verification of selected valve and switch positions.

The

system was walked down using the procedure noted.

Reactor startup locked valves-(0I-RC-28-CL-D, Revision 47)

.

During the walkdown, the NRC inspector noted no problems between the

procedure and plant as-built conditions for the selected areas checked.

No violations or deviations were identified.

6.

Monthly Maintenance Observations

The NRC inspector reviewed and/or observed selected station maintenance

activities on safety-related systems and components to verify the

maintenance was conducted in accordance with approved procedures,

regulatory requirements, and the TS.

The following items were considered

during the reviews and/or observations:

The TS limiting conditions for operation were met while systems or

.

components were removed from service.

Approvals were obtained prior to initiating the work.

.

Activities were accomplished using approved M0s and were inspected,

.

as applicable.

Functional testing and/or calibrations were performed prior to

.

returning components or systems to service.

Quality control records were maintained.

.

Activities were accomplished by qualified personnel.

.

Parts and materials used were properly certified.

.

Radiological and fire prevention controls were implemented.

.

_ - _ _ _ _ _ _ _ _ - _ _ _ _ _ - _ _ _ _

_ _ _ _ _ _ _ - _ _ _ - _ - .__

- _ _ _ _ _ _ _ - _ _ _ _ - _

. _ _ _ --___ - --_

1

.

.

10

l

!

The NRC inspector reviewed and/or observed the following maintenance

l

activities:

l

Inspection of Raychem splices (M0 870154)-

.

Repair of a 480-volt breaker trip device (M0 870974)

l

.

Repair of a heat tracing recorder (M0 872317)

.

Repair of a packing leak on a component cooling water valve

.

(M0 870979)

Repair of a toxic gas monitor (M0 870080)

.

Inspection of the emergency diesel generator fuel oil storage tank

.

(M0 870462)

Trouble shooting of an inverter (M0 872768)

.

No violations or deviations were identified.

7.

Monthly Surveillance Observations

The NRC inspector observed selected portions of the performance of and/or

reviewed completed documentation for the TS required surveillance testing

,

'

on safety-related systems and components.

The NRC inspector verified the

following items during the testing:

Testing was performed by qualified personnel using approved

.

procedures.

l

Test instrumentation was calibrated,

l

.

The TS limiting conditions for operation were met.

.

Removal and restoration of the affected system and/or component were

I

.

accomplished.

Test results conformed with TS and procedure requirements.

.

Test results were reviewed by personnel other than the individual

.

directing the test.

'

Deficiencies identified during the testing were properly reviewed and

.

resolved by appropriate management personnel.

The NRC inspector observed and/or reviewed the documentation for the

following surveillance test activities.

The procedures used for the test

activities are noted in parenthesis.

Emergency diesel generator annual overhaul (ST-ESF-6-F.5)

.

_ _ _ - - _ _ _ _ _ - _ - _ _ _ _

1

.

.

11

I

Fuel transfer tube leak rate determination (ST-CONT-2-F.4)

.

!

Containment pressure channel check (ST-ESF-3-F.2)

.

1

Containment air cooling and filtering system circuit operation

l

.

,

(ST-VA-1-F.2)

{

1

No violations or deviations were identified.

)

!

l

8.

Security Observations

'

The NRC inspector verified the physical security plan was being

i

implemented by selected observation of the following items.

The security organization was properly manned.

f

.

1

Personnel within the protected area (PA) displayed their

j

.

identification badges.

4

Vehicles were properly authorized, searched, and escorted or

.

controlled within the PA.

,

Persons and packages were properly cleared and checked before entry

.

into the PA was permitted.

}

The effectiveness cf the security program was maintained when

J

.

security equipment failure or impairment required compensatory

1

measures to be employed.

The PA barrier was maintained and the isolation zone kept free of

.

transient material.

!

The vital area barriers were maintained and not compromised by

l

.

breaches or weaknesses.

Illumination in the PA was adequate to observe the appropriate areas

.

at night.

'

1

I

Security monitors at the secondary and central alarm stations were

.

functioning properly for assessment of possible intrusions.

No violations or deviations were identified.

9.

Radiological Protection Observations

The NRC inspector verified that selected activities of the licensee's

radiological protection program were implemented in conformance with the

facility policies and procedures and in compliance with regulatory

requirements.

The activities listed below were observed and/or reviewed:

__________ - __ - _ _ _ _-

__

--

,

.

.

I

i

12

Health physics (HP) supervisory personnel conducted plant tours to

.

check on activities in progress.

1

!

Radiation work permits contained the appropriate information to

.

ensure work was performed in a safe and controlled manner.

Personnel in radiation controlled areas (RCA) were wearing the

.

required personnel monitoring equipment and protective clothing,

l

Radiation and/or contaminated areas were properly posted and

.

controlled based on the activity levels within the area.

,

1

Personnel properly frisked prior to exiting an RCA.

.

No violations or deviations were identified.

10.

In-office Review of Periodic and Special Reports

In-office review of periodic and special reports was performed by the NRC

resident inspector and/or the Fort Calhoun project inspector to verify the

following, as appropriate:

Reports included the information required by appropriate NRC

.

requi rements.

