ML20215J864

From kanterella
Jump to navigation Jump to search
Response Team Insp Repts 50-445/86-03 & 50-446/86-02 on 860201-0331.Five Violations & Five Deviations Noted.Violations Included,Inadequate Site Operation Trend Analysis
ML20215J864
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 10/16/1986
From: Barnes I, Ellershaw L, Hale C, Wagner D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20215J811 List:
References
50-445-86-03, 50-445-86-3, 50-446-86-02, 50-446-86-2, NUDOCS 8610270219
Download: ML20215J864 (49)


See also: IR 05000445/1986003

Text

..

.

APPENDIX C

COMANCHE PEAK RESPONSE TEAM ACTIVITIES INSPECTION REPORT

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Inspection Report:

50-445/86-03

Permits: CP"?-126

50-446/86-02

CPPR-127

Dockets:

50-445

Category: A2

50-446

Licensee: Texas Utilities Electric Company (TVEC)

Skyway Tower

400 North Olive Street

Lock Box 81

Dallas, Texas 75201

I

Facility Name: Comanche Peak Steam Electric Station (CPSES), Units 1 and 2

Inspection At: Glen Rose, Texas

Inspection Conducte - February 1 through March 31, 1986

i

/0

S

Inspectors:

g

L.E. Ellershaw, Reactor Inspector, Region IV

Dat~e

CPSES Group

(paragraphs 6. , 7. , 8.e-9, 8.j, 9.g-m)

%

Johbl%

/

C.J. H 1 , Reactor Inspector, Region IV

Date

"

CPSE

roup

(paragraphs 2.f-j,3.,4.,5.a-c,8.c-d,8.h-1)

i

SW

/0//k3

A P.C. Wagner, Reactor Inspector, Region IV

Date

CPSES Group

'

l

(paragraphs 2.a-e, 5.d, 8.a-b, and 9.a-f)

Consultants:

EG&G -

J. Dale (paragraphs 6., 9.j)

A. Maughan (paragraphs 2.c-d, 9.b.-d)

W. Richins (paragraphs 8.e} 8.f, 9.k, 9.1)

,

V. Wenczel (paragraphs 5.b

l

Parameter - J. Birmingham (paragraphs 2.h-i, 3.d, 8.c-d, 8.h-i)

l

8610270219 861017

l

ADOCK 05000445

I

PDR

PDR

G

._

_

_

, - _ _ _ - - . _ .

_ _.

_ . - . . _ ,

_ _ _ - - - - _ - - _ -

_ . -

,_

,

.

.

-2-

J.Gibson(paragraphs 2.e,9.e.)

K. Graham (paragraphs 7.,8.j,9.m)

D. Jew (paragraphs 8.g, 9.g-1)

Teledyne -- J. Malonson (paragraphs 4., 5.c)

Approved:

8w

<o/$M6

I. Barnes, Chief, Region IV CPSES Group

Date

Inspection Summary

Inspection Conducted: February 1 through March 31, 1986 (Reports 50-445/86-03;

50-446/86-02)

Areas Inspected: Nonroutine, unannounced inspection of applicant actions on

previous inspection findings, Comanche Peak Response Team (CPRT) issue -

specific action plans (ISAPs), applicant management of QA activities, CPSES QC

surveillance program, assessment of allegations, pipe supports, and followup on

NRR liner plate concerns.

Results: Within the seven areas inspected, five violations (failure to take

corrective action with respect to Inspection Process Control group findings,

paragraph 5.a; inadequate site operation trend analysis, paragraph 5.b;

inadequate control of a design change, paragraph 5.d; inadequate resolution of

a nonconforming condition, paragraph 6; failure to comply)with ACI requirements

for radiographic examination of a liner weld, paragraph 7 and five deviations

(failure to comply with approved instructions in performance of reinspections,

paragraphs 9.g and 9.j; incorrect consideration of impact of a revision to a

quality instruction (QI) on previous inspections, paragraph 9.k; inadequate

engineering review for applicability of an inspection attribute, paragraph 9.j;

omission of a required inspection attribute from a QI, paragraph 9.n; and

failure to identify an unacceptable weld surface condition, paragraph 9.m) were

identified.

F

.

.

-3-

DETAILS

1.

Persons Contacted

D. L. Anderson, Supervisor of Audits, TUGCo

    • J. L. Barker, Executive Assistant to Executive Vice President, TUGCo
    • J. W. Beck, Vice President, TUGCo

A. K. Bordine, Operations Q-List Engineer, TUGCo

    • C. T. Brandt, TUGCo Quality Engineering (QE) Supervisor (Ebasco)
    • R. E. Camp, Project Manager, Unit 1 (Impell Corp.)
    • W. G. Counsil, Executive Vice President, TUGCo

D. E. Deviney, Operations QA Supervisor, TUGCo

  • P. E. Halstead, Quality Control (QC) Manager, TUGCo

M. Keathly, Evaluation Research Corporation (ERC) Lead Electrical QC

Inspector

P. Leyendecker, Surveillance Supervisor, TUGCo

J. B. Leutwyler, Brown & Root (B&R) Electrical QC Supervisor

J. Mallanda, CPRT Electrical Review Team Leader

D. M. McAfee, Quality Assurance (QA) Manager, TUGCo

  • J. T. Merritt, Director, Construction, TUGCo

M. Obert, ERC Issue Coordinator

      • J. Redding, Executive Assistant, TUGCo

B. C. Scott, Supervisor, Vendor Audits, TUGCo

P. Stevens, Electrical Engineer, TUGCo Nuclear Engineering (TNE)

  • J. F. Streeter, Director, QA, TUGCo
      • T. G. Tyler, CPRT Program Director, TUGCo

,

J. Ziemian, ERC Lead Mechanical QC Inspector

  • Denotes those persons who attended the March 4, 1986, exit interview.
    • Denotes those persons who attended both the March 4, 1986, and the

April 4, 1986, exit interviews.

  • t* Denotes those persons who attended the April 4, 1986, exit interview.

The fiRC inspectors also contacted other CPRT and applicant employees

durir.g this inspection period.

2.

Applicant Actions on Previous Inspection Findings

(Close_d) Unrasolved Item (445/8518-U-02; 446/8515-U-01):

Electrical

a.

penetratien assemblies (EPAs) not properly qualified.

Further review

of this unresolved item disclosed numerous problems which have been

documented in a separate inspection' report; i.e., NRC Inspection

Report 445/86-04; 446/86-03. This item is closed.

b.

(Closed) Open Item (445/8513-0-02):

Lack of inspection procedure for

ISAP No. I.b.4.

The adequacy of the provided procedures to conduct

ISAP No. I.b.4 was further evaluated by a review of ISAP Nos. I.b.2,

.m

.

_

_

.

_

. - _ _

, _ _ . _ _ _ _ _

__

_

.

.

-4-

Revision 4, dated January 24, 1986, and I.b.4, Revision 4, dated

January 24, 1986. The inspections required in I.b.2 include the

issues addressed in I.b.4; therefore, procedures for inspection are

i

not required in I.b.4.

This item is closed.

1

-c.

(Closed)OpenItem(445/8514-0-09): Comparison of ERC with NRC

review results for documentation packages. Comparison of ERC and NRC

documentation reviews of seven verification packages was deemed to be

ineffective because of revisions to the applicable procedures. The

NRC inspector reviewed again the involved packages; the results are

discussed elsewhere in this report. This item is closed.

d.

(0 pen)OpenItem(445/8516-0-20):

Potential deviation regarding

underinsertion of EPA closure flange stud in nut. The condition of

the nuts not being engaged flush with the ends of the closure studs

was documented in ERC Deviation Report (DR) 1-E-EEIN-062-DR-1. This

DR was incorporated into Nonconformance Report (NCR) E85-102021SX,

This item remains open pending NRC review of the disposition of the

NCR.

e.

(Closed)OpenItem(445/8518-0-12): During an independent NRC

inspection in December 1985 of instrument 1-PT-2325, Verification

Package No I-E-ININ-053, it was observed that tubing associated with

the instrument was not color coded to identify its assigned

separation group (train / channel), and that separation spacing was

apparently not maintained on the tubing run. ERC inspection

personnel, similarly identified these conditions on

DRs I-E-ININ-053-DR1 and DR2; the corresponding TUGCo NCRs are

I-85-1012775X and I-85-101278SX dated October 3, 1985.

Gibbs & Hill, Inc (G&H) Pressure Instrument Specification Sheet

No. 05.14, indicated that 1-PT-2323 is a "Q" item (class 1E connected

to a safety class 2 system). The TUGCo "Q" list, 1Q-LIST-MS-0323,

indicates that 1-PT-2325 is safety class 1E, seismic category I, has

two component functions, and must remain functional during and after

a Safe Shutdown Earthquake (SSE). The CPSES FSAR, Figure 10.3-1

(SH-1), shows that 1-PT-2325 controls the power operated atmosphere

steam relief valve (1-MS-259) associated with the main steam line

from steam generator #1. Also, Section 7.4.f of the FSAR lists this

relief valve, controlled by 1-PT-2325, as an essential component

under hot standby conditions. Hot standby is defined in this section

as, ". . . a stable condition of the reactor achieved shortly after a

programed or emergency shutdown of the plant and is the safe

shutdown design basis for CPSES . . . ."

The TUGCo disposition of NCRs I-85-1012777SX and 101278SX stated that

no nonconformance existed because the instrument was "non-Q," and did

not fall within the scope of the QA program. Subsequently, ERC

initiated Technical Information Request (TIR) No. 130 dated

October 31, 1985, requesting further clarification of color code

identification for separation groups I, II, III, IV, A, or B.

The

_ _ _

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

_

.

_ _ _ _ _ _ _ _ _ _ _

.

.

-5-

TUGCo response to TIR 130 stated that color coding of instrument

impulse lines was required only for those instruments annotated by a

diamond symbol on drawings of the 2323-M1-2500 series, because these

were the only nuclear safety-related instruments designated by G8H

Specification 2323-MS-625.

The NRC inspector's review of the instrument tabulation sheet,

2323-M1-2505-03, Sheet 3 of 5, revealed that 1-PT-2325 was assigned

to separation Train "A", but was not associated with the diamond

symbol. Drawing 2323-M1-2500-N, Sheet 1 of 1 indicates that the

diamond symbol ~is used to identify field mounted instruments which,

because of their safety function, require the connecting impulse

tubing to have separation from similar tubing runs on the redundant,

counterpart instrument. On February 13, 1986, TUGCo redispositioned

NCRs I-85-101277SX and 101278SX, to state that no nonconformance

existed because the instrument was nonsafety-related (i.e., not

required for safe shutdown). On February 20, 1986, TUGCo revised the

response to TIR 130, to state that devices that did not have

redundant counterparts were not color coded, and did not require

inspection for separation.

Because 1-PT-2325 did not appear to have a redundant counterpart,

this open item pertaining to maintaining separation color coding and

spacing of the tubing run is closed.

The FSAR listing of the power. operated atmosphere steam relief valves

as essential components for maintaining hot standby, brought into

question the definition of safe shutdown as identified on the

disposition of NCRs I-85-101277SX and 101278SX, and as depicted in

design documents and implementing procedures / instructions. This item

is considered unresolved pending clarification of requirements by the

applicant (445/8603-U-01;446/8602-U-01).

l

f.

(0 pen) Violation (445/8432-02;446/8411-02): Procedures were not

I

established for regular management review of the status and adequacy

of the construction QA program nor was it apparent such reviews were

made. Actions taken and being taken by TUGCo include the following:

Procedure DQP-CQ-5, " Senior Management Overview," Revision 0,

September 23, 1985, has been implemented and two committee meetings

have been held. The following management personnel are members of

this committee: Vice Presidents of Operations, Engineering /

Construction, and Licensing /QA; Director of QA; the Managers of QA

and QC; and the Operations QA Supervisor. The Executive Vice

President of Nuclear Engineering and Operations has attended both

meetings thus far. Based on the NRC review of the minutes of these

meetings, it is apparent that senior plant management is being

appraised of QA/QC problem areas and their input is being provided to

corrective as well as preventive action programs.

In addition, an

INP0 audit we conducted in the summer of 1985, and the CPRT onsite

i

.


_----.----.-- __

.

.

.

-6-

activities are directing more management attention to existing and

potential problem areas and weaknesses.

Further independent

management assessment of the plant will be provided by annual _JUMA

audits, the first scheduled to begin February 24, 1986.

The subject of management assessment is still being evaluated.by the

CPRT in ISAP No. VII.a.5. TUGCo will respond to this violation when

the CPRT effort is complete. This item remains open awaiting that

response.

g.

(0 pen) Violation (445/8432-03;446/8411-03):

Four examples of

'

failures in the program audits of safety-related activities:

(1) inadequate audit procedures; (2) failure to verify proper

'

implementation of all elements of the safety-related program

annually; (3) Westinghouse site activities were not audited in 1977,

.

1978, 1979, 1980, and 1981; and (4) since 1978 vendors have not been

audited annually.

'

(1) At the time of this violation, the audit program for internal

and external audits was prescribed in Procedure DQP-CS-4, "TUGCo

QA Audit Program." Subsequent revisions and new procedures

describe in more detail how TUGCo's. commitments are being

implemented. Currently, the TUGCo audit program is being

implemented with several procedures that are topically specific.

j

These procedures include: DQA-QA-2, " Indoctrination and

Training of TUGCo QA Dallas Personnel"; DQP-QA-15, "TUGCo QA

'

Audit Program"; DQP-VC-14," Conduct of External Audits";

,

DQP-AG-2, " Conduct of Internal Audits"; DQP-AG-3, "CPSES

>

'

Operations Phase Audit Program"; DQP-AG-4, "CPSES Construction

Phase Audit Program"; and DQP-AG-6, " Internal Audit Deficiency

Followup / Closeout."

