ML20214J545

From kanterella
Jump to navigation Jump to search
Insp Rept 50-412/86-17 on 860602-06.No Violation Noted.Major Areas Inspected:Implementation of Program Plan & Procedures for Final in-depth Technical Audit & Licensee Actions Taken in Response to Concern from Previous Insp
ML20214J545
Person / Time
Site: Beaver Valley
Issue date: 08/05/1986
From: Imbro E, Wang H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To:
Shared Package
ML20214J540 List:
References
50-412-86-17, NUDOCS 8608150065
Download: ML20214J545 (13)


See also: IR 05000412/1986017

Text

!

.

.

U.S. NUCLEAR REGULATORY COMMISSION

.

OFFICE OF INSPECTION AND ENFORCEMENT

Division of Quality Assurance, Vendor, and Technical Training Center Programs

Report No:

50-412/86-17

Docket No:

50-412

Licensee:

Duquesne Light Company

Facility Name:

Beaver Valley, Unit 2

Inspection At:

Stone & Webster Engineering Corp., Boston, MA

,

,,

Inspection

Conducted:

June 2-6, 1986

Inspection Team Members:

Team Leader:

H. Wang, Inspection Specialist, IE

Mechanical

Systems:

T. DelGaizo, Consultant, WESTEC Services

Mechanical

Components:

B. Gupta, Consultant, Harstead Engineering

Electrical:

S. Athavale, Electrical Engineer, IE

Instrumentation

and Controls:

J. Kaucher, Consultant, WESTEC Services

Structural:

G. Harstead, Consultant, Harstead Engineering

E.V. Imbro, Chief, Licensing Section, IE

Prepared by:

C' } Wo > . k ..

f'

( j,

,,

,

Hai-Boh Wang

-

-

Team Leader, IE

Approved by:

.

8608150065 860013

^"

E

'k <' "

PDR

ADOCK 05000412

Eugene V. Imbro, Chief

O

PDR

Licensing Section

Quality Assurance Branch

  • Attended Fxit Meeting Only

.

F

.

.

Beaver Valley Unit 2

o

Technical Audit Implementation Inspection

June 2 to 6, 1986

1

'

1.

Background

In a meeting with the NRC on March 15, 1986, the licensee, Duquesne Light Company

(DLC), proposed a two phase program for the completion of the engineering assurance

The first phase

in-depth technical audits of the Beaver Valley 2 (BV-2) project.

provides for completion of four in-depth technical audits, three of which had been

The fourth and final audit will assess the adequacy of the

previously completed.

design process by evaluating the design of the Safety Injection System (SIS) and

the adjoining portion of the Recirculation Spray System (RSS), used to supply

water to the core to provide long term cooling, and associated interfaces. The

fourth audit will be performed by Stone & Webster Engineering Corporation (SWEC)

by qualified engineers who have not worked on the Beaver Valley Unit 2 Project.

The scope of this program was limited in recognition of the supplemental audits

previously performed by SWEC and DLC, particularly SWEC EA Audit #50 of the BV-2-

.'

'

hazards analysis program, SWEC EA Audit #44 covering the fuel pool cooling and

cleanup system plus portions of the fuel building, and DLC's design bases

endorsement program and resulting confirmation programs. The second phase pro-

vides for and evaluation and assessment of the results of the four audits in

order to form a conclusion as to the adequacy of the SWEC design process as imple-

mented for BV-2.

2.

Purpose

The purpose of this inspection was to evaluate implementation of the program

plan and procedures for the final in-depth technical audit. Specifically,

implementation of the audit was evaluated to ensure that the audit was being

conducted in accordance with the program plan and procedures and also that the

audit was being conducted in sufficient technical depth to draw meaningful

conclusions regarding the adequacy of the SWEC design process.

In addition,

action taken in responses to concerns from the previous NRC inspections were

evaluated.

3.

Personnel Contacted

A large number of DLC and SWEC personnel were contacted throughout the course

of the inspecticn. The following is a listing of the key personnel contacted:

Name

Organization

Position

!

R. Martin

DLC

Manager, Regulatory Af fairs

D. King

SWEC

Deputy Director of Engineering

W. Eifert

SWEC

Chief Engineer, Engineering Assurance

,

l

R. Twigg

SWEC

Audit Team Leader

.

C. Miczek

SWEC

Deputy Director of Engineering

-

1

l

'

'

.

4.

General Conclusions

The NRC team found that the In-Depth Audit was being conducted in accordance

with the approved program plan and implementing procedures. The team also

found that the audit was generally being conducted in sufficient technical

depth to draw meaningful conclusions regarding the adequacy of the SWEC design

process. Io certain technical specialty areas (e.g., mechanical component and

equipment supports) a large amount of the audit remained to be completed at

the time of the NRC visit. Although procedures and inspection review sheets

in those areas were found to be in sufficient detail and technical depth, the

NRC was unable to draw conclusions regarding the adequacy of audit implementation

due to the state of completion of the audit. The NRC will reassess those areas in

a later inspection.

On completion of the inspection, the NRC provided the SWEC audit team with

specific comments on a discipline Aar discipline basis. These ccaments are

included in Enclosure 1.