Test results and supporting information were consistent with desig,'

.

predictions and specifications.

Determination that planned corrective actions were adequate 1or

.

resolution of identified problems.

Determination as to whether any information contained in the report

.

should be classified as an abnormal occurrence.

The following reports were reviewed:

April monthly operating report, dated Mey 13, 1987

.

Monthly operations report for April, undated

.

Additional information on Auxiliary Feedwater System reliability

.

analysis, dated May 18, 1987

During review of reports, NRC personnel identified 10 CFR Part 21 reports

submitted by suppliers or vendors that appeared applicable to the licensee's

facility. The NRC resident inspector provided copies of these reports to

<

the' plant licensing engineer for review of applicability by the licensee.

The reports provided are listed below.

,

l

i

.

.

.

13

1

A letter dated February 10, 1987, from the Sacramento Municipal

.

Utility District regarding warped gear limit switch rotors in

Limitorque valves

A letter dated February 17, 1987, from the Foxboro Company related to

.

problems identified in Spec 200 current-to-voltage cards stored in a

high moisture environment

A letter dated January 28, 1987, from Virginia Electric and Power

.

Company regarding defective steel columns provided by the Rockwell

Engineering Company

A letter dated January 13, 1987, from the Morrison-Knudsen Company

.

regarding the failure of a 130-Vdc relay in an emergency diesel

generator control circuit

1

A letter dated March 30, 1987, from Isomedix related to the

.

measurement tolerance associated with the dose and dose rate values

!

certified in test reports

A letter dated March 2,1987, from the Arizona Nuclear Power Project

I

.

regarding a fire in the emergency diesel generator injection tube

l

A letter dated November 25, 1986, from Basler Electric related to

.

cracking of 0-rings on the latch mechanism on the emergency diesel

generator contactors

A letter dated January 12, 1987, from Cooper-Bessemer regarding a

.

failure of the master power rod in the emergency diesel generator

No violations or deviations were identified.

'

11. Followup on Allegations Related to Welding by a Contractor

(Reference 4-87-A-012 and 4-87-A-018)

NRC inspectors performed a followup on allegations related to welding

performed on safety-related seismic supports for masonry walls in the

auxiliary building and on a containment storage platform. The welding was

performed by a licensee contractor, Fuel Econonly Company.

During performance of the followup, the NRC inspectors reviewed

documentation for installation of the containment platform and the seismic

wall supports.

The documentation reviewed by the NRC inspectors are

listed below.

Modification Request (MR) FC-81-180, " Structural Modification of

.

Concrete Masonry Walls in the Auxiliary Building"

MR-FC-83-05, " Storage of Equipment in Containment"

.

l

_ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . - _ _ _ _

_ _ . _ _

_

_

,

.

.

,

i

14

)

l

Welder qualification records for welders employed by the Fuel Economy

.

Company

Weld inspection records for welds associated with MR-FC-81-180 and

.

MR-FC-83-05

Anchor support data sheets completed for installation of concrete

.

anchors for MR-FC-81-180

Safety-Related Design Change Order (SRDCO) 84-73 and SRDC0-85-41,

.

installation instructions for MR-FC-81-180

Purchase Order (P0) 70639, for the purchase of hex-head bolts used

.

j

for installation of the seismic wall supports

SRDC0-87-25, installation instructions for MR-FC-83-05

.

The allegations reviewed by the NRC inspectors are discussed below.

This

inspection was performed to establish the validity of the allegations, and

to take enforcement actions, if appropriate.

This inspection considered

only the technical aspects for the items reviewed.

No other aspects were

considered during the inspection.

An unqualified welder dressed up or rewelded field welds performed by

.

qualified welders on the seismic wall supports so the welds would

pass a quality control (QC) inspection.

This item was not substantiated due to a lack of specific information

as to the location of the welds.

However, the NRC inspectors

verified that the welder redoing the field welds was qualified to

perform the welding.

Therefore, the dressing up or rewelding of the

welds, if it occurred, would be technically acceptable.

Welds installed on the seismic wall supports did not meet the

.

requirements stated in the design installation instructions.

In an inspection performed in March 1987 the NRC inspector verified

that welding on the seismic wall supports was not being performed in

accordance with documented instructions.

An apparent violation was

3

identified in NRC Inspection Report 50-285/87-08.

During this inspection, the NRC inspectors examined the butt welds

used for installation of portions of the seismic wall supports.

During examination of the welds, the NRC inspectors noted that four

square-butt welded joints did not exhibit full-thickness penetration

as required by the weld symbol on the design drawing.

The four butt

welds were installed to connect Support Members CORR-NS-1 to

,

CORR-NS-2, CORR-NS-2 to CORR-NS-3, CORR-NS-3 to CORR-NS-4, and

'

CORR-NS-4 to CORR-NS-5.

i

!

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ . _ _ _ _ . . _ _ _ _ _ _ _ _ _

.

,

15

In addition to the. inadequate weld penetration, the design

installation requirements provided in Design Document MR-FC-81-180

i

stated that welding shall be accomplished in accordance with

AWS D1.1-83.