(2) TUGCo was committed to audit annually all applicable elements of

the QA program. This internal audit program is based on an

annual schedule of audits in areas of continuing and ongoing

safety-related activities. Organizations, disciplines, and

areas or activities to be audited are based on review and

evaluation of site procedures. Subactivities within a given

organization, discipline, or area are audited on a sampling

basis determined by the current site schedules. Therefore, site

procedures and instructions form the basis for the majority of

the audit programs; however, there is no intent that all

implementation activities of all procedures and instructions

will be audited annually (p.aragraph 3 of this report), TUGCo is

Based on the NRC's inyection of the

'

internal audit program

complying with their internal audit program commitments.

i

(3) Westinghouse (W) site personnel's principal responsibilities

were to coordinate construction site activities relative to the

i

W equipment and to provide advice and consultation on testing

)

and startup programs. While most of the necessary audits of

!

, . . _ .

- .

.

- . -

.

- . . - - - .

.

.

. . . .

.

.

.

-7-

these W site responsibilities are performed through TUGCo audits

of thel corporate offices (e.g., Pensacola or Monroeville),

periodic audits onsite are necessary. Such an onsite audit was

conducted in November 1984. The scope of this auait included

the review of the qualifications of the site personnel and

resulted in one finding. Then in September 1985 an evaluation

of the W site activities was made, which concluded that a 1985

audit was not merited based on the absence of problems and no

changes in the W scope during the previous year.

In sumary,

limited items are auditable onsite and these items are now

considered for auditing each year; most W site functions are

controlled by the offsite W organizationi and these are audited,

evaluated, or both annually.

(4) Amendments 52 and 54 to the FSAR were submitted to the NRC on

August 2;,1984, and January 21, 1985. These amendments

proposed the adoption of Regulatory Guide 1.144, which comitted

TUGCo to a minimum of annual evaluations of vendor performance

and triannual audits of vendor QA programs. By NRC letter

(Noonan to Counsil) dated September 30, 1985, this proposal was

accepted with certain changes in the wording. These word

changes were made in Amendment 57 dated December 20, 1985.

Currently, the NRC finds that the vendor audit program is in

compliance with TUGCo comitments.

(See paragraph-3 of this

appendix.)

The subject of the audit program and auditor qualifications is

continuing to be assessed by the CPRT in ISAPs VII.a.4 and VII.a.5,

and the NRC is inspecting this activity on a continuing basis. TUGCo

will respond to this item when efforts on these ISAPs are complete.

Accordingly, this item remains open.

h.

(Closed) Violation (445/8432-05;446/8411-05): One of six inspectors

training files reviewed had not completed the required eddy current

testing course.

The procedural requirement in violation was deleted.before the end of

the subject inspection on the basis that eddy current capabilities

were not necessary for these inspectors. An NRC review of several

TUGCo audit reports supported this TUGCo position.

i.

(Closed)UnresolvedItem(445/8432-04;446/8411-04): Without the

number of required annual audits clearly defined, it could not be

determined if there existed an adequate audit staff to effectively

implement the comitted audit program.

The scope of the internal audit program is more clearly defined

currently, and there are presently 12 internal auditors. Additional

support is available through contract personnel and TUGCo plans to

.

_

.-

.

-

.

._

.

.

_

-8-

qualify other QA personnel as auditors to supplement their staff as

necessary. The scope and staffing of the internal audit program is

addressed further in' paragraph 3 of,this report.

j.

(Closed) Unresolved Item (445/8432-06; 446/8411-06): The onsite

surveillance program appears'to~ lack sufficient purpose, direction,

coordination, and feedback to the overall QA program.

In late 1984, the site surveillances were performed by one group of

four individuals and a supervisor. Currently these surveillances are

conducted by four groups with a total staff of 29. The surveillance

groups functional areas and staffing are: documents, 4 people;

startup/ turnover, 5 people; construction, 8 people; and inspection,

12 people. The surveillance program is defined and controlled by six

procedures. These procedures address the concerns expressed in the

previous NRC inspection. A more detailed NRC inspection of the total

onsite surveillance program is provided in paragraph 4 of this

report.

3.

Applicant Management of QA Activities

-

a.

Organization and QA Program

The NRC inspectors reviewed the QA comitments described in FSAR

Section 17.1, " Quality Assurance During Design and Construction,"

through Amendment 56 dated October 15, 1985.

Since the NRC's last

inspection in this area (50-445/8432; 50-446/8411), several changes

have occurred in the QA program (e.g., adoption of triannual audits

of vendors discussed elsewhere in this report) and organization.

A Director of QA has been added to the QA organization who reports to

the Vice President, Nuclear Fuels and QA. Re

are the managers of QA (Dallas) and QC (site) porting to this director

The functions and

.

responsibilities of the Manager of QA are essentially the same;

however, reporting to this manager are an assistant manager and four

supervisors; vendors, audits, QE and administration.

Except for the

changes in titles, the functions and responsibilities of the QC

Manager are the same; however, a QC Services Supervisor and a QC

Surveillance Supervisor have replaced the QA Supervisor, and a QC

'

Coordinator has been added.

While the division of QA/QC functions and responsibilities remains

essentially the same between the site and corporate office, the

organizational changes have divided some activities and provided

additional management control.

In addition, a number of personnel

,

changes have been made in the past year including new QA and QC

j.

Managers. The corporate QA staff has increased slightly, but the

site QC staff has increased more than 50 percent. This increased

staff has provided among other things, more attention to product

'

l

quality through surveillances of QC inspector effectiveness and

hardware,

i

!

i

e

.

.g_

The aforementioned changes in staff and QA/QC emphasis has resulted

in revision and restructuring of the implementing procedures. The

NRC inspectors reviewed several of the revised and new procedures.

The results of these reviews are provided in subsequent paragraphs of

this report.

Revision 15(October 15',1985) of the Corporate Quality Assurance

Program was reviewed. This program continues to provide the

corporate policy concerning QA and a description of comitments to

assure that all phases of design, fabrication, construction, testing,

and operation are consistent with quality requirements.

A QA program change intended to involve utility management more

closely in QA matters was the formation of the Senior Management.

Overview Comittee (SM0C) in September 1985. The functions of this

comittee are described in DQP-CQ-5. This comittee, which meets at

least three times per year (more often as necessary), is composed of

the following members: the Vice Presidents of Operations,

Engineering / Construction, and QA; Director of QA (chairman); Managers

of QA and QC; and Operations QA Supervisor. The minutes of meetings

conducted thus far were reviewed by the NRC inspector. These were

consistent with the controlling procedure.

In this area of the inspection, no violations or deviations were

identified.

b.

Reviews of QA Program Effectiveness

The CPRT provides management with an ongoing view of the quality and

effectiveness of the QA program. The NRC assessment of CPRT efforts

are provided in monthly inspection reports. Management programs in

addition to the CPRT include the periodic SM0C meetings, audits by

outside organizations (e.g., INP0 in 1985 and JUMA scheduled for

1986), and trend analyses of NCR's and "UNSAT" inspection reports for

construction activities and deficiency reports for operations

activities.

The construction trend reports for November and December 1985 were

reviewed for compliance with Procedure QI-QP-17.0-1, Revision 1,

" Preparations and Distribution of Trend Reports." Potentially

adverse trends and conditions were identified in these reports. The

responses to the November and December reports were reviewed to

assure proper actions were taken. Corrective actions in the November

report response included the replacement of a craft foreman in the

electrical discipline with a request for additional monitoring in

that area. The management evaluation of the December report is still

in process.

Two SM0C meetings had been held by the end of 1985. The first SM0C

meeting was on September 25, 1985, with the second in November. The

minutes of both meetings were reviewed by the NRC inspector. This

I

. .

-

.

. ~... _

. _.

-

,

-

=-

-

'

. .

-10-

i

i

i

forum provides a means of resolving QA issues and developing QA

positions by management with diverse organizational interfaces. Two-

,

,

-

procedural weaknesses were noted concerning the minutes of these

neetings: . attendees were not listed nor is there a means of

identifying the. sequence of the meetings; e.g., sequential . numbering

,

by year.

  • '

c.

Procurement Control

I-

Purchase orders (P0s) to seven currently active vendors were reviewed

by the NRC inspectors to verify that appropriate quality requirements

.

were included based on QA reviews,-vendors were properly on the

approvedvendorslist(AVL),andvendoraudits/evaluationswere

current. These P0s were processed in'accordance with commitments

except for the following.

I

!

Two P0s were issued to Metal-Bellows (for flexible metal hose)

CPD-0320 in May 1980 (with three supplements in November 1980,

January 1981, and April 1982) and CPD-0322 (with supplements in

December 1984,May, September,andOctober1985). The preaward

survey (PAS) was performed April 23-24, 1980, and the vendor was-

placed on the AVL; however, no audits or reevaluations, as required

,

by DQP-QA-15, "TUGCo QA Audit Program," and DQP-VC-11, " Vendor

i

Evaluation Methods," were conducted until the audit of January 23-24,

'

1985, which was required at least every three years, and a

,

reevaluation performed August 16, 1984, which was required annually.

1

This is a further example of the violation identified during a

previous NRC inspection (445/8432-03; 446/8411-03). The action taken

F

.

by TUGCo (the January 23-24,1985, audit) brought this item back into

4

compliance with the current TUGCo vendor audit program.

.

The PO with Stone & Webster Engineering Corporation (S&W),

I

CPF-12658-5, issued in July 1985 and presently containing four

'

supplements, was reviewed by the NRC inspectors, which procured

engineering services for pipe stress and qualification activities,

i

The PAS was scheduled for July 9-10, 1985, but was cancelled and S&W

was placed on the AVL-based on the NRC letter from the Vendor

Inspection Branch dated August 1983 approving the S&W QA topical

i

report, SWSQAP 1-74, Revision D.

The P0 nor any of its supplements

impose this QA topical on S&W, nor is there other documentation

i

indicating that S&W is using this topical for the activities procured

in this P0. This oversight was identified to TUGCo personnel and P0

Supplement 5 was initiated and issued on February 18, 1986, imposing

Revision D of SWSQAP 1-74 on all applicable S&W activities.

<

,

In addition to the above reviews the NRC inspectors reviewed the

various revisions of the AVL from July 1983 to January 1986,

comparing the vendors on the AVL with the required audits and

>

evaluations. The AVLs prior to 1985 contained at least 18 vendors

.

with delinquent audits. This condition was identified in NRC

i

Inspection Report 50-445/8432 as a violation. By the end of-CY 1985

l

-

i

r

-

- - - - , . . . , , . _ , _ . _ , , .

.m.-.-m_m,--

.- ,

,,_,_,..-m

mm - mw

. , _ , _ . , _ , , , _ , , , , , , , .

..,,,w-

,,-nr.

. ~m.-'s

r'M'--r---er-'--?w'enY

s

~. .

=

.

. --.

.

.

.-

--

. .

..

,

-11-

the vendors on the AVL were current based on the NRC inspector's

review of vendor audits and evaluation reports compared with the

,

" active" vendors on Revision 24 of the AVL dated January 1986. This

'

recovered control was the result of: (1)'deliberateauditand

evaluation scheduling; (2) the re-statusing of applicable vendors to

,

" Inactive" or completely deleting them; and (3) the adoption by TUGCo

and subsequent NRC approval of Regulatory Guide 1.144, Revision 1,

which permits triannual audits with annual evaluations of vendor.

performance.-

d.

Internal Audits and Auditors

1

During the NRC inspection of the TUGCo QA audit program, the

following documents were reviewed: audit procedures, 1985 and 1986

audit schedules, audit reports, and audit records.

The "TUGCo Dallas Procedures / Instructions Manual" was reviewed to

verify procedural control-of QA Division organization, personnel

indoctrination and training, QA manual, QA records, document control,

I

and corrective action relative to the audit program. Procedural

controls were adequate except for two areas. Methods to provide

.

assurance that the applicable elements of the_QA program were audited

annually were not procedurally defined, and review of documents that

input to the audit plan / schedule was not documented formally.

,

The qualifications of the audit and vendor surveillance staff were

reviewed. The results of this review will be used in assessing the

CPRT activities on ISAP No. Vll.a.4. Auditors added to the staff in

1985 increased the total staff number and the average years of

,

'

experience. NRC review of the 1985 audit schedule as performed found

the construction audit schedule had been met.

,

Twelve audit packages from 1985 were reviewed to determine adequacy

,

L

,

of audit team makeup, time spent on audits, audit and audit checklist

!

preparations, audit documentation, and. followup of corrective action.

The twelve audit samples included audits of document control,

l

engineering, procurement, QA/QC, operations, and site contractors.

l

In all cases, audit preparation, performance, and followup were in

compliance with applicable procedures. One audit, TCP 85-10, on

'

!

valve assembly and installation had open deficiencies, but review

!

showed that correspondence was timely and that an identified

deficiency was receiving a higher level of management attention as

l

required by procedure.

!

The 1985 audit schedule was reviewed to determine if all applicable

elements of the QA program had been audited. A matrix of audits

-

performed versus applicable criteria of Appendix B to 10 CFR Part 50

l

had been developed by the QA audit supervisor for tracking purposes.

This matrix,- however, is not under procedural control and did not

l

1

- ~.__ _

.

.

.

.

.

.

-

.

.

.

-12-

assure that all applicable elements of the QA program were audited in

full; only that the criteria identified had been audited in part.

Thisitemremainsopen(446/8602-0-02).

A required document review for impact on the audit plan / schedule of

documents such as: HRC correspondence, CPSES Procedures / Instructions,

Construction /Startup Surveillance and Status Reports, and Quality

Trend Reports was stated by the QA audit supervisor to have been

performed. This review, however, was not formally documented relative

to its performance, what personnel performed the review, and the

outcome of the review. This subject is considered an open item

(446/8602-0-03).

4.

CPSES QC Surveillance Program

During the period of TRT activity at CPSES, and subsequent HRC

inspections, the QA site surveillance program was found to be poorly

structured and ineffectively implemented.

