Notice of Violation from Insp on 860708-0814
ML20214L340
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 08/29/1986
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20214L329 List:
References
50-213-86-20, NUDOCS 8609100096
Download: ML20214L340 (1)


Text

APPENDIX A NOTICE OF VIOLATION Connecticut Yankee Atomic Power Company Docket No. 50-213 Hartford, Connecticut 06101 License No. DPR-61 During the inspection conducted on July 8 - August 14, 1986 and in accoEdance with l the " General Statement of Policy and Procedures for NRC Enforcement Actions," 10 CFR Part 2, Appendix C (Enforcement Policy 1986), the following violations were identified:

1. Technical Specification 6.8 requires procedures to be established and main-tained for implementation of the Facility Fire Protection Program. Preventive Maintenance Procedure 9.5-120 requires that portable fire extinguishers be inspected monthly.

Contrary to the above, portable fire extinguishers in the switchgear room were not inspected in July, 1986.

This is a Severity Level V violation (Supplement 1).

2. Technical Specification 3.11, Containment, requires containment integrity to be maintained whenever the reactor coolant system (RCS) is above 300 psig and 200 degrees F.

Technical Specification 1.8, Containment. Integrity, requires that all penetra-tions required to be closed during accident conditions are either: a) capable of being closed by OPERABLE containment automatic isolation valves, or b) closed by manual valves, blind flanges, or deactivated automatic valves secured and locked in their closed positions.

Contrary to the above, on July 8, 1986, with the RCS~ greater than 300 psig and 200 degrees F, normally locked closed manual containment isolation valves SI-V-863A/B/C/D were opened to perform monthly surveillance tests.

This is a Severity Level IV violation (Supplement 1).

-Pursuant.to of 10 CFR 2.201, Connecticut Yankee Atomic Power Company is hereby re-quired to submit to this office, within thirty days of the letter which transmitted this Notice, a written statement or explanation in reply, including: (1) the cor-rective steps which have been taken and the results achieved; (2) corrective steps which will be taken to avoid further violations; and (3) the date when full com-pliance will be achieved. Where good cause is shown, consideration will be given to extending this response time.

8509100096 860829 PDR ADOCK 05000213 G PDR