The welding procedure used for installation of the

square butt welds was not qualified to AWS 01.1-83.

The use of a

welding procedure that was not qualified to the requirements stated

in the design document is a failure to control the special processes

used for installation of safety-related structures.

This is an

i

apparent violation.

(285/8713-01)

)

I

The licensee performed an engineering evaluation on the butt-welded

i

joints, as installed, and determined that the joints would perform

their intended safety function.

Based on the results of the

evaluation, no reinspection or weld repairs were to be performed by

the licensee.

When incorrect (i.e., didn't meet design installation requirements)

.

welds were installed on seismic wall supports, the engineer would

change the requirements in the design documentation so the welds

would be acceptable.

This item was substantiated.

The engineer changed the original

requirements so that welds would be acceptable.

Since the engineer

used the established design change control-procedure to change the

weld acceptance criteria, this method of changing design requirements

is considered technically acceptable.

A seismic support for a safety-related cable tray was notched during

.

installation to avoid an existing obstruction.

Notching of the

support was contrary to the design installation instructions.

Due to the lack of specific information related to this item as to

the location of the tray support, no resolution of this item could be

determined.

However, during review of supports in the field, the NRC inspectors

noted five areas where cable tray supports had been notched.

One

notch extended approximately 50 percent into the support.

In

discussions with a licensee engineer, it was determined that the

supports were not installed by instructions provided in MR-FC-81-180.

The engineer stated that a review of the appropriate documentation

would be performed to verify that the notches identified were

authorized by the installation instructions.

This item remains open

pending the resolution of the identified concerns related to notching

)

of supports and a review of the resolution by an NRC inspector.

(285/8713-02)

Bolts were used for installation of seismic tie-back braces that were

.

not verified to be critical quality equipment (CQE) material.

i

_ _ - _ - _ _ _ _ - _ _

i

i

t

.

.

16

No specific intornation was provided as to the exact location of the

a

non-CQE bolts.

For this reason, this item could not be substantiated

{

as being done during installation of the supports.

The NRC inspectors examined bolts that had been used for-installation

l

l

of the supports in the general area identified in the allegation.

This review confirmed that the material (A-325) of the installed

bolts was the same material as was specified by P0 70639.

The bolts

{

were not marked to identify them as CQE material;.therefore, no

determination could be made to verify that the bolts had been receipt

j

inspected by the quality assurance (QA) organization.

The licensee's

'

QA program does not require the marking of each bolt after receipt

inspection.

While drilling holes for installation of seismic wall support

.

anchors, rebar would be hit inside the concrete.

The installation

documentation required that the hole be filled if rebar was

encountered and another hole drilled.

q

1

Due to a lack of specific information as to where the holes were

located, this allegation was not substantiated.

The NRC inspectors

reviewed selected anchor installation support data sheets to verify

that a preload torque was applied to the anchors.

By application of

a preload torque, it can be verified that the anchor is properly

installed in the hole.

For the selected data sheets reviewed, no

instances were noted where the preload torque was not properly

applied.

Based on this review, it appeared that the anchors were

properly installed.

The NRC inspectors also reviewed MR-FC-81-180 for requirements

associated with installation of the anchors.

No requirement could be

4

found that stated holes were to be filled if rebar was encountered

J

when drilling.

Non-CQE filler material was used to fill abandoned bolt holes in

.

structural seismic wall components.

i

l

Due to a lack of specific information, this allegation could not be

!

substantiated.

However, during field inspection of the supports, the

l

NRC inspectors noted two unfilled bolt holes in a structural I-beam.

j

,

A licensee engineer stated that an analysis had not been performed to

determine the affect of the holes on the strength of the structural

l

member.

This item remains open pending a review of the licensee's

ccmpleted evaluation by an'NRC inspector.

(285/8713-03)

!

l

l

Holes through concrete block walls were enlarged to allow alignment

.

with holes in the seismic wall supports.

]

During field inspections performed by the NRC inspectors, enlarged

holes in concrete blocks were identified in several locations.

An

evaluation of the affect of the holes on the structural integrity of

i

l

>

.

.

17

i

the wall was performed and it was determined that the enlarged holes

'

did not affect the strength of the wall.

Angle iron used to firm the angle between the ceiling and the wall

l

.

for seismic support was installed too low to provide proper support.

l

l

This allegation was not substantiated due to a lack of specific

'

information as to the location of_the angle iron.

The NRC inspectors

reviewed selected locations where angle iron had been installed to

verify it had been installed in accordance with the design

installation instructions.

No problems were noted during this

review.

Non-CQE material was used to plug abandoned holes in the base plates

l

.

!

of the containment equipment storage platform.

This item was substantiated.

A review of the use of the non-CQE

l

material was performed by a licensee engineer and found to be

1

l

technically adequate.

A review'of the design change that allowed use

!

of non-CQE material was performed by the NRC inspectors.

The review

confirmed that the use of non-CQE material was technically

appropriate.

,

l

l

Plug welds were performed on the containment structure using

.

uncontrolled weld material.

l

This item was not substantiated.