In March 1985, the applicant

reorganized and restructured the surveillance program, and revised

existing procedures or provided new procedures for its implementation.

This program is conducted under the responsibility of the surveillance

supervisor who reports directly to the QC manager.

The QC surveillance program implemented at CPSES is structured to provide

a vehicle by which ongoing construction, inspection and startup/ turnover

related activities may be monitored by site certified personnel to assure

proper and consistent methods of construction, inspection, and

documentation are maintained.

Currently, the surveillance progran is divided into four areas:

(a) Construction,(b)RecordReview,(c) Inspection,and

(d) Startup/ Turnover, with a QC supervisor for each area.

a.

Construction Surveillance Group

Construction surveillances, implemented by TUGCo

Procedure CP-QP-19.0, " Construction Start-up/ Turnover (CST)

Surveillances," provide for surveillance. of construction activities

in accordance with site construction procedures. These surveillances

are performed by observation of work in progress, completed work,

and/or review of documentation. The areas of activity covered by

these surveillances include construction, fabrication / installation,

equipment storage and maintenance, and housekeeping practices.

Surveillances are performed using prepared checklists whose

attributes are derived from the procedures that control the activity

under surveillance. Personnel conducting surveillances are trained

in the applicable procedures and certified as surveillance

specialists.

The NRC inspector's review of CP-QP-19.0 found that the procedure

provides adequate description and direction for the conduct of

.

..

.

-

-13-

surveillances by this group. Surveillances are unscheduled;.however,

the area and frequency are determined by the surveillance supervisor

with consideration given to the level of construction activity, the

results of previous surveillances, and project trend information.

Surveillances by this current group were initiated in October 1985.

During December 1985 and January 1986, the emphasis was directed to

the as-built verification of cable tray supports in Unit 2 to prevent

a repeat of the problems encountered in Unit 1.

These support

surveillances resulted in corrective action that revised the as-built

verification inspection procedure.

This inspector reviewed five surveillance reports conducted in

October 1985 and found that all the reports revealed compliance with

the procedure; however, the checklists did not identify the specific

items observed, nor were the results of observations other than

" SAT /UNSAT" clearly documented.

In discussions with the group

supervisor, he stated that this condition was recognized by the

surveillance supervisor and program improvement was implemented.

This inspector's review of documentation for surveillances performed

in January and February 1986 noted improvements and found that

identification of items and observation results were adequately

documented.

b.

Records Surveillance Group

This surveillance activity, implemented by TUGCo

Procedure CP-QP-19.11A, " Records Surveillance," provides a review of

documentation for permanently installed items to verify that Unit 2

QA records package contents are complete and documents contained

therein(e.g.

reports,etc.}operationstraveler,welddatacards, inspection

are legible, accurate, and in compliance with the

applicable procedures.

Reviews are accomplished'using a generic

surveillance report checklist of attributes common to all record

packages. Deficiencies, when found, are recorded on the surveillance

checklist which then becomes the surveillance deficiency report (SDR)

issued for the required corrective action.

Followup verification for correction of SDRs is accomplished and

documented within the surveillance group by the surveillance document

reviewer who originated the report or the group supervisor. Closeout

of the SDR is documented in either case by the supervisor's

signature.

If an NCR is issued, it is processed in accordance with

existing site procedures for the control of nonconformances.

Verification of the implementation of the NCR disposition is

accomplished by QE and QC external to the records surveillance group.

Copies of the surveillance reports are issued to the corrective

action group for trending. Personnel performing surveillances are

trained and certified as documentation reviewers.

.

.

.

-14-

The NRC inspector reviewed Procedure CP-QP-19.11A and found that the

procedure is sufficiently detailed as to purpose and scope, and is

adequately descriptive of the attributes necessary for the

performance of the reviews and detection of deficiencies.

Additionally, the NRC inspector reviewed all documentation

surveillance reports for January, February, and March 1986 and found

that the performance and reporting of these-surveillances was in

compliance with the controlling procedure.

c.

Inspection Surveillance Group

Inspection surveillances, implemented by TUGCo Procedure CP-QP-19.13,

" Inspection Surveillances," provide surveillances of construction-

related QC inspection effectiveness by sample reinspection of QC

accepted item / component and/or observations of inprocess QC

inspection activities. Surveillances are tentatively scheduled on a

monthly basis with concurrence of the site QC manager, with

consideration given to the level of QC field inspection activity,

results of previous surveillances, and Project Connodity Trend Report

information.- Component reinspection is conducted on selected items,

with emphasis placed on assessing hardware quality through

verification of hardware and evaluation of original inspector results

when unsatisfactory conditions are found.

Personnel performing these

surveillances are trained in the applicable construction and QC

inspection procedures and certified as inspection surveillance

specialists. Deficiencies detected by these surveillances are

documented on NCRs that are processed under the existing site

nonconformance procedure. Verification of the implementation of the

NCR disposition and closeout is accomplished by QE and QC external to

the inspection surveillance group.

Although the inspection surveillance program was reorganized and

restructured in late 1985, the inspection surveillance group activity

has been-limited due to the time raquired for hiring, indoctrination,

training, and certification of personnel and procedure preparation

and approval.

Inspection surveillances were well underway by

March 1986.

The NRC inspector's review of CP-QP-19.13 found that the procedure

provides adequate description and direction for the conduct of

surveillances by this group. Additionally, this inspector reviewed

the reports for all surveillances (18) conducted through the end of

March and found that the surveillances were performed and documented

in compliance with the procedure.

d.

Startup/ Turnover Surveillance Group

The startup/ turnover surveillances, implemented by TUGCo Procedure

CP-QP-19.0, " Construction, Startup/ Turnover Surveillances," provide

surveillances of activities as outlined in the TUGCo startup

administrativeprocedures(SAPS). Surveillances include the review

._

.

.

__ __

.

. _ -

. _

_ _ _

. _ . . _ _

_

_ ..

j

,

.

-15-

1

of the SAPS for progransnatic requirements, the witnessing of

prerequisite tests, and establishing " hold points" for witness, by

this group, on all pre-operational tests conducted by the startup-

group. Additional responsibility includes surveillance of system

turnover activities.. Personnel performing these surveillances are

,

trained in the applicable procedures and certified as surveillance

9

specialists.

The NRC inspector's review of CP-QP-19.0 found that the procedure

provides adequate description and direction for the conduct of

surveillances by this group. Surveillances are unscheduled; however,

j

the area and frequency are determined by the surveillance supervisor

with consideration given to the level of startup/ turnover activity,

the results of previous surveillances, and project trend report

.

information. Deficiencies detected are addressed in SDRs. Followup

verification for correction of deficiencies is accomplished and

documented within the surveillance group by the specialist who

,

'

originated the report, or the group supervisor.

If an NCR is issued,

it is processed in accordance with existing site procedures for the

control of nonconformances.

Verification of the implementation of

,

i

the NCR disposition is accomplished by QE and QC external to this-

surveillance group.

The NRC~ inspector reviewed the reports for the months of October 1985

.

through February 1986 and found that, although the surveillances were

!

in compliance with procedures, the checklists did not adequately

identify the item under surveillance and the results of observations

,

i

were poorly documented. This condition was recognized by the

i

surveillance supervisor and program improvement had been im)lemented.

The MRC inspector's review of surveillance reports for Marci 1986

found that the condition had been corrected.

,

i

i

e.

Training Qualification and Certification

!

TUGCo surveillance personnel are indoctrinated, trained, qualified,

I

and certified in accordance with TUGCo Procrfure CP-QP-19.9,

l

" Training, Qualification and Certification of Surveillance

i

Specialists." This procedure provides the detailed requirements for

~,

l

the level of activity performed by the specialists in each of the

four surveillance groups and identifies the documentation to be

retained in each employee's training file.

,

'

The NRC inspector reviewed the files for all surveillance personnel

.

to determine that the documentation and file contents provide

I

objective evidence that the procedural requisites leading to

certification have been met, were in compliance with the procedure,

and that there was evidence of TUGCo verification of education and

i

previous employment. This review found that on-the-job

!

training (0JT) was waived for three specialists. The waivers were

based on prior certification as QA specialists in startup/ turnover

I

i

4

. . - . , . - . _

. , - - , , . - . , , - - . _

- , , . . . .

, , , . _ . _ . , _ . . _ _ _ _ - _ _ _ . . - - _ , - . .

. .

.

. - .

. .

. -

.

.

-16-

surveillances and the justification was documented in their file.

One document reviewer had completed the training requirements but had

not been certified to date. The NRC inspector found that the work

performed by this reviewer was approved by the supervisor in

accordance with procedural requirements.

The NRC inspector's review found that the conduct of training,

qualification, and certification of surveillance specialists and the

supporting documentation was in compliance with procedures.

f.

Review of Surveiliance Reports and SDRs

The NRC inspector reviewed surveillance reports to determine

compliance with the applicable procedures. This review found that

the surveillance checklist attributes developed by the surveillance

specialists were derived from the procedures, drawings,

specifications, and other documents applicable to the activity, item,

component, or system and the source documents were identified on the

checklist. The supervisor's signature on the checklist indicated his

approval prior to use. Observations were recorded on the checklists

and SDRs or NCRs, if applicable, were issued.

SDRs were processed in accordance with TUGCo Procedure CP-QP-19.10,

" Surveillance Deficiency Reports." The NRC inspector's review of

this procedure found it adequate in its descriptive detail and

direction to control the processing of the SDRs. The NRC inspector

reviewed a sample of SDRs from each of the applicable surveillance

groups and found that the deficiencies were adequately described, the

corrective action was clearly stated, and followup verification by

the SDR originator was documented. Additionally, the required review

and approval signatures were entered.

All surveillance group logs reviewed were current for the issue,

closure, and transmittal of the surveillance reports, including the

SDRs, to the assigned records storage location.

g.

Trend Evaluation and Reporting

In addition to the detection and correction of deficiencies, the

determination of QC inspection effectiveness, and the acceptable

quality of hardware, one of the surveillance program objectives was

to assess the collective output of the surveillance groups by

performing trend evaluations to ascertain the need for programmatic

corrective actions.

In interviews with the corrective action group supervisor,

responsible for the trend analyses, and the site QC manager they

stated that the trend evaluations of surveillance reports through

Itarch 1986 had not yielded sufficient data to establish trends.

t

. ,.

,

-

-

_~

.

--

-

_

. . - .

'

a

.

-

i

-17-

,

4

The QA/QC corrective action group (CAG), responsible for trending,

has performed preliminary assessments of the available surveillance

data on an ongoing basis. The site QC manager's evaluation of the

preliminary assessments to date resulted in additional training of

'

personnel and' procedure revisions to increase effectiveness.

Additionally, the CAG is utilizing these preliminary . assessments as

4

input to the development of criteria for establishing the trending

l

program of surveillance findings. The NRC inspector reviewed the

preliminary assessments and in further discussions the site QC

j

manager stated that the initial surveillance program trending results

will be included in the April 1986 trend report.

L

This inspection found that the trending program was implemented in

t

compliance with the applicable procedures, although still in its

formative stages. The pending inclusion of the surveillance program

'

trends in the April 1986 trend report will remain an open item

,

(446/8602-0-04).

Future NRC inspections will consider the

i

effectiveness of the trend criteria, the evaluation process, and the

trend results.

h.

Summary and Conclusion

'

,

This inspection found that the applicable procedures were adequate to

,

control the surveillance process. The review of surveillance

checklists, surveillance reports, SDRs, verification of personnel

certifications, and interviews with supervisors and surveillance

.

personnel found that the surveillance program, except for the open

item regarding trending, was implemented in compliance with the

i

applicable procedures.

During this inspection, an additional concern was identified that

i-

requires further review by the NRC. The surveillance function

reports organizational 1y to the site QC manager as do the QE group

,

and all QC inspector groups, ASME and non ASME. The majority of the

'

output of the surveillance group activities is a direct measure of

the performance and effectiveness of these groups, and therefore of

'

the site QC manager's assigned responsibilities. Consequently, there

i

exists a potential for violation of Criterion I of 10 CFR Part 50,

Appendix B, which requires that organizations (i.e., the surveillence

groups) have sufficient organizational freedom to identify quality

!

problems and initiate, reconnend, or provide solutions. This subject

l

isconsideredanopenitem(446/8602-0-05).

,

l

No violations or deviations were identified in this area of

inspection.

i

!

!

.

i

f

' _ . . , , , - _ _ , _ _ _ _ .

_____..._,,_y.y,,,_

-__,.m___,._,,,__.,m,___,

_ , _ , , _ _ _ _ _ . .

.

. , , , - ~ , _ _ . .

.

'

o

e

-18-

5.

Assessment of Allegations

,

a.

4-85-A-121 and 4-85-A-131: Improper Actions Concerning the Inspection

Process Control Group

The following allegations were made by four individuals concerning

theInspectionProcessControl(IPC) group: 4-85-A-121, QC inspectors

are signing inspection reports " SAT" when the proper entry should be

"NA," further this individual did not trust the Safeteam; and

4-85-A-131, (1) IPC personnel were directed to document problems on

three-part memos, not on NCRs; (2) proper action was not taken in all

cases regarding problems documented on three-part memos; e.g., NCRs

not written, other paperwork not processed, or generic evaluation not

performed.

The NRC inspector reviewed the IPC organization and controlling

procedures. The IPC group was established in early 1985 to

systematically perform reliability assessments of the QC inspection

process by independently inspecting samples of post-process

'

inspection attributes and identifying when process corrective action

was necessary. Procedures reviewed controlling this activity were

IPC-1, " Organization and Administration of the Inspection Process

Control Program," and IPC-3, " Reliability Assessment Program."

IPC-3

required that all current QC inspectors work be sampled at the end of

every 30 day period and the results be documented in a Sample Recheck

Request / Report (SRRR) form. The SRRR forms, when rejectable

attributes were identified, were sent to QE who initiated the

1

necessary corrective action.

