Text
.
INSERVICE EXANINATION Pft0GRAN PLAN INTERVAL - 2 PERl00 - 1 OUTAGE - 2 FlNAL FOR THE ZION UNIT #1 NUCLEAR POWER STATION 101 Shiloh Boulevard Zion, Illinois 60099 FOR 9
C00040NWEALTH ED1 SON COMPANY 101 Shiloh Boulevard Zion, Illinois 60099 OUTAGE DATE: October, 1986 C0009ERCIAL SERVICE DATE: December 31, 1973 OPERATING CAPACITY: 1050 NWe PREPARED BY:
WESTINGHOUSE ELECTRIC CORPORATION
\\'
NUCLEAR SERVICES INTEGRATION OlVISION INSPECTION SERVICE P.O. 80X 355 P11TS80RGN, PA 15230 b'.t
\\,
s.r 8706160572 970526 PDR ADOCK 05000295 O
PDR 10:420lr/50187:50
. ~ ~...
Index (Excerpted from Report)
TAB ISI Certificate - Owner Certificate and Owner's Data Report _ _ _ _ _ _ _ _ _ _ _ _ _
A Summary _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _. _ _
B
\\
Examination Program _ _ _ _ _ _ _ _ _ _ _ _ _
C
FORM NIS 1 OWNE25' CATA CEPORT FOR INSESYlCE INSPECTIONS As required by tlw Provisions of etw ASME Code Rules Page 1 of 4 Commonwealth Edison Co.
P.O.
Box 767 Chicago, Illinois 60690 g, %,
(Name and Address of Owner)
Zion Generating Station, 101 Shiloh Blvd, Zion, Illinois 60099
- 2. Plant (Name and Address of Plant)
- 3. Plant Unit 1
- 4. Owner Certificam of Authoriaation (if required)
N/A 12/31/73. National Board Number for Unit See 1ist below for each 6
- 5. Commercial Service Date component or appurtenance
- 7. Componerts inspected Manufacturer Component or Manufacturer or Installer State or National Appurtenance or installer Serial No.
Province No.
Board No.
Class 1 Inspections RV Welds 610-1044-Bl.30 Babcock & Wilcox 5152 74870 N-184 RV Weld Bl.40 RV a
B3.90 RV Weld B3.100 RV Nozzle B4.ll f(V CRDN 34.12 Westinghouse N/A N/A N/A RV Instr.
610-1044 40z. B4.13 Babcock r wilcnv 5152 7an7n N-184 PRZ Heater delds B4.20 Westinchonnn 1001 U121653 6841 RV. Nuts 610-1044-B6.10 Babcock & Wilcox 5152 74870 N-184 RV Studs B6.30 RV Ligament 610-1044-B6.40 Babcock & Wilcox 5152 74870 N-184 l
RV Washers B6.50 l
RV Bolting B7.10 Westinghouse N/A N/A N/A PRZ Bolting B7.20 Westinghouse 1001 U121653 6841 S/G Manway Bolting B7.
0 Westinghouse N/A U121643 6827 Supplemental sheets in form of lists, sketches. or drawings may be used provided (1) size is 8% in. x 11 in..
Note:
(2) information in items 1 through 6 on this data report is included on each sheet, and ( 3) each sheet is numbered and the number of sheets is recorded at the top of this form.
10017 This form 6E00029) may be ot:tained kom the Order Cept., ASME, 345 E. 47th St.. New York. N.Y.
FORM NIS 1 OWNER 5' CATA CEPO37 FOR INSEGVICE INSFECTIONS
~
As required by the Provisions of the ASME Code Rules Page 2 of 4 Commonwealth Edison Co.
P.O. Box 767 Chicago, Illinois 60690
- 1. Owner (Name and Address of Owner)
Zion Generating Station, 101 Shiloh Blvd. Zion, Illinois 60099
- 2. Plant (Name and Address of Plant)
- 3. Plant Unit 1
- 4. Owner Certificate of Authorization (if required! N/A 12/31/73. National Board Number for Unit See list be1nw fnr nach 6
S, Commercial Service Date component or appurtenance
- 7. Components Inspected Manufacturer Component or Manufacturer or Installer State or National Appurtenance or Installer Serial No.
Province No.
Board No.
Pipe Welds B5.130_
Westinghouse N/A N/A N/A Pipe Bolting B7.50 M.W.