The NRC inspectors reviewed the

L

l

records of weld material used on all containment platform welds.

The

l

review indicated that all weld material was traceable to a heat

j

number.

The licensee issued three operations incident reports (0I 2811, 2812, and

2813) for the violation and two open items identified in this section of

this report.

By issuing the OIs, the licensee will ensure that the

discrepancies identified by the NRC inspectors will receive timely review

and closeout.

During review of the allegations listed above, the NRC inspectors

j

identified concerns related to licensee activities involved with

installation of design changes.

Although not cited as violations or

deviations, the licensee should strongly consider taking appropriate

actions to address these apparent weaknesses.

Emphasis should be placed on meeting all the requirements of the

.

fabrication code.

Improper fabrication practices should not be

tolerated and poor workmanship should be repaired to meet the intent

of the fabrication code.

Engineering evaluations should not be used

as an alternative to compliance with a fabrication code.

The modification program should place more emphasis on the need for

.

craftspersons to ensure quality work is performed at the time of

.

.

18

installation.

The present program relies too much on QC inspections

ensuring that quality was built into the installations.

Emphasizing

the need to build quality into the installation at the time of

fabrication will eliminate unnecessary repairs when QC personnel

perform inspections of the final product.

Design change installation packages issued to the craftspersons do

.

not contain a sufficient level of detail to provide appropriate

instructions as to what work the craftsperson should or should not

perform.

The installation packages should contain a statement that no work may

.

be porformed if not specifically addressed in the installation

instructions.

The craftsperson should be directed to. contact the

engineer if any questions arise so a formal design change may be

properly completed.

The installation packages should provide specific acceptance criteria

.

in words that the craftsperson and QC inspector can easily

understand.

The welder qualification process used by QC needs closer supervision

.

to verify that welders are being qualified to established

l

requirements and that the documentation of qualification is

l

adequately maintained.

l

Contract QC personnel used during outages to support the licensee's-

.

normal QC staff should receive substantial indoctrination training to

ensure that these contract personnel understand how the

administrative controls used at the Fort Calhoun Station (FCS) work.

During the exit interview held on this portion of this inspection, the NRC

inspectors discussed the concerns listed above with licensee management

personnel.

Management personnel stated that the items would be reviewed

for possible inclusion in their current programs.

12.

Review of the Program for Installation of Heat-Shrinkable Tubing

The NRC inspector reviewed the licensee's program for the installation and

inspection of heat-shrinkable tubing used on electrical splice connections

!

and terminations.

This review was performed in response to the issuance

of IE Information Notice (IEN) 86-53, " Improper Installation of

Heat-Shrinkable Tubing," by the NRC on June 26, 1986.

IEN 86-53 was

issued to alert licensees to problems encountered at some plants with the

installation of splice connections manufactured by Raychem.

The licensee established a program'for inspection of Raychem splice

connections based on the information provided in IEN 86-53 and implemented

the program in MO 870154, " Inspection of Raychem Splices." The

established program required that a 100 percent inspection of all

!

safety-related splice connections in a harsh environment be performed

i

I

- _ _ _ _ _ _ - _

. _ _ _

. _ _ _ _ _ _

__

_

.

.

i

19

during the 1987 refueling outage.

The program also required that all'

inspections be performed by a team of at least two individuals, one from

engineering and one from QC.

Prior to initiating the inspection and repair of the Raychem splice

connections, the licensee brought a Raychem representative onsite to

instruct and train several licensee employees on how to properly inspect

and install the splice connections.

These licensee employees, in turn,

trained all other remaining personnel involved in inspection and

installation activities, on the proper methods to be used.

During inspection of the previously installed splices, the licensee

inspection teams determined that approximately 245 splice connections had

been improperly installed.

All the splice connections were located in the

flexible conduit attached to ASCO solenoid-operated valves.

Themajor

problem with these connections was that the minimum bend radius for the

splices had been exceeded.

The rejected splices were repaired using

instructions provided in MO 871422, " Work Instructions for Raychem Splice

a

Repai r. " The reinstallation of the splices was performed under full-time

QC surveillance.

To ensure that Raychem splice connectors are properly installed during

future activities, the licensee issued installation instructions in

i

Technical Standard ETS-11, " Conductor Splice Installation Specification."

l

This document incorporated information supplied by the Raychem

representative, as well as the experience recently derived'from inspection

and repair of the splices.

The NRC inspector reviewed the documentation listed below in conjunction

with the performance of this inspection.

No problems were noted during

the review.

l

M0s 870154 and 871422 to verify that appropriate instructions for

!

.

inspection and repair of splices had been provided.

Technical Standard ETS-11 to verify that the newly issued procedure

.

contained adequate installation instructions.

Training records for selected personnel involved in ths inspection

.

and repair program to verify that training had been re eived.

Selected evaluations performed in accordance with 10 CFR 50.59 to

.

verify that the evaluations were properly completed.

!

l

The PO used for acquisition of the splice connectors to verify that

'

.

the appropriate requirements were stated and to verify that the

splice connectors were environmentally qualified.

l

The NRC inspector examined the installation of a sample of splice

connectors that had been replaced as a result of the inspection program.