IPC personnel were advised of the

action taken by QE for information purposes only.

(1) 4-85-A-121

The NRC inspector reviewed the completed SRRR forms for all QC

'

inspectors. A sample of SRRR forms that were in process (QE

review not completed) was also reviewed. The dispositioning of

^

identified rejectable attributes for 24 QC inspectors (70 SRRR

forms) was reviewed. This review included all of the associated

documentation; e.g., drawings, changes, NCRs, and inspection

reports (irs).

Of the 70 SRRR forms reviewed, the NRC inspector found 80

examples where " SAT" was entered by the QC inspector when "NA"

would have been the proper entry. Examples of IR attributes

j

where " SAT" was incorrectly entered were Nelson stud spacing,

but liiltis were used; triax cable, but not used; ring torque lug,

'

but ring torque lug not used; cable tray rung spacing, but it

was a solid tray; and supports, but no supports.

In a few of

the above examples an NCR was issued. When an NCR was issued,

the disposition was usually to correct the documentation,

nothing else indicated. When no NCR was issued, the corrective

action ranged from no action to a commitment that the QC

. . - - - - - - -

- .

-.

. . _ _ , - - - - -

_ _ _ - , _ . , _ _ _ - - _ _ - - - - - - . _ -

- - ~ . _ _ _ . _ _ . . .

.

-19-

inspector's supervisor would be advised. These examples

occurred from July 1985 to December 1985, when the IPC program

was revised and new personnel assigned. The QE basis for no

action in several of the examples where no NCRs were issued, was

that marking " SAT" where "NA" was applicable does not render the

quality of the item unacceptable. The NRC inspector agrees;

however, the numerous occurrences of this problem does indicate

a condition that is adverse to quality, which in the absence of

corrective action is a violation of Criterion XVI of 10 CFR Part 50, Appendix B.

Monthly IPC reliability assessment reports

to QC management identified this as a problem. The October and

November 1985 reports identified this problem as a generic

deficiency and requested action from the QC supervisor. The QC

supervisor sent a memo on January 24, 1986, to the training

supervisor to prepare a class for training personnel in the

implementation of CP-QP-18.0, " Inspection Report," but did not

mention the " SAT vs NA" problem. As of the end of March, this

training had not been scheduled. The foregoing is considered a

violation of Criterion XVI of 10 CFR Part 50, Appendix B

(446/8602-V-06).

In sumary, numerous examples were identified that substantiate

the allegation that " SAT" was used on inspection reports when

"NA" should have been used.

Since no details or basis were provided concerning this

individual's distrust of the Safeteam, the NRC was unable to

assess this concern. The CPRT is evaluating the exit interview

p(rogram established for the site which includes the Safeteam

ISAP No. VII.a.6). The NRC will be inspecting the

implementation of this effort.

(2) 4-85-A-131

The NRC inspector's review of applicable procedures did not

identify any provisions for the use of three-part memos to

document problems.

During the NRC inspector's review of the IPC monthly reliability

assessment reports, it was noted in the September and

October 1985 reports that potential discrepancies unrelated to

l

the attributes being inspected were identified on three-part

memos and sent to the applicable QE group. On further review

the NRC inspector found that not only were three-part memos

'

being used to document potential nonconforming conditions, but

the three-part memos were not being tracked and there was no

formal followup to assure that they were properly dispositioned.

l

This condition was identified as a violation in a previous HRC

InspectionReport(50-445/86-01). An informal log of the

three-part rcemos was found within the IPC group, but there was

no assurance that all memos had been logged.

L

.

.

-20-

Forty-seven memos were identified on this informal log; however,

six can no longer be found. The 47 problems referred to in the

log were reviewed by the NRC inspector. The problems identified

on some of the memos that were located resulted in NCRs being-

issued, while others appeared to require an NCR but none were

issued. On February 28, 1986,_NCR E-86-200637 was issued

requiring all retrievable memos to be reviewed and where

nonconforming conditions were found to; exist an NCR would be

issued.

Included in the action on.this NCR will be a reinspection in the

areas where the six missing three-part memos originated. The

conditions identified on the informal log will be the point of

focus in an attempt to identify the source of the original

concerns. This area will be inspected further by the NRC when

action on the NCR is completed. Accordingly, this matter is

consideredopen(446/E602-0-07).

In conclusion, the allegations were substantiated, with one

exception. Numerous examples were found where QC inspectors

,

were completing irs with " SAT" when "NA" was the appropriate

I

entry (4-85-A-121). This was recognized by TUGCo as a generic

problem, but they failed to identify the magnitude of the

problem or take prompt action to correct, resulting in a

violation of 10 CFR Part 50, Appendix B. -It could not be

established that IPC personnel were directed to docuent

problemsonthree-partmemos(4-85-A-131);~however,this

practice was permitted and'was also identified as a violation.

It could not be determined that proper action was taken

concerning.the problems identified on these three-part memos in

every case. TUGCo recognized this and issued an NCR to

reevaluate all of the actions taken. The NRC will inspect the

disposition of this NCR when it is completed. The lack of trust

in the Safeteam on the part of one alleger could not be assessed

due to the lack of specifics; however, this program is being

evaluated by the CPRT and the NRC is inspecting the

implementation of this effort.

b.

-AQ-161 (4-85-A-31): QA Deficiencies Not Documented

It was alleged that Operations QA handled deficiencies without

documenting problems; thus, no preventative actions were effected

and, consequently, QA problems identified by operations did not

appear to be reported to the appropriate level of management.

The FSAR commitments for control of nonconforming materials, parts

and components were reviewed. Section 17.2.15 of the FSAR commits

and requires that nonconforming conditions be identified, documented,

reviewed, dispositioned, and reinspected for acceptability after

.

,

-21-

dispositioning is completed. Further, Section 17.2.16 commits to

reporting significant conditions adverse to quality to the

appropriate level of management.

To verify the inniementation of the above nonconformance reporting

commitments, the NRC inspectors reviewed ongoing work to determine if

nonconforming conditions were documented, dispositioned, and

-appropriate corrective action taken to prevent recurrence.

In NRC

walkdowns of selected rooms, it was observed that nonconforming

conditions for safety-related hardware were brought into compliance

with the item's specification and/or drawing without an NCR being

written. These occurrences, as well as other departures from the

nonconformance reporting system discovered during NRC walkdowns, were

reported as a violation in a previous Region IV Inspection Report

(50-445/86-01).

In assessing the portion of the allegation dealing with problems not

being reported to management, it was found that NCRs were not

reviewed on a periodic basis for adverse quality trends as required

by the Op(OA.C&QAP), Section 3.9, "Nonconformances, Deficiencies and

erations Administrative Control and Quality Assurance

Program

Corrective Action." Consequently, the commitment that periodic

analysis of NCRs be forwarded to management to show quality trends-

did not occur. Applicant QA personnel were interviewed to determine

why the deviation from this commitment occurred. The reply was that

trend analysis performed in the early days of the Operations QA

program did not identify meaningful trends or recurring significant

conditions adverse to quality.

For calendar years 1984 and 1985, 421

and 240 NCRs, respectively, were written.

During the assessment of the operations nonconformance reporting

system i

identify,t was observed that the applicant has a separate method to

report,'and take corrective action on procedural

(programmatic) deficiencies that is different from the methods used

on hardware deficiencies. The deficiency report is used to document

procedural deficiencies.and the NCR is used to document hardware

deficiencies. Each employee is required to report observed

procedural deficiencies on a deficiency report and submit it to

operations QA for processing. The NRC inspector found that for 1985

approximately 50 percent of the deficiency reports (203) were written

j

by non-quality personnel. Monthly, quarterly, and annual trend data

i

reports were published presenting those deficiency reports. These

trend reports were issued to various levels of management including

onsite and offsite senior management.

Based on trend analysis of

deficiency reports, recurring conditions found adverse to quality

!

were reported on corrective action requests to the appropriate levels

.of management. Therefore, the procedural system for deficiency

reporting does identify, document, and report programmatic problems

to the appropriate levels of management.

i

I

b

.

.

-22-

Deficiency reporting procedure, STA-404, Revisions 1, 2, and 3, used

from February 1982 to January 1986 (current), were reviewed. The NRC

inspector found no revision that clearly differentiated between the

use of a deficiency report and NCR in the purpose, applicability, and

definitions sections. Revision 2 dated June 1985 revised the

deficiency report process instructions to include blocks "yes" or

"no" for specifying an NCR is required in connection with the

deficiency reports. Therefore, the deficiency reports written prior

to June 1985 potentially may not have NCRs written, even if hardware

deficiencies were present as a result of procedural violations that

were reported in the deficiency report system. Accordingly, the

deficiency reporting system used prior to June 1985 may not have

caused the identification and reporting of nonconforming hardware on

NCRs.

In conclusion, the potential that Operations QA corrected hardware

nonconformances without documenting them on an NCR, and thus without

corrective action to prevent recurrence, does exist. Accordingly,

this allegation was substantiated.

The portion of the allegation that QA problems were not reported to

the proper level of management was partially substantiated. NCRs

were not trended to identify conditions adverse to quality and

therefore not reported to management. However, quality trends for

deficiency reports were reported to the applicable levels of

management. The substantiation of this allegation has the following

implications in the Operations QA area: (1)inadequateidentification

and reporting of nonconforming conditions; (2) no NCR trend analysis

for 1984 and 1985; and (3) no evaluation of deficiency reports (prior

to June 1985) to determine if an NCR was required in connection with

the deficiency reports. These items have been identified as a

violation (445/8603-V-02).

c.

'AQ-156 (4-85-A30) and AQ-163 (A-85-A31): Improper Processing Of

Deficiencies

It was alleged that surveillance management did not initiate

corrective action when a surveillance identified QC directing craft

intheinstallationofequipment(AQ-156);andQCinspectorsallowed

craft to correct deficiencies during final QC inspections without QC

recording the "UNSAT" condition on the IR; thus, circumventing the

trendingprogram(AQ-163).

The NRC inspector determined that although the allegations were

resented by different allegers they pertained to the same subject

p(event). The allegers referred to a recent surveillance of

electrical conduit installation, but did not identify the

surveillance report by number or date. The NRC inspector searched

the surveillance report files and interviewed the construction

startup/ turnover surveillance (CSTS) supervisor and found that

surveillance report DSR 85-023 dated March 28, 1985, was consistent

.

- . _ -

..

-.

- . .

. _ .

-

- -

-_

^

.'

'.

L

-23-

,

with the subject and time frame expressed by the allegers.

DSR 85-023 contained information which provided the details and

4

"

.

. probable basis for the allegations.

(1) AQ-156

Based on the alleger's statements, the allegation was

characterized that QC was instructing electrical craft how to

install electrical conduit. Craft had not finished the job

correctly and QC was telling craft what had been-done wrong;

i.e., the junction box has to go this way, or this has to be

over here. The alleger perceived the foregoing as a concern

that QC was instructing craft in the performance of their job

"

and that when the surveillance supervisor was advised of this

i

concern he did not initiate any action.

In review of the applicable construction and QC inspection

procedures for this assessment; the NRC inspector did not find

j

any procedural constraints that would prohibit QC inspectors

from providing clarification of deficiencies, nor from providing

recommendations for their correction. The alleger did not

identify, nor did the NRC inspector find any procedural

deviations or program violations. The alleger's concern was

,

related to an activity which appeared to be an example of the

proper implementation of 10 CFR Part 50, Appendix B,

i

Criterion I, " Organization," which states in part:

"The authority and duties of persons and organizations

performing quality assurance functions shall be clearly

established and delineated in writing. Such persons and

organizations shall have sufficient authority and

i

organizational freedom to identify quality problems, to

initiate, recomend, or provide solutions, and to verify

the implementation of solutions."

.

This assessment found that the procedures in place complied with

this criterion and the alleged practice was not a violation.

The surveillance supervisor did not agree that the described

activity constituted "QC instructing craft," but rather was an

example of QC implementing the requirements of 10 CFR Part 50,

'

Appendix B.

The NRC's assessment of this allegation supports

the decision of the surveillance supervisor.

While the allegation was substantiated, both QL and the

'

j

surveillance supervisor were acting in compliance with

requirements.

,

(2) AQ-163

Surveillance report DSR 85-023, discussed above, also provided

j

the detail necessary to the definition and assessment of this

l

- . . - - . -

.-

-

- - . .

. - . . . -

. . - .

. , . , , - - - - _ . _ - - - - - - - - - ,

-.

.

_

_ ._

-

_ _ _ .

.

.

4

-24-

l

j

allegation. This allegation is further characterized that

during QC inspections the accompanying craft would correct an

"UNSAT" condition detected by-the inspector, but there is a

gotentialthattheinspectorwouldnotdocumenttheinitial

UNSAT" on the inspection report.

If this occurred, the "UNSAT"

finding would not be captured as input to the trending program.

The NRC inspector found that this allegation was identified as a

'.

concern in DSR 85-023 issued to the site QC inspection

supervisor. The QC supervisor's response cited the words of

TUGCo Procedure CP-QP-18.0, " Inspection Report," that required

the QC inspector to record any identified "UNSAT" condition

without regard to the time or circumstances under which the

"UNSAT" condition was found. The surveillance report package

contained evidence that the res)onse was reviewed and accepted

by the surveillance specialist w1o identified the concern, and

the surveillance supervisor had reviewed, approved and closed

the report.

The NRC inspector interviewed the electrical QC inspection

supervisor, electrical inspectors, the site QC inspection

supervisor, and mechanical inspectors. The NRC inspector

-

described the concern being assessed. These individuals were in

agreement that it was common practice for craft to accompany and

correct "UNSAT" conditions identified during QC inspections. As

the procedure required, the inspector would record the "UNSAT"

'

condition, notwithstanding its immediate correction, and there

l

was no resistance by craft to this process. These individuals

also stated they were not aware of any cases of procedural

noncompliance regarding the recording of this type of "UNSAT"

'

conditions.

l

Based on reviews of procedures, documentation, and interviews

!

with personnel, this assessment did not find any evidence that

i

"UNSAT" conditions were not recorded nor that the construction

i

and inspection activities related to the concern were conducted

in other than compliance with the applicable procedures. Since

.

there was )rocedural compliance and the alleger did not identify

'

or state t1at there was procedural noncompliance, there is

assurance that the "UNSAT" conditions were identified as

j

required and included in the trending program. Accordingly,

this allegation was not substantiated.