Kelloco N/A N/A N/A Pump Bolting B7.60 Westinchouse N/A N/A N/A Pipe Welds M.W.
- Kellogg, B9.11 Westinchouse N/A N/A N/A Pipe Welds B9.21 M.W. Kellogg N/A N/A N/A Pipe Welds B9.32 M.W. Kellogg N/A N/A N/A Pipe Welds B9.40 M.W. Kellogg N/A N/A N/A Integral Attach B10.1 3 Kellogg/ITT Grinnel N/A N/A N/A 4
RCP Flywheel BRGl.14 Westinghouse N/A N/A N/A System Press B15.90 N/A N/A N/A N/A Class 1 Repairs Valve IMOVRC8000B Velan N/A N/A M /n Seal Weld Valve IRC8074D Hunter N/A N/A N/A Sensing Line lLT 459.60. 61 Hunter N/A N/A N/A Sensing line 1DPT-467A Hunter N/A N/A N/A Install Line IRC-222/ components Hunter N/A N/A M /n Note: Supplemental sheets in form of lists, sketches, or drawings may be used provided (1) size is 8's in. x 11 in.,
(2) information in items I through 6 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.
1001'i This form IE0002m may be ctatained kom the Crder Dept.. ASVE, 325 E. 47th St., New York, N.Y.
FORM NIS 1 OWNER 5' CATA GEPORT FOR INSE3VICE INSPECTIONS As required by tlw Provisions of alw ASME Code Rules Page 3 of 4 Ccmmonwealth Edison Co.
P.O. Box 767 Chicago, Illinois 60690
- 1. Owner (Name and Address of owner)
Zion Generating Station, 101 Shiloh Blvd, Zion, Illinois 60099
- 2. Plant (Name and Address of Plant)
N/A
- 3. Plant Unit 1
- 4. Owner Certificate of Authorization (if requiredt f
See list below for each S. Commercial Service Date 12/31/7 3. National Board Number for Unit 6
component or appurtenance
- 7. Components inspected
\\
I Manufacturer Manufacturer or Installer State or National Component or or lastaller Serial No.
Province No.
Board No.
J Appurtenance Class 2 Inspections S/G Welds cl.10 Westinchouse 1061 U121643 6827 S/G Welds 1083 U121640 6821 C1.20 Westinghouse I
S/G Welds C1.30 Westinghouse 1061 U121643 6827 Excess Letdo en 857 U122991 708 Ilx Welds C1. LO Westinghouse Excess Letdo'en IIx Welds cl. 20 IIx Welds C1. LO Westinghouse N/A U125448 12C0ll j
Seal Water I
j Seal Water lix Welds C1..?0 i,
Mon Regen Hx N/A U122992 N/A Jelds C1.10 Westinghouse Ron Regen Hx Jelds C1.20 Pipe Welds C3.20 M.W.
Kelloqq N/A N/A N/A Pump Integra:
Nttach C3.30 Pacific Pumn 45609 N/A N/A Pipe Welds
~
C5.21 M.W. Kellogg N/A N/A N/A Pipe Welds C5.22 M.W.
Kelloqq N/A N/A N/A System Press N/A N/A N/A N/A c7_90 Note: Supplemental sheets in form of lists. sketches. or drawings may be used provided (1) size is 8% in. x 1 (2) information in items 1 through 6 on this data report is included on each sheet, and (3) each sheet is numbere and the number of sheetsis recorded at the top of this form.
10017 This form iE0002% may be ot)tained from the Crder Cept., ASVE, 325 E. 47th St., New York, N.Y.
FORM NIS-1 OWNERS' DATA REPORT FOR INSERVICE INSPECTIONS As required by the Provisions of the ASME Code Rules Page 4 of 4
- 1. Owner Commonwealth Edison Co.
P.O.
Box 767 Chicago, Illinois 60690 (Name and Address of Owner)
- 2. Plant _ Zion Generating Station, 101 Shiloh Blvd, Zion, Illinois 60099 (Name and Address of Plant)
- 3. Plant Unit 1
- 4. Owner Certificatt of Authorization (if required)
N/A 12/31/73. National Board Number for Unit See list below for each
- 5. Commercial Service Date 6
component or appurtenance
- 7. Components Inspected Manufacturer Component or Manufacturer e
or Installer State or National Appurtenance or Installer Serial No.
Province No.
Board No.