It appeared that the splice connectors had been properly installed.

- _ _ _ _ _ - _ _ _ _ _ _ _ _ _

1

_ - - _ _ _ - _ _ .

- - _ _

_ _ _ _ _ _

_.

. _ -

.

.

20

Based on a review of documentation related to and inspection of installed

splice connectors by the NRC inspector, it appeared that the licensee had

established a program that would ensure proper installation of Raychem

splice connectars.

No violations or deviations were identified.

13.

Followup on Licensee Actions Related to Reactor Vessel Pressure Transient

Protection

The purpose of this portion of this inspection was to review what actions

the licensee had taken to ensure that an effective mitigation system had-

been established for low-temperature overpressure (LTOP) conditions.

The

inspection was based on the response made by the licensee to Unresolved

Safety Issue (USI) A-26, " Reactor Vessel Pressure Transient Protection for

Pressurized Water Reactors."

During review of this issue, the NRC inspector determined that the

licensee had established the measures listed below to prevent an LTOP

transient.

!

A variable trip setpoint for the power-operated relief valves (PORV)

q

.

and a pretrip annunciator in the control room had been installed.

!

Surveillance Procedure ST-PORV-1 was used for verification of the

.

operability of the PORVs.

1

An operator was stationed at control room Panels CB-1/2/3 to

.

continuously monitor and control reactor coolant system (RCS)

pressure while the primary plant was in a solid-water condition.

Administrative controls were established to ensure the high pressure

safety injection and charging pumps were not started, manually or

automatically, while the primary plant was in a solid-water

I

condition.

i

The NRC inspector reviewed the documentation listed below to verify that

the licensee performed an adequate assessment of an LTOP transient on the

!

,

plant and had established the proper administrative and hardware controls

discussed above.

j

MR-FC-79-81, " Variable Setpoint for PORV Actuation," including

I

.

evaluations performed in accordance with the requirements of

10 CFR 50.59, wiring and logic diagrams, and seismic design criteria.

Requirements were issued that stated a reactor coolant pump shall not

.

be started while the primary plant is in a solid-water condition

unless a pressurizer steam space of 60 percent, by volume, or greater

exists, or the delta temperature between the steam generator primary

and secondary side is less than 50 F.

_ _ _ _ _ _ _ _ _ _ _ _ _ _ - -

l

-

j

.

.

j

21

i

i

Caution tags were installed with the pressurizer heater control

j

.

switches in the off position to prevent inadvertent heater

energization while the primary plant is in a solid-water condition.

Procedure 01-RC-2B, " Reactor Coolant Vent and Leak Test Instruction"

.

Procedure 01-RC-3, " Reactor Coolant System Startup"

.

Procedure DI-RC-4, " Reactor Coolant System Normal Shutdown"

i

.

Procedure ST-PORV-1, " Low-Temperature, Low-Pressure Power-Operated

.

Relief Valve System"

Setpoint curves (RCS pressure-temperature limits) for the PORVs

.

Applicable sections of the TS

.

In addition, the NRC inspector verified that the annunciator for PORV

actuation and pretrip conditions ~were present in the control room.

The

NRC inspector interviewed a senior reactor operator on various aspects of

LTOP operations and noted that the operator was very knowledgeable in the

procedural requirements to mitigate an LTOP transient.

Based on the review performed by the NRC inspector, it appeared that the

licensee had established an adequate program to minimize the affects of an

LTOP transient.

It also appeared that the licensee had adequately

implemented LTOP controls as described in the licensee's response to

USI A-26.

No violations or deviations were identified.

14.

Verification of Containment Integrity

The NRC inspector performed a review to verify that the licensee had

established containment integrity prior to commencing heatop of the RCS

above 210 F.

Verification of containment integrity was established by

reviewing the items listed below:

Verification that selected electrical and mechanical barriers had

.

been properly installed.

Containment isolation valves were properly positioned as required by

i

.

the appropriate documentation,

i

Local leak rate tests were performed on the personnel airlock,

q

.

equipment hatch, and fuel transfer tube.

!

_

._.

_ _ _ - - _ _ _ .

_ - _ _ -

_ . _ _ _ - _ _ _ _ _ - - _ - _ _ _ _ _ _ _ _ _ _ _ _ - - _ _ - - -

.

.

22

Containment integrity was verified by performance of the items listed

below:

Review of the local leak rate test performed on the personnel air

.

lock in accordance with Procedure ST-CONT-2-F.2, the equipment hatch

performed in accordance with Procedure ST-CONT-2-F.3, and the fuel

transfer tube performed in accordance with Procedure ST-CONT-2-F.4.

Walk down and verification of selected valve positions related to

.

containment integrity as provided in Procedure 01-C0-5, " Containment

Integrity Checklist."

Walk down and verification of selected valve positions as provided in

.

Procedure 01-RC-28-CL-D.

See paragraph 5 of this inspection report

for additional information on the results of the walkdown.

Walk down and verification of selected valve positions performed

.

during followup on Deviation 285/8702-01.

See paragraph 2.c of this

inspection report for details on this item.

.

