o, OPERATINC DATA REPORT DOCKET NO 50-255 DATE 05-07-87 COMPLETED BY CCPackard TELEPHONE (616)764-8913 OPERATINC STATUS NOTES 1.
Unit Names Palisades 2.
-Reporting Period:
870401-870430 3.
Licensed Thermal Power (MWt):
2530 4.
Nameplate Rating (Cross MWe):
811.7 5.
Design Electrical Rating (Net MWe):
805 6.
Maximum Dependable Capacity (Cross MWe): **770 7.
Maximum Dependable Capacity (Net MWe):
- 730 8.
If Changes Occur in Capacity Ratings (Items Number 3 through 7) since last report, give reasons:
9.
Power Level to Which Restricted, if any (Net MWe):
- 10. Reasons for Restrictions, if any:
This Month Yr-to-Date Cumulative
- 11. Hours In Reporting Period 719.0 2,879.0 134,678.0 12.
Number of Hours Reactor Was Critical 574.6 574.6 70,364.9
- 13. Reactor Reserve Shutdown Hours
- 14. Hours Generator On-Line 537.2 537.2 66,820.3
- 15. Unit Reserve Shutdown Hours
- 16. Cross Thermal Energy Generated (MWH) 951,309.3 951,309.3 139,313,949.3
- 17. Cross Electrical Energy Generated (MWH) 295,410.0 295,410.0 43,409,340.0 18.
Net Electrical Energy Generated (MWH) 274,021.0 274,021.0 40,856,625.0
- 19. Unit Service Factor 74.7 18.7 49.6 20.
Unit Availability Factor 74.7 18.7 49.6 21.
Unit Capacity Factor (Using MDC Net) 52.2 13.0
- 47.5 22.
Unit Capacity Factor (Using DER Net) 47.3 11.8 37.7 23.
Unit Forced Outage Rate 25.3 81.3 36.2
- 24. Shutdownn Scheduled Over Next Six Months (Type, Date and Duration of Each):
Scheduled Maintenance, October 2, 1987, 45 Days 25.
If Shut Down at End of Report Period, Estimated Date of Start Up:
26.
Units in Test Status (Prior to Commercial Operation):
Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION
- Based on condenser backpressure
- Weighted Average (635 MWe used as MDC Net prior to October 1985)
OC0185-00018-OP03 9
A B705120338 870430 l
_ _ _ ~ _ - - - _ _ - _ _ _ - _ _ _ _ _ - _ _ _ - _ - - _ _ _ _ _
a,..
AVERACE DAILY UNIT POWER LEVEL DOCKET NO 50-255 UNIT Palisades DATE 05-07-87 COMPLETED BY CCPackard TELEPHONE (616)764-8913 MONTH April 1987 DAY AVERACE DAILY POWER LEVEL DAY AVERACE DAILY POWER LEVEL (MWe-Net)
(MWe-Net) 1 0
17 109-2 0
18 352 3
110 19 561 4
151 20 576 5
175 21 732 i
6 271 22 748 7
296 23 751 8
299 24 735 9
298 25 755 10 304 26 762 11 432 27 753 12 291 28 754 13 0
29 756 14 0
30 763 15 0
16 0
INSTRUCTIONSt On this format, list the average daily unit power level in HWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
OC0185-0001C-OP03 I
\\
~,
e;
~
DOCKET NO.
50-255 UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME Palisades-DATE 05-07-87~
COMPLETED BY GCPackard REPORT MONTH April 1987 TELEPHONE
'(616)-764-8913 l
2 No.
Date Type Duration Reason Method of Licensee System Component Cause'& Corrective 4
5 (Hours)
Shutting Event-Code Code Action to 3
Down Reactor Report #
Prevent Recurrence 1
860519 F
52.4 A
3 86-18 2
870412 F
129.4 A
2.
3.
4.
5.
F: Forced Reason:
Method:
Exhibit G - Instructions Exhibit I - Same Source 5: Scheduled A-Equipment failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER) File D-Regulatory Restriction 4-Other(Explain)
E-Operator Training & License Examination F-Administrative G-Operational Error (Explain)
H-Other (Explain)
OC0185-0001D-0P03
'* s.
i
SUMMARY
OF OPERATING EXPERIENCE FOR APRIL 1987 The unit was placed on line on April 3 at 0255 hours0.00295 days <br />0.0708 hours <br />4.21627e-4 weeks <br />9.70275e-5 months <br />, ending the outage from May 19, 1986. The plant escalated to 68 percent power until April 12 at 0534 hours0.00618 days <br />0.148 hours <br />8.829365e-4 weeks <br />2.03187e-4 months <br /> when the unit was manually tripped due to an EHC lube oil line break.
The reactor was again~ critical on April 16 at 1925 hours0.0223 days <br />0.535 hours <br />0.00318 weeks <br />7.324625e-4 months <br /> and the unit was placed on line on April 17, at 1503 hours0.0174 days <br />0.418 hours <br />0.00249 weeks <br />5.718915e-4 months <br />. On April 21, the plant reached approximately 100 percent power and remained at this power level through the end of 'the reporting period.
d l
l i
l l
OC0185-0001E-OP03
... ~.,
Consumers Power re w nesus maaramanags paggNE55 Pahsedes Nudear Plant: 27780 Blue Star Memorial Highway, Covert. MI 49043 May 7, 1987 US Nuclear Regulatory Commission Mail and Records Section Washington, DC 20555 LICENSE REPORT OF MONTHLY OPERATING DATA DPR-20, DOCKET NO 50-255 Enclosed is a copy of the Monthly Operating Data and a Sununary of Operating Experience for the Palisades Nuclear Plant for the month of April 1987 Dewey VanDenBerg Reactor Engineer CC: Khilaas, Palisades CHCoralski, Palisades JCKeppler, USNRC KWBerry, P24-614B CSKozup, Palisades Resident Inspector, Palisades DLHackett, P11-420B MALapinski, P21-332 CWBruckmann, Div of Radiological Health Services, Lansing, Michigan SLHall, Michigan Dept of Labor RCallen, Michigan Public Service Conunission Records Center, INPO, Atlanta, CA Rirraylor, CE, Palisades AAAlatalo, Palisades LLBumb, P21-324 CBSzczotka, P-21-311B Document Control, 950*22*35*10/L CCP87-012 i I 6