Class 2 nona i rc:
Valve Cl, C; (lC Accum)
Hunter N/A N/A N/A Sensing Line 1FT512.13.2:
Rosemount N/A N/A N/A Sensing Linc 1FE970.971 Hunter N/A N/A N/A Repair fitti ng 1PT615 Parker Hannifin N/A N/A N/A Replace 1FT-183 Taylor Sybron Corp.
N/A N/A N/A lLT517,18,lS 1LT527,28,25 Rosemount N/A N/A N/A 1LT537,38,39 lLT547,48,49 Rosemount N/A N/A N/A 1FT 512,513, lFT 522. 523 Rosemount N/A N/A N/A 1FT 532,533 IFT 542,543 Rosemount N/A N/A N/A 2" Manual V1v on IVCl14-2" Hunt or N/A N/A N/A Accum Site Glass (A.B.C.D.)
Hunter N/A N/A N/A Class 1 & 2 Supports Supports Fl.lO Kellogg/ITT Grinnell N/A N/A N/A Note: Su,*plemental sheets in form of lists, sketches, or drawings may be used provided (1) size is 8% in. x 11 in..
(2) information in items 1 through 6 on this data report is included on each sheet, and (3) each sheet is numbered and the number of sheets is recorded at the top of this form.
l This form (E00029) may be obtained from the Order Dept., ASME, 345 E. 47th St., New York, N.Y.
10017
v --
. FORM NIS 1 (bsck) 12/31/93 10/4/86 2/26/87
- 9. Inspection Interval from 12/31/8 3o
- 8. Examination Dates to
- 10. Abstract of Examinations. Include a list of examinations and a statement concerning status of work required for current interval.
Refer to Tab C
- 11. Abstract of Conditions Noted Refer to Tab B
- 12. Abstract of Corrective Measures Recommended and Taken Refer to Tab B We certify that the statements made in this report are correct and the examinations and corrective men-sures taken conform to the rules of the ASME Code,Section XI.
b/27/
19 87 Signed Edison Company By d -
Commonwealth Date Owner Certificate of Authorization No. (if applicable)
N/A Expiration Date N/A CERTIFICATE OF INSERVICE INSPECTION I, the undersigned, holding a valid commission issued by the National Board of Boiler and Pressure Vessel Inspectors and/or the State or Province of Illinois and employed by HSBI & I Co.
of c'rt ave inspected the components described in this Owners' Data Report during the period un_ rt f ord -
t
_Qct 4, 1986 to Feb 26, 1987 and state that to the best of my knowledge and belief, the Owner has performed examinations and taken corrective measures described in this Owners' Data Report in accordance with the requirements of the ASME Code,Section XI.
By signing this certificate neither the Inspector nor his employer makes any warranty, expressed or implied, concerning the examinations and corrective measures described in this Owners' Data Report. Furthermore, neither the Inspector nor his employer shall be liable in any manner for any personalinjury or property damage or a loss of any kind arising from or connected with this inspection.
Date 3
1 1
-tt Commissions Mfh @klO.
I t,
\\'6 \\ k Inspector's Signature National Board, State, Province and No.
I
COMONNEALTH EDISON COMPANY
~
ZION NUCLEAR POWER STATION UNIT 1 INSERVICE INSPECTION INTERVAL-2 PERIOO-1 OUTAGE-2 EXAMINATION
SUMMARY
INTRODUCTION An inservice examination of Class 1 and Class 2 and Class 3 components 4
.and piping was conducted at the Zion Statien Unit i from October 4, 1986 to February 26, 1987. The examinations were performed in accordance with an approved Examination Program Plan located under Tab C of the Final Report.
Also during this outage, eddy current examinations were conducted on 100%
of the accessible tubes in each of 4 steam generators in accordance wi+h Plant Technical specification 4.3.1 8.5.B.
This program included approximately 940 examinations from tube end to tube end in each The remainder were examined from the hot leg tube end to the generator.
neighborhood of the seventh tube support plate of the cold leg side.
Examination procedures were approved prior to the examinations, and certification documents relative to personnel, equipment and materials were reviewed and determined to be satisfactory.
Additionally, as noted in the Owners' Data Report, several repairs /-
replacements were accomplished during this outage.
i ID:6618r/51487:50-1
Inspections, citnessing and surveillance cf the examinations and related
~
activities were conducted by personnel from:
U. S. Nuclear Regulatory
)
Commission; Hartford Steam Boller Inspection and Insurance Company; and Zion Station Quality Assurance and Technical Staff.