Plant tours were performed to verify selected mechanical and

,

electrical penetrations had been properly installed.

During performance of the activities listed above, no containment

f

isolation valves or mechanical / electrical penetrations were found that

were not in the proper position or properly installed.

Problems were

noted with the documentation related to administrative control of some

containment isolation valves.

See paragraph 2.c of this inspection report

for a discussion of the items.

No violations or deviations were noted.

15.

Review of Modification Testing for Installation of a Containment Equipment

Storage Platform

The NRC inspector performed a review of the installation of an equipment

storage platform in containment to verify the installation was

accomplished in accordance with the applicable codes, standards, and

regulations.

The NRC inspector reviewed the signed-off copy of

MR-FC-83-05, " Storage of Equipment in Containment," and performed a review

'

of selected items on the installed platform to verify the installation

conformed with the requirements stated in the modification request.

This

modification was installed to provide an area for storage of equipment

4

during refueling shutdowns.

During evaluation of the installation, the

'

NRC inspector reviewed selected portions of supporting documentation

i

associated with construction of the platform.

The documentation reviewed

l

is listed below:

Welder qualification records for each individual performing welding

.

on the platform

m

._

._________________ _ ___ o

.

.

23

Records of the results of visual weld inspections performed by QC

.

Anchor support data sheets completed for installation of concrete

.

anchors

Weld verification forms used to document the individual making the

.

weld and the type of weld rod used

SRDCO-87-25, installation instructions.for MR-FC-83-05

.

The NRC inspector reviewed MR-FC-83-05 for the following:

Torque values had been specified, as appropriate, and QC verified the

.

torque value on a sampling of fasteners.

The appropriate weld procedure was specified and used.for

.

installation of the welds.

Materials used in construction were receipt inspected prior to use

.

and verified to meet limited-CQE requirements.

Design changes made to the Md were performed in accordance with

.

established procedural requirements.

Drawings were changed to reflect the as-built conditions of the

.

installed platform.

.

Changes to other procedures affected by the modification were made.

-

An evaluation of the affects of the installation on other plant

.

systems was properly performed in accordance with the requirements of

10 CFR Part 50.59.

An as-low-as-reasonable-achievable (ALARA) checklist was performed

.

prior to commencement of installation activities.

During review of MR-FC-83-05, the NRC inspector noted the following:

A change to the design installation package was not performed in

.

accordance with established procedures.

The. change was instituted by

issuance of a memo from the engineer to QC stating that use of

non-CQE material was satisfactory.

Non-CQE material was used to plug

abandoned bolt holes in the platform base plates. This change made

by the engineer was not pcrformed in accordance with established

design change control procedures.

Subsequent to the review of the

MR, the licensee processed a proper design change.

The change

determined that use of the non-CQE material was satisfactory.

The

NRC inspector reviewed the design change and determined that the

change was properly made.

_ _ _ _ _ _ - -

_ _ _ _ _ _ _

_

. _ _

1

.

.

i

24

J

The installation drawing referenced the appropriate welding code as

.

AWS D1.1-83; whereas, the installation instruction specified the

)

appropriate code as AWS D1.1-85.

The as-built drawings did not show the location of the plug welds;

.

PW-1, PW-2, PW-3, and PW-4, made in the structural members.

Prior to review of MR-FC-83-05 by the NRC inspector, the MR had been

,

reviewed the day before by operations quality assurance (QA) personnel.

f

In reviewing the discrepancies identified by QA, the NRC inspector noted

1

that QA had identified the same concerns.

To ensure that the concerns

were properly addressed, QA issued a deficiency report (DR-FC-1-87-056)

related to the changing of design documents without following established

procedures.

The DR was issued to ensure that the generic, as well as

specific problems related to this design change were addressed.

In

addition, QA also verified that the other discrepancies discussed above

,

were corrected.

Since the discrepancies were identified by QA prior to

I

the review performed by the NRC inspector, no violation of Criterion III

}

of Appendix B to 10 CFR Part 50 for failure to properly process a design

change was issued.

The NRC inspector will review the actions taken by the

QA department to verify the discrepancy is properly addressed.

This item

will remain open pending a review of the closed DR by an NRC inspector.

(285/8713-04)

No violations or deviations were identified.

16.

Licensed Operatt.r Requalification Program

The NRC inspector continued a review of the licensee's requalification

program initiated during the previous inspection period.

The review was

performed to verify that the licensee had imp.emented a program that

complied with 10 CFR Part 55 and the licensee's NRC-approved training

program.

A major portion of this area of inspection was performed to verify that the

licensee had taken appropriate corrective actions on previously identified

items.

Previous items were identified during an inspection performed in

August 1986, as detailed in NRC Inspection Report 50-285/86-24.

The

inspection report identified a total of six items that indicated weaknesses

existed in the overall training program.

Three of the items were found to

be satisfactory and closed.

However, the three items that remained open

due to unsatisfactory corrective actions were related to the basic aspects

of the training program.

The items included the following:

Unresolved Item (URI) 285/8624-01 related to establishing an effective

.

training records program to document completion of training activities.