,

,

d.

4-85-A-130: A concern was raised by an anonymous caller that a

designchangeauthorization(DCA)allowedthereductionofNo.16AWG

4

sized electrical wire to No. 18 AWG size, and that this was a

!

breakdown of the engineering controls. The DCA identified by the

caller was DCA 18,016 dated July 8, 1983. This DCA affects the

2

internal wiring of four termination cabinets, 1-TC22 and 1-TC23 in

i

I

-

. . .

_-____.._._..,___-,,__.___,,___,.,_____m

_ __-__._ ,_ ___

_ , _ _ _ , _ . , . , , . _ _ . , _ . ,

..

.

-25-

Unit 1 and 2-TC22 and 2-TC23 in Unit 2.

These termination cabinets

are located in their respective unit's lower cable spreading room.

When a cable connector was added to each of these termination

cabinets in order to connect its internal wiring to the appropriate

section of the main control board, it was determined that the

connector would only accept connection to No.18 AWG, or smaller,

electrical wire. The cabinets' internal wiring,'which was-installed

by the vendor, was specified on drawings numbered W-TC22701-D,

W-TC22702-D, W-TC23701-0 and W-TC23702-D, for cabinets 1-TC22,

2-TC22,'l-TC23 and 2-TC23, respectively, to be 16 AWG minimum

stranded, copper with 17 mil Tefzel insulation, gray.

In an effort

to resolve the problem of the installed wiring being larger than the

connector would accept, DCA 18,016 was initiated.

The DCA 18,016 solution states, "Use the #16 AWG Tefzel wire for the

internal connections from the terminal strip to the connector.

Remove enough strands from the #16 AWG, by using the #18 AWG

stripper, to reduce the size of the wire to #18 AWG at the connector

end of wires. Note: This DCA is for clarification only. Design

review is not necessary." A Field Design Change - Design

Verification Report was, however, completed on June 3,1984

This

report concluded, based on a telephone conversation with the vendor,

that " approval of this DCA is based on the assurance that the #16 AWG

Tefzel wire will become no less than a size #18 AWG when the strands

are removed."

Following the NRC inspector's questioning of the feasibility of

performing the DCA's proposed solution, he was informed that tests

conducted by the applicant confirmed the removal of strands with a

wire stripper was impractical.

Initial inspection of this subject identified what appeared to the

NRC inspector to be, less than 16 AWG size internal wiring connected

-to terminal board, TB-2, in the Unit 1 termination cabinets, 1-TC22

and 1-TC23; additionally, these wires had orange and green colored

insulation, respectively. The wiring in the Unit 2 cabinets, 2-TC22

and 2-TC23, appeared to the NRC inspector to be the correct wire size

which had the specified, gray colored insulation.

In an effort to

verify the acceptability of the wiring in the Unit 1 cabinets, a

review of the vendor surveillance, receiving inspection and

installation / modification documentation was conducted. The NRC

inspector was unable to locate any record that other than the

specified (#16~AWG, gray Tefzel insulated) wiring had been installed

by the vendor or any documentation to indicate that a wiring change

had been authorized onsite. The applicant's representatives,

however, have provided information, in response to the NRC

inspector's requests, to indicate that changes to the installed

wiring in 1-TC22 and 1-TC23 have been authorized by DCAs 8939 and

8940 for the use of additional wire, if required, to complete earlier

.

o

-26-

wiring modifications; however, no records had been located, as of the

end of this report period to indicate which wire was actually

installed nor how the #16AWG wire was reduced to #18AWG. ThisJmatter

is an unresolved item ending completion of the applicant and NRC

reviews (445/8603-U-03.-

The applicant's representatives also provided the NRC inspector with

completed copies of the construction operation travelers

(EE85-11696-2-5202 and EE85-11693-2-5202) which were used to install

the cable connectors in the Unit 2 termination cabinets, 2-TC22 and

2-TC23. -Review of these documents-indicated that it was recognized

that the solution proposed in DCA 18,016 was impractical, and

instructions were included to use small, diagonal pliers to remove 6

of the 19 strands from the No. 16 AWG wire so that connection to the

connector could be accomplished. The DCA, however, was not revised

to reflect this new solution. The failure to revise the DCA is an

apparent violation of Criterion V of Appendix B to 10 CFR Part 50

(446/8602-V-08).

6.

Pipe Supports

During a previous pipe support inspection, the NRC inspector observed two

baseplates of pipe support No. AF-1-035-029-533A, which were attached to

the wall with eight 1" Hilti Kwik Bolts, three of which were installed

through an embed plate. Subsequent to this inspection, additional review

of the documentation identified a violation.

A B&R memo dated October 19, 1980, addressed drilling through an embed

plate and hitting a rebar at a 5-1/2" depth that appeared to run at a 45'

angle to the vertical. The response from the design engineer stated that

no structural rebar should be encountered at this location and depth and

was probably a construction installed " Template" bar and could be cut as

required.

On November 6, 1980, NCR M-80-00161 was initiated, addressing drilling

through the rebar and the requirements of B&R Procedure CEl-20 which

states that engineering approval is required to cut rebar.

In addition,

the NCR stated that the above mentioned memo gave approval for drilling

through the probable template bar at the 5-1/2" depth; however, the NCR

also identified two other cut rebar. The tentative disposition of the NCR

!

was "use as is."

In support of this disposition, DCA 9091 was initiated

i

on November 18, 1980, addressing one cut rebar. The solution of the DCA

l

stated that the described condition is acceptable. The DCA also listed

the NCR as being supporting documentation. As a result of the DCA

approval, the NCR was closed on December 19, 1980, and it referenced

DCA 9091 as support for the "use as is" disposition.

!

The failure to disposition all of the identified nonconforming conditions

j

isaviolation(445/8603-V-04).

!

i

I

i

!i

_

Q

e

-27-

7.

Followup on NRR Liner Plate Concerns

A public meeting was held on November 5-6, 1985, in Granbury, Texas, to

discuss licensing issues for the Comanche Peak project. The subject of

deviations identified during the reinspection / verification sampling

program was addressed by ERC and NRR.

Personnel from ERC indicated that

excessive undercut on containment liner welding had been identified as a

deviation from inspection procedure requirements, and documented on a DR.

The safety significance evaluation (SSE) group from ERC analyzed specific

cases where excessive undercut exists and determined that the safety

function of the containment liner had not been impaired. The basis for

this conclusion was that the specific material properties provide a design

margin that is not compromised by the depth of the undercut identified.

Personnel from NRR expressed concern that the identified deviation was a

code violation (Proposed Section III, Division 2 of the ASME Code) and

questioned what actions would be taken by the applicant. The team leader

for ERC's QA/QC review team responded that a minimum of three actions

would be taken by the applicant: determine if corrective action is

necessary; determine if applicable commitments were violated; and

determine reportability requirements per 10 CFR Part 50.55(e).

Due to the expressed concern identified by NRR, a n. ore comprehensive

evaluation of quality of construction for containment liner plate was

initiated. The NRC inspector identified that ERC Verification Package

No. I-S-LINR-060 DR-2 documented undercut greater than 1/32", which is a

deviation from quality standards required by paragraph CC-4542.3 in

ACI-359. This paragraph states, "The surface of welds shall be free from

coarse ripples or grooves, overlaps, and abrupt ridges or valleys. Abrupt

changes in section thickness such as undercuts or reinforcements which do

not exceed 1/32", and which do not encroach on the section thickness

required to satisfy the rules of CC-3000, are permitted. The surface

condition of the finished weld shall be suitable for the proper

interpretation of nondestructive examinations (NDEs) of the weld.

If the

surface of the weld requires grinding, care shall be taken to avoid

reducing the weld or base material below the required thickness."

In addition to the above requirement, G&H Specification 2323-SS-14,

Revision 3, paragraph 8.4.2.3 states, "The surface of welds shall be free

from coarse ripples or grooves, overlaps, and abrupt ridges or valleys.

Abrupt changes in section thickness stch as undercuts or reinforcements

which do not exceed 1/32 in, and whic'i do not encroach on the section

thickness required to satisfy the design are permitted. The surface

condition of the finished weld shall be suitable for the proper

interpretationofnondestructiveexaminations(NDEs)oftheweld.

If the

surface of the weld requires grinding, care shall be taken to avoid

reducing the weld or base material below the required thickness."

As a result of ERC DR I-S-LINR-060-DR-2 being issued and validated, TUGCo

issued NCR M-85-101128SX. This NCR was awaiting disposition as of the end

of this report period.

Review of the disposition of this NCR is an open

item (446/8602-0-09).

(

.

.

-28-

The NRC inspector reviewed portions of the following containment liner QA

records: welding procedure specification; welder qualification records;

NDE p(CBI) quality assurance manual; CBI RT film and reports of RTrocedu

Co.

examinations; and CBI record drawings, which document all containment

liner weld joint fabrication activities.

While reviewing RT film and reports of RT examination for Unit 2

containment liner welding of seam No. P84, Film #146, the NRC inspector

noted that the term " pickup and reshoot" was entered in the remarks column

and film grading was marked unacceptable for a line entry documenting the

results of Film #146 Tracer 2.

Tracer 2 was required due to weld

inclusions identified by CBI when grading Film #146.

'

Discussion with a.CBI QA superintendent revealed that " pickups" are

surface imperfections that require additional work for cosmetic purposes

on the area in question to comply with specifications, code and/or CBI

requirements and customer /CBI evaluator interpretations.

The NRC inspector reviewed the CBI RT examination procedure,

RTP-(74-2427/8), and noted that paragraph 5.1 states, "The weld ripples or

weldsurfaceirregularitiesonbothinsideandoutside(whereaccessible)

shall be removed by any suitable means to such a degree that the

radiographic image due to any irregularities cannot mask or be confused

with the image of discontinuity."

In addition to the surface preparation

requirement before performing radiographic examination, a CBI inspector

whowascertifiedasbeingqualifiedforvisualexamination(VT),had

signed the finish joint checked column on the record drawing, indicating

that fabrication of the weld joint complied with the applicable

specifications and standards.

Section CC-5521.1.1 of ACI-359 states, in part, "If the 12" radiograph in

the 50-ft-long increment of weld does not meet the acceptance standards,

two 12" film shall be taken at other locations within the 50-ft-long

increment . . . if either of the second radiographs does not meet the

acceatance standards . . . the remaining portion of the 50-ft increment

of tiis weld shall be radiographed."

Subsequent to the unacceptable film grading of Film #146 T2, CBI welders

deposited additional filler material to-resolve the unacceptable linear

indication identified by markup of the radiographic film. The additional

weld material did eliminate the marked-up indication. However, the NRC

inspector identified that an unacceptable linear indication existed at

film location #146 T2 in addition to the " pickup" (additional welding)

performed by CBI to remove an unacceptable linear indication.

Section CC-4545.3.1 of ACI-359, defect removal, states, " Unacceptable

defects detected visually or by the examinations required by CC-5500 shall

be removed by mechanical means or by thermal gauging processes. The area

prepared for repair shall be examined and comply with the requirements of

CC-5533(MT)orCC-5534(PT)."

__

,

.

.

.

-29-

Contrary to the requirements of ACI-359, CBI did not expand the

!

radiographic film examination of containment liner welding when an

unacceptable tracer location linear indication was identified; performed

I

unauthorized, undocumented repair welding at the tracer location; and

failed to implement the required NDE examinations when repair welding was

performed. These findings constitute a violation (446/8602-V-10).

8.

CPRT ISAPs (Excluding ISAP No. VII.c)

a.

Flexible Conduit to Flexible Conduit Separation (ISAP No. I.b.1)

The objectives of this action plan are (1) to determine by testing

and analyses the minimum acceptable separation between two cable

trains within SERVICAIR flex and (2) to reinspect all panels which

potentially could violate the final separation criteria.

Paragraph 4.1.4 of this ISAP requires: (1) revision of

Drawing 2323-El-1702-02, " Cable and Raceway Separation Typical

Details," and any other related documents to reflect this final

separation criteria; (2) revision of the applicable QC inspection

procedures; and (3) review of these revisions by the Review Team

Leader (RTL). NRC inspector review of the above documents disclosed

the following:

(1)DCA21,446, Revision 1,datedOctober8,1985,

approved modifications to the control board internal wiring

separation criteria by providing revised and additional typical

details for separation requirements to Drawing 2323-El-1702-02,

Revision 2; (2) TUGCo Instructions QI-QP-11.3.40, " Post Construction

Inspection of Electrical Equipment and Raceways," Revision 21, dated

January 8,1986, and QI-QP-11.3-28, " Class IE Cable Terminations,"

Revision 28, dated March 7, 1986, both reference the revised

separation requirement by drawing details and specifically discuss

theServicairflexibleconduit;and(3)therewerenorecordsinthe

CPRT files to document the RTL review of the above changes.

Documented review by the RTL will complete this item (NRC

Reference No. 1.b.01.07).

No NRC violations or deviations were identified.

b.

Conduit to Cable Tray Separation (ISAP No. I,b.3)

The oujective of this action plan is to substantiate the

acceptability of the criteria governing the separation between

conduits and cable trays, and submit the evaluation and supporting

-

documentation to the NRC.

The NRC inspector evaluated the CPRT files to determine which of the

aspects of this action plan had been completed. The five aspects

submittal to the NRC, (4) preparation, (2) report review, (3) report

involved are: (1) report

personnel qualification, and

(5) acceptance /decisioncriteria.