T RESULTS Eddy current examintions resulted in 614 recordable indications. These included " squirrels" (large magnitude and unidentifed indications) and "0RI" (distorted roll transitions with possible indications) in addition to indications of 20% thru wall and greater.
Based on evaluation of the 614 Indications, 128 tubes were sleeved and 83 were plugged.
Other examinations based on the original Examination Program Plan, noted 69 recordable indication areas on the basis of procedure recording criteria which, generally are more critical than specified Section XI acceptance criteria. These indications consisted of:
(a) I volumetric, which was well within specified acceptance limits; (b) 6 Surface, 5 of which were eliminated during investigation and 1 (CHE-1-4800-38) which was repaired and will be monitored at the next refueling outage, and, (c) 62 visual, 92% of which were IWF components, were corrected or accepted as appropriate to maintain integrity of the individual components.
Subsequent implementation of the " Additional Examination" requirements of ID:6618r/51487:50-2
Section XI resulted in the examination cf 100% of the IMF components on the affected systems. These examinations noted approximately 257
~
additional indications, all of which were corrected or accepted as appropriate to maintain integrity of the individual components.
Excepting eddy current examinations, specific data relative to all of the indications noted above are located at Tab E, F and J of the Final Report.
Eddy current data is filed as a separate report to the Commission.
EXAMINATIONS Examinations were conducted to review as much of the specified surface / volume as reasonably practicable.
For a few items, exami-nations were limited by geometric, metallurgical or design access restrictions, as explained under LIMITATIONS.
Mostly, the limitations relate to examinations by ultrasonic methods and the effect is that a small volume of base matal, on the restricting side only, may be missed. The resulting coverage in such cases is that the sound beam passes through all of the specified volume of weld metal and adjacent heat affected zones that are within the volume specified for examination; through all of the base metal on the unrestricted side and; through all but a small mid-wall portion of base metal on the restricted side.
The occurrence and cause of various limitations have been noted.
l ID:6618r/51487:50-3 i
1
M LIMITATIONS
' Sche of the arrangements and details of the piping system and components ware designed and fabricated before the access and examination requirements of Section XI of the 1971 Code could be applied; consequently some examinations are limited or not practical due to.
geometric configuration and/or design accessibility. Generally these limitations' exist at all fitting-to-fitting joints such as elbow to tee, elbow to valve, reducer to valve, etc., where geometry precludes optimum ulltrasonic search unit contact or scanning distance from both sides of the weld. The limitations exist to a lesser degree at pipe to fitting assemblies, such as pipe to valve or pipe to flange. At these joints, search unit contact and scan distance is usually adequate to achieve a minimum acceptable converage from the pipe side.
4 In many cases scanning is accomplished from both sides of a weld in an attempt to cover as much of the specified volume from as many directions as practical, however, the extent of additional coverage from the
-restricted side cannot be specifically quantified.
k The resulting coverage is the maximum that is reasonably practical.
Specific limitations and restrictions for all examinations are indicated on the examiners' data sheets, under Tab-D of Outage Report.
ID:6618r/51487:50-4
~
O COMONWEALTH EDISON COMPANY ZION NUCLEAR PLANT UNIT #1 INSERVICE INSPECTION INTERVAL 2 PERIOD 1 OUTAGE 2 FINAL 1986 All items and areas listed below were examined as indicated, in accordance with the requirements of the plant Technical Specifications Section 4.3, which is based on the 1980 Edition,Section XI of the ASME Boller and Pressure Vessel Code up to and including Winter, 1981 Addenda.
Reference APPENDIX A for specific details of Reactor Vessel Remote examinations.
CWE Line Code Sketch Examination Examination Number item Reference item / Area Procedure Vol.
Surf.
Vis Notes Reactor Vessel 1.
B1.30 1-1100 Weld 1 154 2.
83.90 1-1100 Welds 12, 14, 16& 18 154 3.
86.40 1-1100 Threaded Ligaments 154 L1 thru L3; Ll4 thru 21 L31 thru L40 and L49 thru L54 4.
83.100 1-1100 IR's 12, 14, 16 and 18 8/V1 5.
B4.11 1-1100 Partial Penetration Welds VT-2 1
VT-2 1
6.
84.13 1-1100 7.
Bl.40 1-1300 Weld 6 47 70 2
8.
84.12 1-1300 Partial Penetration Nozzles VT-2 1
9.