A discussion of the followup performed on URI 285/8624-01 was provided

in paragraph 2 of NRC Incpection Report 50-285/87-10.

The followup

inspection indicated that the licensee had just recently initiated

actions to establish an auditable records system.

w__-__-__-___

__ ..

_

,

.

25

URI 285/8624-02 related to not providing on-the-job training for all

.

aspects of plant operations by failing to give classroom lectures for

the loss of instrument air and the loss of shutdown cooling.

A

discussion of this item was provided in paragraph 2 of NRC Inspection

Report 50-285/87-10.

The followup inspection indicated that no

corrective actions had been initiated in providing these classroom

l

lectures since the problem was initially identified in August 1986.

l

URI 285/8624-03 related to providing a preplanned lecture series on

.

E0Ps.

This item is discussed in paragraph 2 of this inspection

,

'

report.

The followup inspection indicated that some E0Ps were

discussed during simulator training given in the early part of 1987,

i

but training on all E0Ps had not been providsd.

1

i

Based on the review performed on these items, it appeared that the

licensee had not taken timely actions to correct the previously identified

problem areas. Without an adequate level of performance in the areas

identified by the three URIs, the licensee's operator training program is

not currently at a level of proficiency that would ensure adequate

training of licensed operators.

For this reason, it'is requested that the

{

licensee provide a response to URIs 285/8624-01, 285/8624-02, and

j

285/8624-03.

The response should include a discussion of the actions you

i

plan to take to satisfactorily resolve the items and when the actions will

be completed.

During this inspection, no additional unresolved items were identified.

However, a number of concerns were identified by the NRC inspector.

The

j

concerns are listed below.

The NRC inspector discussed each concern with

l

licensee training management personnel.

I

a.

Approximately 75 percent of the training staff is composed of

contractor personnel.

These contractor personnel taught

,

l

approximately 85 percent of the classes giver, from September 1986

through March 1987.

Although most of the contractor personnel have

received licenses as operators at other plants or have held

l

instructor certifications; none of these instructors have had any

'

operating experience at the FCS.

Without actual operating experience

i

at the FCS, the classroom lectures could not include a description of

!

actual plant operating experiences.

This type of information would

i

enhance the overall knowledge level of tia operators attending

classroom lectures.

i

1

Licensee personnel stated that efforts were initiated in the recent

l

past to add instructors to the training staff that currently hold

operating licenses at the FCS.

This effort will begin in July 1987.

,

i

i

b.

The licensee had not established a method for certification of

contract instructors to teach plant systems.

Without a certification

program, the level of knowledge of contract instructors was not

determined for a specific area prior to allowing the contractor to

provide training in that area.

_ _ _ - - _ _ _ _ _ _

_ - _ _ _ _ _ _ _

_ _ _ _ _ _ _ _ _ . __

__

_

_ -

. _ _ _ _ _ - _ - _ _ _ _ _ _ _ _ - - _ _

.

.

26

Licensee personnel stated that instructors were interviewed by the

Supervisor-Station Training prior to being allowed to teach and have

been evaluated for the technical content of their lectures twice each

year.

Based on the results of these evaluations, it was felt

additional certification was not required.

Licensee personnel _ stated

that they would consider giving each instructor a check out on the

,

individual systems they teach to verify their technical knowledge is

1

adequate.

1

c.

A review of 15 lesson plans indicated that 9 of the lesson plans were

prepared by a contractor and approved by a licensee employee.with no

operating experience at any nuclear plant.

The review also indicated

that no operating personnel at the FCS had reviewed the lesson plans.

Licensee personnel stated that the lesson plans previously unreviewed

by licensed personnel would be rereviewed by appropriate personnel in

the near future.

d.

Lesson plans for Sections 1 and 2 (Safety Limits and Limiting

i

Conditions for Operations) of the TS, the auxiliary feedwater system,

and the E0Ps were reviewed for technical content.

The results of the

review indicated that the lesson plans contained technically

incorrect information, appropriate information had not been included,

and typographical errors affecting the technical meaning of the

information were not uncommon.

Licensee personnel stated that the lesson plans were in the process

of being reviewed.

No time frame was given as to when the reviews

would be completed.

Lesson plans had not been completed for Sections 4 and 5 (Design

e.

Features and Administrative Controls) of the TS.

Without an approved

lesson plan, no learning objectives were established and no assurance

j

was made that the licensed operators received the in-depth

instruction needed to perform their assigned duties.

1

Licensee personnel stated that the lecture given on Sections 4 and 5

J

of the TS was given using the TS manual as the lesson plan.

These

personnel stated that they felt lectures given from the TS manual

were adequate.

1

f.

The licensee established a formal program for maintaining lesson

i

plans up-to-date in April 1987.

Prior to this time, it was the

j

individual instructor's responsibility to ensure that the lesson plan

contained the latest information.

As discussed in paragraph 6.d

!

above, a review performed on three lesson plans indicated that the

information contained in the lesson plans was incomplete or

inaccurate.

These lesson plan inadequacies were due, in part, to the

lesson plans not being updated with the latest information.

w

--

-

-

l

.

.

