Text
.
,
OCT ': E 1933
In Reply Refer To:
Dockets:
50-498/86-31
50-499/86-31
Houston Lighting & Power Company
ATTN:
J. H. Goldberg,
Group Vice President, Nuclear
P._0. Box 1700
Houston, Texas 77001
Gentlemen:
This refers to the inspection conducted by Messrs. C. E. Johnson and D. L.
Garrison of this office during the period August 30 through October 3, 1986, of
activities authorized by NRC Construction Permits CPPR 128 and 129, for the
South Texas Project, Units 1 and 2, and to the discussion of our findings with
Mr. J. Westermier and other members of your staff at the conclusion of the
inspection.
Areas examined during the inspection included heating ventilation and air
conditioning (HVAC), spent fuel storage racks, mechanical components, and
various other areas and activities observed during site tours. Within these
areas, the inspection consisted of selective examination of procedures and
representative records, interviews with personnel, and observations by the NRC
inspectors. The inspection findings are documented in the enclosed inspection
report.
During this inspection, it was found that certain of your activities were in
violation of NRC requirements.
Consequently, you are required to respond to
this violation, in writing, in accordance with the provisions of Section 2.201
of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal
Regulations.
Your response should be based on the specifics contained in the
Notice of Violation enclosed with this letter.
The response directed by this letter and the accompanying Notice is not subject
to the clearance procedures of the Office of Management and Budget as required
by the Paperwork Reduction Act of 1980, PL 96-511.
Should you have any questions concerning this inspection, we will be pleased to
discuss them with you.
Sincerely,
Originar ag,cd Dy
J. E. Gagliardo
J. E. Gagliardo, Chief
Reactor Projects Branch
Enclosures:
(see next page)
RIV:SIQF
RPB/CN
RPB/DM
C: k/C
C:RPB
CEJohnson/1r
DLGarrison
RGTaylor
G
stable
JEGagli
o
^>'g (>\\
/d /g(/86
/0 g /86
- /yr/86
/v/d/86
I't/s#/
/
8611030139 861028
ADOCK 05000498
G
w
.
Houston Lighting & Power Company
-2-
Enclosures:
1.
Appendix A - Notice of Violation
2.
Appendix B - NRC Inspection Report
50-498/86-31
50-499/86-31
cc w/ enclosures:
Houston Lighting & Power Company
ATTN:
M. Wisenberg, Manager,
Nuclear Licensing
P. O. Box 1700
Houston, Texas
77001
Brian Berwick, Esquire
Asst. Attorney General
Environmental Protection Division
P. O. Box 12548, Capitol Station
78711
Lanny Alan Sinkin
Citizens Concerned About Nuclear
Power, Inc.
Christic Institute
1324 North Capitol Street
Washington, D.C.
20002
Charles Bechhoefer, Esquire
Chairman, Atomic Safety & Licensing
Board
U.S. Nuclear Regulatory Commission
Washington, D.C.
20555
Dr. James C. Lamb, III
313 Woodhaven Road
Chapel Hill, North Carolina
27514
Frederick J. Shon
Administrative Law Judge
Atomic Safety and Licensing Board
U.S. Nuclear Regulatory Commission
Washington, D.C.
20555
Alvin H. Gutterman
Newman & Holtzinger, P.C.
1615 L St., N.W., Suite 1000
Washington, D.C.
20036
Texas Radiation Control Program Director
bcc:
(see next page)
,
.
.
Houston Lighting & Power Company
3-
-
bec to DM8 (IE01)
bec distrib. by RIV:
- RPB
DRSP
- RRI-0PS
R. D. Martin, RA
- RRI-CONST.
- Section Chief (RPB/C)
- R&SPB
- MIS System
- RIV File
- D. Weiss, LFMB (AR-2015)
- RSTS Operator
R. Pirfo, ELD
- R. G. Taylor, RP8/C
- RSB
- B. A. Breslau, RPB/C
- w/766
>
.
h
d
a
1
f
f
I