B7.10 1-1300 Bolting, CSB-5 8/V1 10.
86.10 1-1400 RV Nuts for Hole Locations 70 1 thru 18 11.
B6.30 1-1400 RV Studs for Hole Location 70 8/V1 1 thru 18 12.
86.50 1-1400 RV Washers for Hole Locations 8/V1 1 thru 18
\\
\\
ID:6608r/42887:50-2
CWE Line Code Sketch Examination Examination Number item Reference Item / Area Procedure Vol.
Surf.
V3 Notes Pressurizer 13.
87.20 1-2100 Bolts 1 thru 5 8/V1 14.
84.20 1-2100 Partial Penetration Welds VT-2 1
Steam Generators 15.
87.30 1-3100 Bolting 1-81 thru l-832 VT-1 1
Piping 16.
85.130 1-4100 Held 1 206 11 17.
89.11 1-4100 Weld 14 206 11 18.
B9.21 1-4107 Weld 7 11 19.
89.32 1-4109 Weld 1 11 20.
89.32 1-4110 Weld 1 11 21.
89.40 1-4114 Weld 15 11 22.
89.40 1-4115 Weld 19 11 23.
85.130 1-4200 Held 1 206 11 24.
B9.21 1-4207 Weld 28 11 25.
B5.130 1-4300 Held 1 206 11 26.
d5.130 1-4400 Weld 1 206 11 27.
89.11 1-4506 Weld 12 206 11 28.
87.50 1-4700 Bolting, Items 5, 6, 7 8/V1 and 29 29.
B10.10 1-4800 Items 7, 28, 38 and 47 11 RC Pumps 30.
N/A 1-5100 Flywheels, Loops 1 & 4 11 31.
87.60 1-5100 Seal House Bolting 1-825 VT-1 1
thru l-836 and 4-825 thru 4-B36 System Leakage-General 31.
N/A 1-9100 Class 1, System Leakage VT-2 1
ID:6608r/42887:50-3
CLASS 2
~
STEAM GENERATORS CWE Line Code Sketch Examination Examination Number ites Reference item / Area Procedure Vol.
Surf.
VR Notes 32.
C1.10 2-1100 Weld 1-3 47 3
33.
C1.20 2-1100 Weld 2-8 47 4
34.
C1.30 2-1100 Weld 1-2 47 3
Excess Letdown H.X.
35.
C1.10 2-1110 Held 2 206 36.
C1.20 2-1110 Weld 1 206 Sealwater H.X.
37.
C1.10 2-1130 Weld 2 11 8/V1 38.
C1.20 2-1130 Weld 1 11 8/V1 Non Regen. H.X.
39.
C1.10 2-1140 Weld 2
'06 40.
C1.20 2-1140 Weld 1 206 Piping 41.
C5.21 2-2200 Weld I and 2 206 70 42.
C3.20 2-2700 Integral Supports, Items 70 24, 25, 28, 29, 30, 31, 33 34 and 35 43.
C5.22 2-2800 Weld 9 206 70 Centrifugal Charging Pump 44.
C3.30 2-3110 Support I-lWS 11 System Leakage-General VT-2 1
45.
N/A 2-9100 Class 2, System Leakage 10:6608r/42887:50-4
IWF SUPPORTS CWE Line Code Sketch Examination Examination Number Iten itsference Item / Area Procedure Vol.
Surf.
Vis Notes 46.
F1.10 F-1000 Items 2, 10, 18, 62, 85 thru 98, 8/V3 197, 227 thru 233, 257 thru 262, 264 thru 270, 368, 426, 446 thru 457, 460 thru 462, 490 thru 495 and 527 thru 536 47.
F1.10 F-2000 Items 22 thru 35, 100 thru 120, 8/V3 and 208 thru 210 48.
F1.10 F-3000 Items 1 thru 106, 127, 8/V3 128, 160, 178, 211, 226, 227, 254 thru 259, 343, 359 thru 364, 366, 367 and 427 I
i i
ID:6608r/42887:50-5 ut j
O!
-C ff0TES Conducted by utility personnel using appropriate procedures.
1.
2.
Surface examination relative to stud hole 11 thru stud hole 30.
Volumetric examination relative to stud hole 12 thru stud hole 29.
3.
Examined from 0 in. thru 12 ft.
4.
Examined from 0 in thru 16 ft.
.IO:6608r/42887:50-6
..