27

i

Licensee personnel stated that the lesson plans that had become out

dated would be reviewed and brought up-to-date.' No date was

j

specified as to when the updating of the lesson plans would be

l

completed.

{

g.

The licensee did not maintain an as given training schedule.

The

schedule was issued at the beginning of the week to notify

appropriate individuals of the classes to be taught.

If, for'some

reason, the class was rescheduled or the class was cancelled, no

changes were made to the schedule to reflect the actual as given

training. Without this information, the licensee can not establish

that the training required by 10 CFR Part 55 and the licensee's

NRC-approved training program was provided.

Licensee personnel stated that this concern would be reviewed and, if

appropriate, actions would be taken to establish a program to

maintain an as given training schedule.

The NRC inspector interviewed onshift licensed operators to verify that

the training records actually reflected the training received by each

individual.

During discussions with licensed personnel, it was determined

that the classroom attendance sheets for a lecture given on special topics

in March, April, and May 1987 had been completed, but approximately

1 month after the attendance sheet was signed, individuals received a

letter stating that the individual had missed the classroom lecture.

There appeared to be a discrepancy as to whether or not the training

records correctly reflected the individual's attendance at the lecture on

special topics.

By the end of this inspection period, the licensee had

not established the reason for the apparent discrepancy.

This item

remains open pending a review of the discrepancy by the licensee and a

followup review by the NRC inspector.

(285/8713-05)

The NRC inspector also interviewed onshift licensed operators to solicit

comments regarding their perspective on the quality of the training being

provided.

The list of comments provided below were derived from

interviews with shift supervisors, senior reactor operators, and reactor

operators.

,

l

The drawings and diagrams given as training handouts during lectures

.

were unreadable.

The reference material in the training library was out-of-date

.

because the changes to the procedures were not incorporated in' a

timely manner.

The material presented in classroom lectures was not detailed enough

.

to provide the instruction needed to operate the plant.

)

Instructors were late for class and not prepared due to last minute

.

changes in the training schedule.

.

.

.

28

Training material did not contain plant operating experience.

.

Four instructors (licensee employees and contractors) were identified

.

as being excellent; however, the overall knowledge level of the

j

instructors in general was not too good.

Management has been told of concerns listed above but no apparent

I

.

action has been taken.

{

In discussion with licensee personnel regarding the above items, licensee

{

personnel stated that they thought the comments provided by the licensed

operators were problems that existed in the past, but were not. current

problems.

The NRC inspector noted to the licensee personnel that the

operators that made the comments stated that the problems still existed.

Licensee personnel stated that they would review the concerns of the

operators and take actions, as appropriate.

The licensee received bids for installation of an onsite, plant specific

simulator.

It is anticipated that the contract for the simulator will be

awarded in the near future.

It is also currently anticipated that the

simulator will be fully operational by late 1990 or early in 1991.

In February 1987, the licensee received accreditation from the Institute

of Nuclear Power Operations for the three programs associated with

licensed operator training.

The three accredited programs are shift

supervisor training, licensed-operator requalification training, and

initial licensed-operator training.

No violations or deviations were identified.

17.

Containment Local Leak Rate Testing

The NRC inspector performed this inspection to verify, through observation

and records review, that the local leak rate test program for testing of

the containment isolation valves and penetrations (mechanical and

electrical) was performed in accordance with TS requirements.

Prior to startup from the current refueling outage, the licensee verified

that all penetrations and isolation valves had been tested in accordance

with approved procedures.

For isolaticn valves and penetrations that were

repaired, the licensee verified that the valve or penetration received

posttesting to verify the leak rate was satisfactory.

The licensee also

verified that the total leak rate for all penetrations did not exceed

0.6 La, as required by the TS.

The NRC inspector reviewed the preliminary data available to verify the

licensee had properly completed local leak rate testing of the appropriate

penetrations and valves.

Based on a review of the preliminary data, it

appeared that the licensee had properly performed the required testing.

u

, - -

,

.

,

I

l

29

J

l

Since the final leak rate testing data was not available prior to the end

of this inspection period, this portion of this inspection will be

continued into the next inspection period.

No violations or deviations were-identified.

18. Meetings

i

On May 14, 1987, an enforcement conference was held in the Region IV

l

office.

The conference was held to discuss apparent violations related to

maintenance and welding inspections performed by Region IV personnel as

detailed in NRC Inspection Reports 50-285/87-05 and 50-285/87-08,

respectively.

The attendees at the meeting included licensee personnel,

NRC management personnel, senior resident inspector, Region IV enforcement

officer, Region IV reactor inspectors, and a representative from the NRC's

Office of Nuclear Reactor Regulation.

19.

Exit Interview

Tiie NRC senior resident inspector met with Mr. W. G. Gates (Plant ttanager)

and other members of the licensee staff on June 1, 1987.

At this meeting,

the NRC inspector summarized the scope of the inspection and the findings.

During this inspection period, three additional exit interviews were held

related to items discussed in this inspection report. . The details of the

dates, attendees, and subject matter of these exit intervie >s are provided

in paragraph 1.

I

l

1

i

E-

-

_ _ _ _ _ _

__________o