..

..

.

___

.

.

-30-

Review of the CPRT working files revealed that the initial analysis

of conduit to cable tray separation was.provided by G&H letter dated

September 27, 1984. This analysis was required because no formal

analysis had been performed to justify the design and construction

documents. Review of the G4H analysis by the RTL and the Third Party

Advisor resulted in clarifications to, and the removal of

inconsistent assumptions from, the provided analysis. These problems

were discussed in the RTL's March 12, 1986 memorandum. A final

revision of the analysis was provided in the G&H letter to TUGCo

dated March 6, 1986.

'

TheRTLapprovedRevision0oftheresultsreport(RR)onMarch14,

1986, and transmitted the report to the SRT. The SRT requested

certain clarifications to the report which were incorporated into

Revision 1 by the RTL. Revision 1 of the RR was approved by the SRT

on March 26, 1986.

The NRC inspector also reviewed the FSAR change request

documentation.

(A FSAR change request is required to be initiated as

l

part of the Action Plan.) The initial FSAR change request was

submitted to TUGCo by G&H letter dated September 19, 1985; comments

I

by the TUGCo FSAR coordinator have resulted in a finalized change

request.

Further review of the CPRT files for this ISAP indicated that

appropriate personnel resumes and objectivity questionnaires were

included and acceptable; therefore, this aspect of this ISAP is

considered complete.

Revision 1 of the RR concluded that the separation criteria for

conduit to cable trays meets the intent of IEEE-384 (1974) and

Regulatory Guide 1.75, Revision 1, January 1975, and, therefore that

the acceptance criteria had been met and no root cause evaluation was

required.

The formal submittal of the RR will be evaluated for technical

adequacy and documented in separate correspondence.

No NRC violations or deviations were identified,

c.

QC Inspector Qualification (ISAP No. I.d.1)

During this report period, NRC inspections were conducted for the

activities identified by NRC Reference Nos. 1.d.1.03, and 1.d.1.04.

SET Evaluation of ASME and non-ASME Inspector Qualification

(NRC Reference No. 1.d.l.03)

TheNRCinspectorconfirmedthattheSpecialEvaluationTeam(SET)

had completed the Phase II review of the remaining inspector

qualifications by reviewing the sumary sheets for these inspectors.

_ _ _ _ _ _ _ _ _ _ _ _ _

.

.

-31-

Additional inspectors may be added as a result of other ISAPs. The

summary sheets were found complete and to meet the requirements of

this ISAP. Using the Phase II review as a basis, the SET validated

the Phase I reviews conducted by TUGCo Audit Group of non-ASME

inspectors and the Phase I reviews conducted by ERC of ASME

inspectors. These reviews were previously reported by the NRC

inspector. Sumary sheets requiring response from TUGCo are being

addressed. The NRC inspector reviewed 5 percent of the TUGCo

responses that have been completed and found that the TUGCo responses

addressed the SET identified problems. The completed TUGCo responses

have been sent to the ERC QA/QC RTL who is responsible to determine

if inspectors whose qualifications cannot be demonstrated as

satisfactory will be evaluated in Phase III. The NRC inspector will

review the results of these evaluations as they are completed.

No NRC violations er deviations were identified.

Phase III Sample Selection and Reinspection (NRC Reference No. 1.d.1.04)

The NRC inspector reviewed the qualification records system utilized

by TUGCo. The qualification records system was found to be a

computerized program of required qualifications versus inspector

certifications. The system provides a means of ensuring that

collected qualification data can be recorded in a clear and concise

form that is readily retrievable. Additionally, the system provides

an effective means of identifying inspectors requiring updates to

their certification files such as annual evaluations or annual eye

exams. This system is in part a result of recommendations coming

from the implementation of this ISAP.

No violations or deviations were identified.

d.

Guidelines for Administration of QC Inspector Tests (ISAP No. I.d.2)

During this report period, NRC inspections were conducted for the

activities identified by NRC Reference No. 1.d.2.02.

-

Evaluate Recomendations and Revise Instructions (NRC Reference

,

No. 1.d.2.02)

-

The NRC inspector verified that the subtasks in paragraph 4.1.2 of

this ISAP have been completed. The daughter instructions of

CP-QP-2.1 have been deleted and their training requirements

incorporated into a more comprehensive CP-QP-2.1.

Inspector

certification exams currently in use by TUGCo have been revised to

assure that they meet the current procedural requirements of

CP-QP-2.1. Accomplishment was verified by review of four

examinations and their exam banks of questions. The NRC inspector

also reviewed other TUGCo improvements made to enhance training,

e.g., creation of a " tickler" system to assure updating of inspector

--

..

'

.

.

-32-

certifications and eye exams and centralized filing of OJT

requirements. No further NRC inspection is planned for this

activity.

No NRC violations or deviations were identified.

e.

Maintenance of Air Gap Between Concrete Structures (ISAP No. II.c)

Th'e following activities for ISAP No. II.c were reviewed by the NRC.

inspector during this report period:

i

Removal of Debris or Rotofoam (NRC Reference No. 2.c.02.00)

The NRC inspector has witnessed cleaning and repair of both single

and double walled gaps on numerous occasions. These inspections

included witnessing the use of a variety of tools used for debris

removal and a review of the overall process.

During this report p(eriod, the NRC inspector witnessed gap cleaning

operations along:

1)theLA-AFwallgapbetweentheAuxiliary

Building and the Fuel Building, (2) the gap between the Unit 1

Reactor Building and the Fuel Building, and (3) the gap between the

Unit 1 Reactor Building and the Auxiliary Building. Most

observations were made from the roof where crews were removing debris

,

at depths of approximately 60 to 90 feet using a variety of specially

built tools. . Activities were observed using remote video equipment.

No NRC violations or deviations were identified.

Analyze Final As-Built Condition (NRC Reference No. 2.c.03.00)

Calculations by G&H of the' minimum gaps required to preclude

interactions of Category I buildings and of the internal structures

and the containment wall of the Reactor Building (calculations

LIS-100c, Set 1 and Set 2) were reviewed by the NRC inspector. These

calculations utilize displacement data from G&H books FMI-IR and

FMI-2R, dated September 1975 and December 1976, respectively. The

NRC review did not extend to the calculations of the relative

displacement data presented in these two books.

The methodology and assumptions used were compared against the design

commitments contained in Sections 3.7 and 3.8 of the Comanche Peak

FSAR. Numerical calculations LIS-100c, Set 1 and Set 2, and the

transfer of relative displacement dats from books FMI-1R and FMI-2R

were. extensively checked.

'

A third party review of these calculations was done by Hansen, Holley

'

and Biggs Inc., Consulting Engineers under contract to TERA, who

concluded that the G&H approach was conservative. The conclusions of

this third party review were examined by the NRC inspector and found

to be consistent with established engineering practices.

!

!

~

.

.-

. - . - .

-

- - - - -

-

- - . ,

_

. .

.

_

-

.

o

.

!

-33-

NRC inspections were not performed on other activities during this

report period.

No NRC violations or deviations were identified.

f.

Improper Shortening of Anchor Bolts in Steam Generator Upper

4

Lateral Supports (15AP No. V.b)

.

The following activities for ISAP No.'V.b were reviewed by the NRC

inspector during this report period:

i

Examine Bolts Blind Threaded Holes, and Assembly Dimensional

Tolerances (NRC Reference No. 5.b.03.00)

i

Reinspection of the bolt holes and threads in the steam generator

upper lateral supports for all compartments in Unit 1 began on

i

March 25, 1986. The following construction operation travelers were

used for this reinspection:

Compartment No.

Traveler No.

1

CE-86-222-8902

2

CE-86-223-8902

3

CE-86-224-8902

l

4

CE-86-225-8902

A total of 144 bolt holes are being reinspected by TUGCo and/or

Westinghouse personnel. The travelers include the reinspection of

the following six attributes:

(1) internal pitch diameter,

(2)internalminordiameter,(3)holedepthandthreadlength,

(4) thread damage, (5) angle of bolt inclination, and (6) bolt to

'

base plate gap measurement.

i

The NRC inspector witnessed partial reinspections of from 1 to 6

attributes on the following 13 bolt holes:

,

j

Location

Bolt Hole Nos.

Compartment 1 West End

1W7, 1W9

Compartment 4 West End

4W1, 4W6, 4W10, 4W13, 4W15, 4W17

Compartment 4 East End

4E7, 4E8, 4E9, 4E16, 4E18

i

'Four of the above bolt holes were unsatisfactory. Bolt holes 4W1 and

4W6 had thread damage.

Bolt hole 4E7 had a misaligned shim requiring

repair before reinspection. Bolt hole 4W15 had excessive bolt to

,

l

base plate gap.

i

l

!

-.. , _

- . - -

-

- , - - , , . . - . - .

. . - . - .

.__..- - -..,, , _ - __~ ..--

-,

, - - - - , . . - - _ . --

.

i

o

.

-34-

The NRC inspector also reviewed the reinspection procedures as

specified in the above listed travelers and witnessed the exchange of

temporary bolts for compartment 1.

Temporary bolts were installed in

either 3 or 4 bolt holes, in a pattern specified by G8H to provide

temporary support of the beams during reinspection.

NRC inspections were not performed on other activities during this

report period.

No NRC violations or deviations were identified.

g.

Installation of Main Steam Pipes (ISAP No. V.g

The following activity was identified in NRC Inspection Report

50-445/86-01; 50-446/86-01 as being part of the program proposed by

the applicant. This activity had not been previously inspected by

the NRC.

Activity

ISAP

NRC

Paragraph No.

Reference No.

Interview Personnel Involved with

4.2

5.e.02.00

Steam Line Adjustment

The CPRT conducted interviews with personnel involved with the steam

line adjustment, in order to establish a starting point for assessing

the steam line adjustment and reconstructing the sequence of events.

Discussions with the involved personnel by the NRC inspector

confirmed these CPRT interviews. This activity is now complete.

No NRC violations or deviations were identified.

h.

Receipt and Storage of Purchased Haterial and Equipment

(ISAP No. VII.a.9)

ISAP No. VII.a.9, issued during this report period, is a result of a

concern by the NRC that verification of material and equipment

compliance with procurement / design requirements needed to be

addressed. This is the initial report for this ISAP and the specific

activities of this ISAP are delineated in the following table. The

activities will be reported as they are completed.

Table of Activities for ISAP No. VII.a.9, Receipt and Storage

of Purchased Material and Equipment

Activity

ISAP Para

NRC Reference No.

Select Procured Items to be Audited

4.1.2

7.a.9,01

.__

_ _ _

.

.

-35-

Develop Checklists for Program Review

4.1.3

7.a.9.02

,

Review Program Documents for Adequacy

4.1.3

7.a.9.03

Develop Checklists for Records Audits

4.1.4

'7.a.9.04

Perform Audit of Records

4.1.5

7.a.9.05

Identify Deviations

4.1.5

7.a.9.06

Qualification of Personnel

4.3

7.a.9.07

1.

Onsite Fabrication ( ISAP No. VII.b.1)

During this report period, the activity identified by NRC Reference

No. 7.b.1.02_was inspected as follows:

Identify and Select Samples from ASME and non ASME Fabrication

(NRC Reference No. 7.b.l.02)

The NRC inspector verified the selection of safety-related fabricated

items. This was accomplished by the NRC inspector witnessing the

selection activity in part and subsequent review of the entire sample

selection. The sample selection was found to conform to the

requirements of this ISAP, para

The selection of ASME

packages (principallyhangers) graph 4.1.2.2.

is complete. Selection of non-ASME

packages (principally electrical items) is ongoing and will be

reported later.

No NRC violations or deviations were identified.

j.

Hilti Anchor Bolt Installation (ISAP No. VII b.4)

The NRC inspector has verified implementation of the following

activity by witnessing performance of ERC's reinspection / verification

effort in accordance with ERC QI-063, " Reinspection of Torque for

Drilled-In Concrete Expansion Anchors (Hilti Bolts):"

Activity

ISAP

NRC

Paragraph No.

Reference No.

Torque Verification Program

4.1.7

7.b.04.07

To date, 131 of the estimated 180 torque verifications have been

completed, of which the following 18 were witnessed by the NRC

inspector and determined to be acceptable per QI-063:

Verification Pkg. No.

Equipment Tag No.

System *

Unit No.

I-S-HLTV-010

AB-900-1H aG-01

VA

1

1-S-HLTV-216

AB-900-1M-4G-01

VA

1

___

.

.

-36-

I-S-HLTV-024

FB-810-1F-WP2

VA

1

I-S-HLTV-017

FB-806-1G-WPS

VA

1

I-S-HLTV-060

FB-806-1G-WP5

VA

1

I-S-HLTV-037

DG-844-1K-1AZ

VA

1

I-S-HLTV-318

JB15-30130

N/A

1

I-S-HLTV-084

AF-1-043-001-Y43R

AF

1

I-S-HLTV-120

AF-1-043-001-Y43R

AF

1

I-S-HLTV-205

AF-1-043-001-Y43R

AF

1

I-S-HLTV-074

AF-1-043-001-Y43R

AF

1

I-S-HLTV-315

C16R09450-1

N/A

1

I-S-HLTV-203

AF-1-001-021-Y33R

AF

1

I-S-HLTV-107

AF-1-097-020-533R

AF

1

I-S-HLTV-173

CTH-1-341

N/A

1

I-S-HLTV-172

CTH-1-3336

N/A

1

I-S-HLTV-179

CTH-1-5644

N/A

1

I-S-HLTV-175

CTH-1-2696

N/A

1

  • VA - Heating, ventilation, air conditioning

AF - Auxiliary feedwater system

N/A - Not Applicable

The acceptance criteria used by ERC was as follows:

o

The position of the nut was noted prior to torquing by marking

the it.tersection of two flats (point) and the corresponding

location on the attached fixture

o

Torque was applied to the nut and the verification was

determined to be acceptable if either the nut did not turn

before the applicable test torque value was reached, or the

minimum installation torque was reached prior to the nut turning

a full turn.