,.

.

5.

Previous Inspection Concerns

Daring the course of this inspection, the NRC team evaluated action taken in

response to NRC concerns raised during the previous inspection of the program

scope (Inspection Report 50-412/86-09 dated June 17, 1986). The NRC found

that the EA team had taken action to resolve the prior inspection concerns.

Details of this action are provided in Enclosure 2.

.

.

!

I

i

i

- - - -

. , - - - .

--

- . , . , - .

. ---,,,,


- - . , - , . , , - . - . - - , , , _ - - . , , . -

j

-

,

.

.

Enclosure 1

.

-

u.

BEAVER VALLEY UNIT 2 ENGINEERING ASSURANCE PROGRAM

Discipline Specific Conunents

.

!

I

l

l

. . . -

.

.

.

.

Enclosure 1

.

Discipline Specific Comments

Mechanical Systems / Power Discipline

1.

An audit of completed and partially completed review plans was conducted.

This effort included an independent check of fourteen design calculations,

the Recircuiation Spray System (RSS) overpressure protection analysis,

Westinghouse NSSS interface information, and three equipment

specifications.

Based on the information which was audited in the

'

mechanical systems area, the NRC concluded:

a.

The Mechanical System EA audit is being conducted in accordance with

the review plans.

b.

Action Item P05 (beta / gamma source term calculation) could have a

broad impact on environmental qualification of electrical components;

-

-

The NRC will monitor the resolution of this action item.

Mechanical Components / Engineering Mechanics

1.

The NRC team conducted an independent assessment of the review plans which

have been completed or are in progress. The results of the NRC assessment

indicate:

a.

Review Plan 1903-2, states that the calculation for the analysis and

design of the Recirculation Spray Cooler support / restraints is

satisfactory. However, the design calculation for the tapered

cantilever support plate was omitted. This finding resulted in the

issuance of a new action item which will be followed by the NRC.

b.

Review Plan 1904-2, pipe stress isometrics, was found acceptable by

the EA team. However, the isometrics do not contain the type of branch

connections used, as required by the review plan. An action item will

be issued to address this concern.

c.

No explanation was given for the lack of branch point stress

intensification factors (SIF). SIFs should have been considered as

part of pipe stress calculations. The licensee concurs with the

team's concern and a new action item will be issued.

Structural Discipline

1.

The In-Depth Audit being performed is being conducted in accordance with

the intent of the audit plans. However, some changes have been made to

make the audit more representative. For example, 6 N&Ds and 6 E&DCRs

were reviewed rather than the 10 specified in the original plan. This

was reasonable considering the time period of the audit, and the

additional audit items that had been added to the plan.

.

2.

Of the action items which have been produced, two are of particular

. _ .

-

.

- -

-

!

.-

,

.

interest because of the potential for broader impact. These items, listed

.

below, will be reassessed during the next NRC inspection.

a.

Action Item S10 indicates that the seismic model of cable trays and

supports has all masses lumped on the vertical members of the support

trapeze instead of at midspan of the cable trays and horizontal members

of the trapeze. This could lead to an under-estimate of vertical

seismic effects. The project response did not fully address the action

item.

b.

Action Item S14 indicates that a steel beam subject to torsional moments

was checked caly for St. Venant torsional shear stresses. Longitudinal

stresses in the flanges due to warping were neglected. This warping

effect should be investigated to ensure that the beam was ,r.roperly

designed.

Electrical Discipline

"

,

..

.

1.

The NRC team was informed that the review of all documents related to the

review plans, except for Review Plan #1908, had been completed. The NRC

team reviewed samples of calculations to verify that the audit was being

conducted in accordance with the approved audit plan. The NRC found that

the following inconsistencies were not addressed by the EA auditors:

a.

The equalizing battery voltage, during the recharging cycle, can be as

high as 2.4 volts / cell. This exceeds the FSAR commitment of 2.33

volts / cell (maximum). The team found no evidence of how the voltage

will be limited, or an evaluation of the effects of the higher

voltage on equipment qualification and operation.

b.

Several calculations were found to have unverified assumptions. The

NRC team was informed that programs (" Confirmation Program to Key

Documents," 2BVM-117 and " Engineering Confirmation Update

Program", 2BVM-122) are in progress which will verify all such

assumptions prior to fuel load. The NRC will monitor the

rezolution of these unverified assumptions when the programs are

completed.

2.

The NRC team reviewed all action items which had been produced as of

June 3, 1986. The following items are significant and the NRC will

i

continue to monitor the resolution of these items.

a.

Action Item E03 indicates that certain class 1E devices located

below flood level in the containment may not be qualified for

submergence.

l

b.

Action Item E04 indicates that cables furnished prior to May 1984

l

may not meet the fire testing qualification requirements described

j

in FSAR section 8.3.3.

i

i

c.

Action Item E09 indicates that the separation requirements committed

'

to in FSAR section 8.3.1 for redundant electrical penetrations may

have been violated.

,

l

l

d.

Action Item E16 indicates that failure of non-Category 1 equipment

could damage Category 1 equipment in the same area.

