ML20214S383

From kanterella
Jump to navigation Jump to search
Forwards Insp Repts 50-313/87-06 & 50-368/87-06 on 870322-27 & Notices of Violation & Deviation
ML20214S383
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 06/01/1987
From: Gagliardo J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Campbell G
ARKANSAS POWER & LIGHT CO.
Shared Package
ML20214S386 List:
References
NUDOCS 8706090250
Download: ML20214S383 (2)


See also: IR 05000313/1987006

Text

_ __

' ' -

JUN I 1987

In Reply Refer To:

Dockets: 50-313/87-06

50-368/87-06

Arkansas Power & Light Company

ATTN: Mr. Gene Campbell

Vice President, Nuclear

Operations

P. O. Box 551

Little Rock, Arkansas 72203

Gentlemen:

This refers to the inspection conducted by Mr. H. D. Chaney of this office

during the period March 22-27, 1987, of activities authorized by NRC Operating

Licenses DPR-51 and NPF-6 for Arkansas Nuclear One, Units 1 and 2, and to the

discussion of our findings with Messrs. E. C. Ewing and S. M. Quennoz and other

members of your staff at the conclusion of the inspection.

Areas examined during the inspection included the solid radioactive waste

program and radioactive materials transportation activities. Within these

areas, the inspection consisted of selective examination of procedures and

representative records, interviews with personnel, and observations by the NRC

inspector. The inspection findings are documented in the enclosed inspection

report.

During this inspection, it was found that certain of your activities were in

violation of NRC requirements. Consequently, you are required to respond to

these violations, in writing, in accordance with the provisions of

Section 2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of

Federal Regulations. Your response should be based on the specifics contained

in the Notice of Violation enclosed with this letter.

Also during this inspection, it was found that certain of your activities

appeared to deviate from commitments made to the NRC. This reference to the

commitments is identified in the enclosed Notice of Deviation. You are

requested to respond to this deviation in writing. Your response should be

based on the specifics contained in the Notice of Deviation enclosed with this

letter.

The response directed by this letter and the accompanying Notice is not subject

to the clearance procedures of the Office of Management and Budget as required

by the Paperwork Reduction Act of 1980, PL 96-511.

RIV:FRP6 C:FRPSJ C:RPSB C:f , C:RPB

HDChaney/cg BMurray LAYandell DRF nter J Gagliardo

9 987 m i8, w 87

4 i87 4 87

0706090250 070601

\Y

gDR ADOCK 05000313 D

PDR

i .

Arkansas Power & Light Company -2-

Should you have any questions concerning this inspection, we will be pleased to

discuss them with you.

Sincerely,

ORIGINAL SIGNED BY:

J. E. Gagliardo, Chief

Reactor Projects Branch

Enclosures:

1. Appendix A - Notice of Violation

2. Appendix B - Notice of Deviation

3. Appendix C - NRC Inspection Report

50-313/87-06

50-368/87-06

cc w/ enclosure:

J. M. Levine, Director

Site Nuclear Operations

Arkansas Nuclear One

P. O. Box 608

Russellville, Arkansas 72801

Arkansas Radiation Control Program Director

bec to DMB (IE06)

bec distrib, by RIV:

  • RPB *RRI R. D. Martin, RA
  • RPSB *Section Chief (RPB/B) *D. Weiss, RM/ALF
  • RIV DRSP *RSB
  • MIS System *RSTS Operator * Project Inspector
  • R. Hall "H. D. Chaney *B. Murray
  • L. A. Yandell R. L. Bangart
  • w/766

i