If the nut turned one full turn before the minimum

installation torque value was reached, the torque verification

was determined to be rejectable.

No NRC violations or deviations were identified.

9.

ISAP No. VII.c

A discussion of the NRC inspection activity is contained in the following

subparagraphs for those populations which were inspected during this

report period:

a.

Electrical Cable

Status of CPRT Activity

ERC has completed 40 reinspections and 78 documentation reviews of

sampled electrical cables as of March 31, 1986. The decrease in the

above total completions from those reported in previous inspection

reports is the result of ERC rework required by revisions to the

.

- __

_ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ .

.

.

-37-

acceptance criteria and by the establishment of (and movement of some

.

sampled cables into) a new population for plant lighting systems. A

discussion of the lighting population is contained in a subsequent

section of this paragraph.

Status of NRC Inspection Activity

The completion status for NRC inspection activity is unchanged from

the previous report period; i.e., the NRC inspectors have, as of

March 31, 1986, witnessed 21 ERC reinspections, performed 6

independent inspections, and conducted 10 documentation reviews.

The NRC inspector observed two unusual looking electrical cables

while conducting an independent inspection related to allegations of

improper electrical cable installation.

(See paragraph 5.d of this

Appendix.) The electrical cables were imprinted with "No. BAWG

VULKENE SUPREME" and were covered with a brown colored insulation.

The cables had been designated safety related, Train A, by the

attachment of bands of orange colored tape and were located in

Train A cable tray T130CCQ34 in the Unit i lower cable spreading

room. These two single conductor cables did not appear to the NRC

inspector, based on his prior knowledge of the list of approved

electrical cable vendors, to be approved for use at CPSES.

Information provided to the NRC inspector by the applicant's QE

representatives, identified the cables as a two conductor cable

numbered E0106306.

In addition, an NCR (No. 82-01977 dated

November 10,1982) had been written to question this cable's

installation. The disposition of NCR E82-01977 states that cable

E9106306, and the Train B counterpart, cable EG106317, had been

supplied by the vendor and were acceptable. A review of supporting

r

records indicated that the cables were provided in October 1982 by

l

General Electric Company (GE) as part of the 125VDC distribution

systems' ground detection circuitry. Review of the AVL, Revision 7,

dated August 1982 showed that the vendor, GE of Plainville,

Connecticut, was an approved vendor.

Based on this information, the NRC inspector had no further concerns.

No NRC violations or deviations were identified.

b.

Cable Trays

Status of CPRT Activity

ERC has completed 103 reinspections and 103 documentation reviews as

of March 31, 1986.

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

-

_

_

_

.

.

'

-38-

J

Status of NRC Inspection Activity

The NRC inspectors have witnessed 11 ERC reinspections, conducted 6-

independent inspections and performed 7 documentation reviews as of

March 31, 1986; these totals remain unchanged from those previously

!

reported.

The performance of the seven documentation reviews was reported in

NRC Inspection Report 445/85-14; 446/85-11, with the results being

made an open item (445/8514-0-09) pending comparison of ERC findings

for the same reviews. -When the comparison of findings was undertaken

during this report period, it was discovered that revisions to the

,

applicable procedure (QI-017) had affected the attributes to be -

verified. Therefore, to assure completeness and clarity, another

independent documentation review was performed of these same

verification packages prior to the comparison of review results. The

verification packages reviewed were for the following Unit 1 cable

trays:

1

Verification Package No.

Cable Tray No.

Location

R-E-CATY-004

T149CDJ17

Cable Spreading Room

R-E-CATY-023

T129CBD68

Room 121

R-E-CATY-024

T139RCJ28-

Reactor Building

R-E-CATY-036

T149SDA05

Room 65

R-E-CATY-055

T129FBUO4

Fuel Building

R-E-CATY-060

T129FBU05

Fuel Building

R-E-CATY-129

T129RBK17

Reactor Building

Comparison of NRC and ERC review results produced the following

common findings:

R-E-CATY-004: An inspector signed off welding as being satisfactory,

but no welding IR or traveler was found. DR R-E-CATY-004-DR01 and

NCR E85-101525SX have been written for this deficiency. This finding

,

!

is an open item (445/8603-0-05) pending disposition of the NCR.

R-E-CATY-024: Using QA records, it could not be verified that the

welder with symbol BSY was qualified at the time he made the weld on

this cable tray. DR-E-CATY-024-DR01 and NCR E85-101525SX have been

written for this deficiency. This finding is an open item

(445/8603-0-06) pending disposition of the NCR.

No NRC violations or deviations were identified.

c.

Electrical Conduit

i

Status of CPRT Activity

'

ERC has completed 29 reinspections and 80 documentation reviews of

sampled electrical conduit as of March 31, 1986. The decrease in the

,

__ , .-.-

- - _

.

.

-39-

number of reinspections from the. number reported in previous NRC

inspection reports has been due to some of the samples being replaced

because of selection questions, the implementation of a new

population for lighting (discussed later in this paragraph) and some

reinspections required by revisions to the applicable procedure.

Status of NRC Inspection Activity

The NRC inspectors have, as of March 31, 1986, witnessed 14 ERC

reinspections, conducted 5 independent inspections, and performed 15

documentation reviews. These totals are unchanged from those

previously reported.

ERC memorandum QA/QC-RT-1626 dated March 12, 1986, which transmitted

Revision 4 of QI-008, was reviewed by the NRC inspector. The

revision to this procedure will require backfit reinspections by ERC

l

to verify the proper rating of junction boxes installed in the

. reactor building. The addition of this attribute will provide

assurance of compliance with the environmental qualification of

terminal blocks installed in these junction boxes.

No NRC violations or deviations were identified.

d.

Electrical Equipment

Status of CPRT Activity

ERC has completed 76 reinspections and 20 documentation reviews of

sampled electrical equipment installations as of March 31, 1986. The

decrease in the number of reinspections and reviews from previously

reported totals was caused by the rework of completed packages to

incorporate additional, new requirements.

Status of NRC Inspection Activity

l

The NRC inspectors have, as of March 31, 1986, witnessed 11 ERC

reinspections, performed 3 independent inspections and conducted 10

l

documentation reviews; these totals are unchanged from those

previously reported.

'

!

The NRC inspector began the comparison of ERC and independent NRC

i

documentation review results for those reviews previously reported as

open items (445/8514-0-12 and 445/8516-0-29). The comparison

activity could not be completed because 7 of the 10 documentation

packages had been returned to the ERC engineering organization for

revision in response to ERC memorandum QA-QC-RT-1382 dated

February 28, 1986.

In accordance with this memorandum, 21

verification packages will be revised, the documentation reviews will

__ _,

__ _

e

.

-40-

be redone, and the results documented using a new checklist. The NRC

inspector will evaluate the need to reperform the NRC documentation

reviews when these verification packages are reissued.

No NRC violations or deviations were identified.

e.

Instrumentation Equipment

Status of CPRT Activity

"

-

ERC has completed 107 reinspections and 107 documentation reviews of

sampled instrumentation equipment as of March 31, 1086.

Status of NRC Inspection Activity

The NRC inspectors have, as of March 31, 1986, witnessed 11 ERC

reinspections, performed 7 independent inspections and conducted 5

documentation reviews of sampled instrumentation equipment.

During this report period, ERC reissued all of the previously

completed instrumentation packages to the instrumentation inspectors

to reinspect for certain attributes. The attributes reinspected

included material identification, tubing size, routing, air gap, and

bend radius. The NRC inspector witnessed three of these Unit I

reinspections during this report period:

Verification Package No.

Instrument No.

System

I-E-ININ-030R

1-PI-4762

Containment Spray

I-E-ININ-034R

1-PI-1094

Boric Acid

I-E-ININ-046R

1-FT-918

Safety Injection

The ERC inspectors identified the following to the NRC inspector as

subject to evaluation as potential deviations:

(1)

I-E- ININ-030R:

(a) The tubing immediately adjacent above and below the drain

valve did not contain longitudinal color coding for

material size, identification, and traceability.

(b) The information to verify flange material identification

and traceability was not included in the verification

package.

(c) Four air gap violations (less than 1/8" clearance) between

the tubing installation and adjacent tubing runs were

identified and are located at:

the bottom of the ceiling

penetration in room 51; approximately 3'-4" upstream from

{

.

.

-41-

the floor penetration in room 66; approximately 4'-4"

upstream from the floor penetration in room 66; and

approximately 4'-6" from the root valve.

(2)

I-E-ININ-034R:

(a) The information to verify flange material identification

and traceability was not included in the verification

packege.

(b) One air gap violation (less than 1/8" clearance) between

the tubing installation and an adjacent tubing run was

identified, located approximately 4'-6" from the root

valve.

(3)

I-E-ININ-046R:

Two air gap violations (less than 1/8" clearance) between the

tubing installation and adjacent tubing runs were identified

and are located at the bottom of the ceiling penetration in

room 54 and approximately 3' north of the vent valve in room 67.

The above six findings are open items pending the NRC inspector's

review of ERC's disposition and/or the applicant's applicable

corrective action (445/8603-0-07 through 445/8603-0-12).

No NRC violations or deviations were identified.

f.

Lighting

This new population was initiated as part of the ISAP No. VII.c.

reinspection and documentation review program because of installation

cnd inspection differences between plant lighting and other

electrical systems. These differences would affect the homogeneity

of the other populations, i.e., cable and conduit, if the lighting

circuits were included.

The procedures that were issued for the lighting system installation

required only limited QC inspection of the distribution panels and no

QC inspection of the other connection boxes or fixtures.

Status of CPRT Activity

ERC has completed 24 reinspections and 62 documentation reviews of

sampled lighting circuits as of March 18, 1986, in accordance with

QI-071 and QI-072, respectively,

i

(

l

l

l

..

_

_

_

__

..

_

.

,

.

-42-

Status of NRC Inspection Activity

The NRC inspector was informed by the ERC electrical engineers on

March 18, 1986, that ERC had completed the documentation reviews for

all 62 verification packages, with few deficiencies being identified.

ERC reinspection of 24 inspection packages resulted in 133 findings,

which were documented in 49 DRs. All of these findings were located

in various junction or pull boxes, which did not require QC

inspection. The most prevalent findings were loose or damaged

crimped splices, damaged wire insulation, and too many wires in the

connection boxes.

(The wire used in the lighting system, except for

long rows of fixtures where stranded wire is used, is solid

conductor, No. 12AWG).

The NRC inspector was also informed that, because of the magnitude

and significance of the findings, ERC had ceased inspection

activities and was preparing a report to present findings and

recommendations to TUGCo. The NRC inspectors will perform some

independent inspections of lighting systems in Unit 2 as the system

is installed.

No NRC violations or deviations were identified.

g.

Large Bore Piping Configuration

Status of CPRT Activity

ERC ha~s completed 84 reinspections of large bore piping

configurations out of the planned random and engineered sample size

of 85. The combined sample size was increased from a previous figure

of 82 as a result of further evaluation of the engineered sample size

in which it was determined that three additional packages were

required to meet the sample criteria.

Fifty-three valid DRs have

been identified and issued.

Status of NRC Inspection Activity

To date, the NRC inspector has witnessed seven ERC reinspections and

performed four independent inspections, of which the following

independent inspection occurred during this reporting period:

Verification Package No.

Drawing No.

System *

Unit No.

I-M-LBC0-148

BRP-RH-1-58-006

RH

1

While performing the independent inspection, three instances were

identified where the separation criteria of paragraph 5.2.6.2 of

QI-025 were not met and documentation could not be located which

-

-

_

.

t

.

.

-43-

would justify this condition. The stated criterion is that a minimum

clearance of 2" must exist between two pipes, including insulation,

when the operating temperature of at least one of the lines equals or

exceeds 200"F. The ERC inspector signed off attribute 1.f on the

checklist, which deals with separation, as acceptable.

(1) Line 2-CC-1-060-152-3 is in contact with the inspected line at a

location 6'6" north of wall 7-S and 10' west of wall D-S.

The

two lines are parallel and are in contact for about 4'.

(2) Line 2-CC-1-061-152-3 is in contact with the inspected line at a

location 12'6" north of wall 7-S and about 8' west of wall D-S.

(3)' Line 1-CC-1-062-152-3 is closer to the inspected line than the

allowable 2" at a location 6'6" north of wall 7-S and 7'6" west

of wall D-S

Theseidentifiedinstancesconstituteadeviation(445/8603-D-13).

h.

Small Bore Piping Configuration

Status of CPRT Activity

ERC has completed 87 reinspections of small bore piping

configurations out of the combined random and engineered sample size

j

of 88. Sixty valid DRs have been identified and issued by ERC.

'

Status of NRC Inspection Activity

To date, the NRC inspector has witnessed seven ERC inspections and

performed two independent inspections, of which the following

independent inspection occurred during this inspection period:

Verification Package No.

Drawing No.

System *

Unit No.

1-M-50C0-101

BRP-CC-2-AB-044

CC

2

,

  • CC - Component Cooling Water System

1

No NRC violations or deviations were identified.

i.

Instrument Pipe / Tube Supports

Status of CPRT Activity

ERC has cor.pleted 106 reinspections of instrument pipe / tube supports

out of the combined random and engineered sample size of 111. Three

hundred thirty-nine valid DRs have been identified and issued by ERC.

ERC has completed 34 document reviews of these packages with 4 valid

DRs being issued to date.

-

_

..

..

__

-.

.

.

._ _

- . - . .

.-.

.

_ .

. .

-

.

-

.

--

-

. -

-.

.

a

44-

-

Status of NRC Inspection Activity

To date, the NRC inspector has witnessed four reinspections and

<

performed seven independent inspections of which the following two

independent inspections occurred during this reporting period:

Verification

Instrument

<

Package No.

Tag No.

Sy stem *

Unit No.

