Notice of Violation from Insp on 860830-1003
ML20215M662
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 10/28/1986
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20215M659 List:
References
50-498-86-31, 50-499-86-31, NUDOCS 8611030143
Download: ML20215M662 (1)


Text

-

APPENDIX A NOTICE OF VIOLATION Houston Lighting & Power Company Docket: 50-498 South Texas Project Units 1 & 2 50-499 Permit: CPPR 128 CPPR 129 During an NRC inspection conducted on August 30 through October 3, 1986, a violation of NRC requirements was identified. The violation involved the component cooling water pump room. In accordance with the " General Statement of Policy and Procedure for NRC Enforcement Actions," 10 CFR Part 2, Appendix C (1986), the violation is listed below:

Failure to Follow Inplace Storage Requirements Criterion XIII of Appendix B to 10 CFR 50, states, in part, that measures shall be established to control the handling, storage, and preservation of material and equipment to prevent damage or deterioration.

This requirement is amplified by Section 13 of the HL&P Quality Assurance Program which requires that storage requirements be promulgated in procedures and specifications to preclude damage and deterioration.

Bechtel specification 5A300GS1002, Revision 8, paragraph 3.3D requires inplace protection to minimize damage or degradation of quality.

Contrary to the above, the "B" Component Cooling Water Pump, motor and other room accessories have not been adequately protected from the overhead installation of fireproofing insulation resulting in a deteriorating condition. Details are included in paragraph 4.

This is a Severity Level IV violation. (Supplement I.E) (498/8631-01)

Pursuant to the provisions of 10 CFR 2.201, Houston Lighting & Power Company is hereby required to submit to this office, within 30 days of the date of the letter transmitting this Notice, a written statement or explanation in reply, including for each violation: (1) the reason for the violations if admitted, (2) the corrective steps which have been taken and the results achieved, (3) the corrective steps which will be taken to avoid further violations, and (4) the date when full compliance will be achieved. Where good cause is shown, consideration will be given to extending the response time.

Dated at Arlington, Texas this g'? day of C&fm 1986 8611030143 861028 PDR G ADOCK 05000498 ppg