,l ,
Ch0
'
JUR 2 9 L%7
.
!
l
Docket Nos. 50-424, 50-425
License Nos. NPF-61, CPPR-109
Georgia Power Company
!
I
ATTN: Mr. James P. O'Reilly
Senior Vice President-
Nuclear Operations
P. O. Box 4545
Atlanta, GA 30302
Gentlemen:
SUBJECT:
(NRCINSPECTIONNOS. 50-424/87-34 AND 50-425/87-24)
This refers to the Nuclear Regulatory Commission (NRC) inspection conducted by
P. G. Stoddart on May 18-22, 1987.
The inspection included a review of
activities authorized for your Vogtle facility.
At the conclusion of the
inspection, the findings were discussed with those members of your staff
identified in the enclosed inspection report.
Areas examined during the inspection are identified in the report.
Within
these areas, the inspection consisted of selective examinations of procedures
and representative records, interviews with personnel, and observation of
activities in progress.
l
The inspection findings indicate that certain activities appeared to violate
NRC requirements.
The violation, references to pertinent requirements, and
elements to be included in your response are described in the enclosed Notice
of Violation.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and its enclosures
I
will be placed in the NRC Public Document Room.
i
The responses directed by this letter and its enclosures are not subject to the
clearance procedures of the Office of Management and Budget as required by the
1
Paperwork Reduction Act of 1980, PL 96-511.
f
,
J
l
887 EE S$ha
I
G
l
i\\
j
yu
)
.
.
.
<-
.-
,-
Georgia' Power Company
2
Should you have any questions concerning this letter, please contact us.
Sincerely,
4
J. Philip Stohr, Director
Division of Radiation Safety
and Safeguards
Enclosures:
1.
2.
Inspection Report
cc w/encls:
P. D. Rice, Vice President, Project
Engineering
l
C. W. Hayes, Vogtle Quality
Assurance Manager
G. Bockhold, Jr., General Manager,
Nuclear Operations
'
L. Gucwa, Manager, Nuclear Safety
and Licensing
J. A. Bailey, Project Licensing
Manager
B. W. Churchill, Esq., Shaw,
Pittman, Potts and Trowbridge
J. E. Joiner, Troutman, Sanders,
l
Lockerman and Ashmore
l
D. Kirkland, III, Counsel,
i
l
Office of the Consumer's Utility
l
Council
i
D. Feig, Georgians Against
,
!
Nuclear Energy
i
M. B. Margulies, Esq. , Chairman,
Atomic Safety and Licensing Board
Panel
Dr. O. H. Paris, Administrative Judge
Atomic Safety and Licensing Board
Panel
G. A. Linenberger, Jr., Administrative Judge
Atomic Safety and Licensing Board
Panel
bec w/encls:
(See page 3)
f
i
l
. _ _ _ _ _ _ _ _ _ - _ - _ - _ _ _ _ _ - -
. - . . .
.
-#
'
Georgia Power Company
3
bcc w/encls:
E. Reis, 0GC
M. Miller, NRR
M. Sinkule, RII
NRC Resident Inspector
l
Document Control Desk
State of Georgia
G. Jenkins
f,4;f-
/W
PStoddart
J able
MSinkule
DColbs
6/ p/87
6
/87
6/(3/87
6/l$/87
7