I-S-INSP-107

1-PT-2326-C

MS

1

I-S-INSP-126

1-PT-2328

MS

1-

i

No NRC violations or deviations were identified.

j

HVAC Duct Supports

.

Status of CPRT Activity

A. total of 89 HVAC duct supports were randomly selected from a

population of 2580 supports representing Units 1, 2, and common. To

l

date ERC has inspected 79 supports and initiated 253 DRs, primarily

in the areas of undersize welds and configuration discrepancies. Of

the 253 DRs, 233 have, to date, been established as valid.

e

Status of NRC Inspection Activity

To date, the NRC inspector has witnessed seven ERC reinspections and

performed one independent inspection. The independent inspection and

results, are as follows:

Verification

Duct

l

Package No.

Support No.

System *

Unit No.

I-S-HVDS-075

DG-844-2K-1J

DG

2

,

  • DG - Diesel Generator

I-S-HVDS-075: QI-035, Revision 0, requires that verification be made

with respect to weld sizes meeting the requirements of the duct

support detail drawing. The checklist applicable to this

verification package showed that the ERC inspector had measured and

'

accepted two skewed fillet welds using a Fiber Metal Fillet Gauge.

'

The NRC inspector found that neither a Fiber Metal Fillet Gauge nor

any conventional measuring device could be used to measure one leg of

the fillet on each weld.

The ERC inspector's acceptance of these welds is an NRC deviation

(446/8602-D-11).

,

J

.n-,-

- - ~ . , , - -

, - , , -

-..g...

.

,n..

--.

._.,.n,

-~...-n.

, ., ,..- ,, - , ,.-. _, ,,,-.,,,,. .-.

-

- .

-

,

.

..

.

___

___

_ _ _ _ _ _ _ _ _ _ _ _ _

.

.

-45-

QI-035 requires verification of member lengths and all other

dimensions that describe the lengths and positions of members in the

support frame. This attribute on the checklist was signed off as

being acceptable by the ERC inspector. The NRC inspector identified

that for several members, there was either a lack of, or insufficient

information provided in the drawing. Therefore, verification of

member lengths could not be performed.

'

The ERC inspector's acceptance of this attribute is an NRC deviation

(446/8602-D-12).

Section 5 in Revision 2 of CPP-008 states in part, ". . . Should an

attribute appear on the generic checklist and not be applicable to

the specific item, the engineer indicates 'N/A' and provides

reasonable justification for the entry." The NRC inspector observed

that attributes 2F.1, 2F.2, and 2F.3 dealing with enhed plates and

spacing violations had been N/A'd by the engineer. The_noted

justification for this entry was "No embedded Pls;" however, the NRC

inspector identified the existence of an embed plate with dimensions

of approximately 20'X8".

The engineer's error relative to this attribute is an NRC deviation

(446/8602-D-13).

k.

Reinspection of Small Bore Pipe Supports

Status of CPRT Activity

Reinspection of the combined random and engineered sample of 76 small

bore pipe supports is complete. Ninety-seven deviations have been

identified, and to date, 53 have been evaluated as being valid.

Documentation review is also complete with 23 valid deviations

identified. Thus far, a total of 56 valid deviations have been

evaluated for safety significance with no safety significant

deviations being identified.

Status of NRC Inspection Activity

The NRC inspector has witnessed 7 reinspections and independently

inspected 11 small bore pipe supports. The following three supports

were independently inspected during this report period:

Verification

Pipe

Package No.

Support No.

  • System

Unit No.

I-S-SBPS-031

WP-X-AB-042-010-3

WP

Common

I-S-SBPS-034

SW-1-SB-013-009-3

SW

1

l

_ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ - _

o

.

-46-

I-S-SBPS-246

CH-X-FB-009-002-3

CH

Common

  • CH - Vcntilated Chilled Water system

SW - Service Water System

WP - Solid Waste Processing System

The NRC inspector reviewed ERC Description Memorandum QA/QC-RT-1436

and ERC QI-019, Revision 3. Paragraph 5.3.5(A) of ERC QI-019 includes

the addition of a clarification of the requirements for clearance.in

the gravity direction between the pipe and the support for small bore

box frame supports, and states, in part, "Where design shows 0 inch

on one side and 1/16 inch on the other side, the sum of both gaps may

not exceed 1/8 inch or be less than 1/32 inch *. . . ."

  • Where design shows 0" on bottom (in the gravity direction) then it

shall be such with no allowable variation."

The clarification preceded by -an asterisk was not included in

previous revisions of QI-019.

Section II of ERC Description Memorandum QA/QC-RT-1436 lists changes

incorporated in Revision 3 of ERC QI-019 and, with respect to

paragraph 5.3.5(A) states, in part, "Added clarifying information on

allowable clearances for dead weight and 0" clearance

supports . . . ."

Attachment A to the above ERC Description Memorandum lists previously

issued reinspection packages and states that Yerification

Package I-S-SBF'i-051 is not affected by changes incorporated in

Revision 3 of ERC QI-019.

The NRC inspector previously measured a gap of 1/16" in the gravity

direction for Verification Package I-S-SBPS-051. Drawing CP-AA-040,

Revision 0, for this pipe support specifies a clearance of zero in

the gravity direction. The changes in Revision 3 of QI-019 do, in

fact, affect the previous inspection of Verification Package

I-S-SBPS-051. ThisconditionisanNRCdeviation(445/8603-D-14).

1.

Documentation Review of Fill and Backfill Placement

Status of CPRT Inspection Activity

Documentation review of fill and backfill placements is nearly

complete with 179 of 180 packages reviewed. A total of 310 valid

deviations have been identified.

ERC DR R-S-FILL-GEN-DR-1 was issued

to address inspector certification for the safe shutdown impoundment

dam construction during the period April 24, 1976, through April 19,

1977.

Inspection certification documentation for Freese & Nichols

Consulting Engineers and Mason & Johnson Associates, Inc. could not

be located. This DR applies to 60 of the 180 fill and backfill

packages and is an open item (445/8603-0-15).

- - _ _ .

.

-

--.

. . .

---

.

..

-47-

Status of NRC Inspection Activity

The NRC inspector performed independent documentation reviews of the

following seven fill and backfill packages:

Verification Package No.

Inspectors Daily Report No.

R-S-FILL-015

1184

R-S-FILL-027

1425

R-S-FILL-035

1417

R-S-FILL-043

1191

R-S-FILL-125

B&R Dated 12/1/77

R-S-FILL-140

B&R Dated 12/29/77

R-S-FILL-143

B&R Dated 9/14/77

4

No NRC violations or deviations have been identified.

m.

Inspection of Non-Pressure Boundary Welds for a Supplementary

Evaluation of Visual Welding Inspection Techniques

Status of CPRT Activity

To date, 52 randomly selected samples of weld joints obtained from

ISAP Nos. VII.b.3 and VII.c populations have been inspected before

removal of coatings. The following 29 were inspected during this

report period:

Verification Pkg. No.

Equipment Tag No.

System *

Unit

I-S-NPBW-015

RC-1-135-907-C47W

RC

1

I-S-NPBW-077

RC-1-135-909-C47W

RC

1

I-S-NPBW-045

1-TE-5400

NI

1

I-S-NPBW-041

MS-1-003-904-C77W

MS

1

I-S-NPBW-071

CC-1-RB-004-007-3

CC

1

I-S-NPBW-008

VME-1

VA

1

I-S-NPBW-051

8"X18"-90

VA

1

,

'

I-S-NPBW-076

RMD-1

VA

1

I-S-NPBW-086

EMD-6

VA

1

I-S-NPBW-066

EMD-1

VA

1

I-S-NPBW 's33

54"X38" Str Duct

VA

1

I-S-NPBW-026

CB-830-IN-1R

N/A

1

1-S-NPBW-068

FW-1-017-912-C47W

FW

1

I-S-NPBW-025

FW-1-017-913-C47W

FW

1

1-S-NPBW-043

CP2-MEFT1F-01

N/A

2

I-S-NPBW-107

CT-1-008-001-5225

CT

1

I-S-NPBW-111

AF-1-101-001-523K

AF

1

I-S-NPBW-104

CC-1-RB-033-007-3

CC

1

1-S-NPBW-101

CC-1-228-007-C53R

CC

1

I-S-NPBW-109

CC-1-126-702-F43R

CC

1

I

_--__.

-_

_

_ - _ _ _ _ _ _ _ -

_ _ _ - _ .

.

.

-48-

I-S-NPBW-097

EMD-2

VA

1

I-S-NPBW-085

CP-1-ELDPEC-05

N/A

1

I-S-NPBW-096

AB-810-1L-WP23

N/A

1

I-S-NPBW-098

MS-1-RB-036-007-2

MS

1

I-S-NPBW-091

BSC SUB SMD-2

VA

ll

I-S-NPBW-092

AF-1-102-031-543R

AF

1

I-S-NPBW-087

CC-1-EC-006-005-3

CC

1

I-S-NPBW-083

CC-1-EC-007-013-3

CC

1

I-S-NPBW-110

CT-1-047-007-C92R

CT

1

To date, 27 of the randomly selected weld joint samples have been

inspected after removal of coatings. The following second phase

inspections (20) were performed during this report period:

Verification Pkg. No.

Equipment Tag No.

Sy stem *

Unit

I-S-NPBW-035

AF-1-043-001-Y43R

AF

1

1-S-NPBW-063

AF-1-001-021-Y33K

AF-

2

I-S-NPBW-005

1-FI-4695

NI

1

1-S-NPBW-014

FW-1-019-902-C57W

FW

1

I-S-NPBW-046

FW-1-102-901-C57W

FW

1

I-S-NPBW-077

RC-1-135-909-C47W

RC

1

I-S-NPBW-015

RC-1-135-907-C47W

RC

1

I-S-NPBW-016

I-LS-4795

NI

1

I-S-NPBW-052

1-FT-156

NI

1

I-S-NPBW-025

FW-1-017-913-C47W

FW

1

I-S-NPBW-010

MS-1-001-902-C77W

MS

1

I-S-NPBW-017

MS-1-001-908-C67W

MS

1

I-S-NPBW-004

FW-1-017-908-C77W

FW

1

I-S-NPBW-041

MS-1-003-904-C77W

MS

1

I-S-NPBW-076

RMD-1

VA

1

I-S-NPBW-051

8"X18"-90

VA

1

I-S-NPBW-026

CB-830-1N-1R

N/A

1

I-S-NPBW-091

BSC SUB SMD-2

VA

1

1-S-NPBW-067

SG-1-852-1J-1AF

N/A

1

I-S-NPBW-008

VME-1

VA

1

Main Steam System; CC - Component Cooling Water System; VA - Heating,

l

Ventilation, Air Conditioning; FW - Steam Generator Feedwater

'

System; CT - Containment Spray System; AF - Auxiliaiy Feedwater

l

System; and N/A - not applicable.

Status of NRC Inspection Activity

(

'

The NRC inspector has witnessed 100 percent of the inspections performed

on welding in the coated and uncoated condition. Listed below are the NRC

findings with respect to ERC's supplementary evaluation of visual welding

inspection techniques:

._-___

. _.

.

_ .

- - -, --

_ _ . -

-

.

_ _

.

- __

_

.

.

..

-49-

I-S-NPBW-063: . ERC inspection of a 5/16" fillet weld was documented

" accept" in the coated condition. After the weld coating was removed, the

' same weld was documented " reject" due to a 1/2" long segment of weld being

approximately 1/32" undersize. This was documented on a DR and the

disposition of this finding is an open item (445/8603-0-16).

l~

the weld joining item 1 to the support steel identified on Drawing

I-S-NPBW-014: ERC rejected, before removal of the coating, the surface of

FW-1-019-901A-C57W, in accordance with QI-062, Revision 0, Attribute 5.2.D

,

which states " Verify surface of welds are sufficiently free of overlap,

abrupt ridges and ripples so proper interpretation of. radiographic and/or

other required NDE could be accomplished." After removal of the coating,

ERC documented the surface of weld condition as " Accept." The NRC

inspector's examination of the subject > id surface, before and after

removal of coating, identified that the weld surface condition was not

suitable for NDE due to excessive ridges and ripples that could impair

accurate interpretation of NDE results. An NRC review of fabrication

'

records identified that the weld had been examined and accepted by the

magnetic particle (MT) method of NDE by CBI. Subsequent to the NRC

inspection, ERC obtained an independent NDE Level III examiner's opinion,

.

who was contracted from the technical service division of Daniel

International Corporation. Following this independent examination, ERC

i

issued a DR documenting the weld surface condition as " Reject."

'

Acceptance of the weld surface condition by_ERC, during inspections

erformed as re

p(445/8603-D-17) quired by I-S-PWRE-006 and I-S-NPBW-014, is a deviation

i

.

.

I-S-NPBW-107: While witnessing performance of the reinspection, the ERC

inspector identified that grinding at the toe of fillet welding exceeded

the allowable undercut depth. The ERC inspector stated that the QI did

not require inspection for base material defects and the finding would be

documented as an "out-of-scope observation." An NRC evaluation of the

purpose and scope of QI-029, the applicable QI for the population from

,

which reinspection / verification PKG-I-S-NPBW-107 was chosen, did not

include a requirement to inspect base material. The failure of ERC

engineering to identify and include base material defects as a safety

,

significant attribute which can be reinspected, as required by

'

paragraph 5.1 in Revision 2 of ERC's CPP-007, is a deviation

,

(445/8603-D-18).

l

10. Exit Interview

l

Exit interviews were conducted on March 4 and April 4, 1986, with the

applicant representatives denoted in paragraph 1 of this appendix. During

<

these interviews, the NRC inspectors summarized the scope and findings of

-

the inspection. The applicant acknowledged the findings.

i

1


.

,-----.--..-.,,,..,-._.-.,--,-n.

. -

n.,,-.,nn--,

...,-.~-c.,,,,,-

,,-.-e....._-,--,,,

-r,.-n-~

.

,. , , , .

.