. _ . -

--

.

t

9

e.

Action Item E19 indicates that the lack of separation may disable

redundant buses by a common-mode failure due to a connection between

the redundant buses.

Instrumentation and Controls Discipline

1.

The NRC's review of the controls section of the BV-2 Engineering audit,

included an independent review of selected specifications, calculations,

E&DCRs and diagrams. Additionally, a review of the action item list of

June 3, 1986, including the items resolved to that point, was conducted.

During the review of Calculations SP-2RSS-10 and RSS*10-0-C, a question

regarding the setpoint of the reset for the recirculation spray pump

recirculation valves was identified. With the present setpoint as cal-

culated, it appears that in certain plant configurations the recirculation

valves could continuously cycle. The NRC will review the resolution to

this item during the next inspection.

-

.

2.

Based on this review the NRC team concluded that the audit was conducted in

accordance with the approved audit plans.

t

\\

-

l

l

l

i

!

, - _ - - . , _ _ - _ . . . . _

. - . - - , _

-

. . - - -

.

.

.

<

.

.*

.

Enclosure 2

-

,. ,

STATUS OF CONCERNS FROM NRC INSPECTION 50-412/86-09

Dated June 17, 1986

l

l

.

t

,

.

.

Enclosure 2

,

STATUS OF NRC INSPECTION ITEMS FROM

INSPECTION 50-412/86-09

OBS.NO.

SUMMARY OF CONCERN OR QUESTION

STATUS

COMMENT

MECHANICAL SYSTEMS / POWER

1.1

Design of the RSS sump screen

Closed

FSAR commitments were

vs. FSAR commitments should be

verified.

verified.

1.2

Single-failure review should

Closed

Review of single-

include measures taken to prevent

failure criteria con-

freezing of the RWST supply line

firmed suitable measures

to the SI pumps.

through the existence-

%.

of a redundant heat-

trace system.

1.3

Verification of the basis for

Closed

Review of radiation

radiation levels in the RSS

calculations resulted

cubicle should be performed.

in initiation of Action

Items P05 and P06.

ELECTRICAL POWER

2.1

Review of derating factors for

Closed

As part of the review of

cables should be added to the

safety-related cable

scope of the EA audit.

ampacity calculations,

the application of

appropriate derating

factors were checked.

2.2

Review of power supplies to NSSS

Closed

Power supply panels and

vendor supplied SIS and ESFAS

distribution boards were

equipment, including isolation of

reviewed as part of the

non-Class IE from Class 1E

review plan.

inverters should be performed.

Calculations for the voltage

between the distribution

panels and the SIS and

ESFAS equipment had been

reviewed.

2.3

Review of electrical protective

Closed

Several components

devices, including components

located below the post-

located below post-accident flood

accident flood levels

levels should be performed.

were reviewed relative

to electrical system

protective devices.-

2.4

A review of equipment specifi-

Closed

NSSS vendor supplied

cations for selected NSSS vendor

equipment have been

supplied equipment should be

reviewed as part of the

performed.

review plan.

..

,

.

OBS.NO.

SUMMARY OF CONCERN OR QUESTION

STATUS

COMMENT

2.5

Review of technical details

Closed

The electrical instal-

of the electrical installation

lation specification was

specification should be included

reviewed by the EA team

in the scope of the EA audit.

during the site visit,

including a walkdown of

selected equipment.

INSTRUMENTATION & CONTROLS

3.1

A review of NSSS vendor require-

Closed

NSSS vendor supplied

ments for SIS should be performed.

elementary, wiring, and

logic diagrams for the

SIS were reviewed.

,

-

.

.

3.2

A review of RWST level

Closed

Drawings and

instrumentation should

specifications

be performed.

for RWST

level instruments

2QSS*LSL104A-D were

reviewed.

3.3

A review of specifications

Closed

A specification for

for electronic pressure

electronic pressure

transmitters should be

transmitters was

included as part of review plan

reviewed. This in-

1906-2.

cluded instrument

data sheets for

Rosemount model

1153 B and D.

3.4

NSSS Vendor supplied setpoints

Closed

Westinghouse document

should be reviewed for

" Precautions, Limitations

interface requirements.

and Setpoints" was

reviewed for consistency

with BV2 requirements.

3.5

A review of the I&C equipment

Closed

The EA team reviewed the

instu11ation specification should

I&C equipoent

be included in the scope of the

installation specifi-

audit.

cation (2BVS-977)

,

during the site visit,

l

including a physical

walkdown of selected

equipment.

.

.

-

.

.

.

.

.

OBS.NO.

SUMMARY OF CONCERN OR QUESTION

STATUS

COMMENTS

3.6

The vendor document review should Closed

Calibration data,

include MOV torque switch settings

including torque switch

and calibration data.

settings, were reviewed

for MOVs purchased

under specification

2GVS-082A.

MECHANICAL COMPONENTS

4.1

Review of a Class 1 stress

Closed

The scope of the EA

analysis package should

audit was expanded to

be performed.

include the review of'i

.,

,

Class 1 stress analysis

package.

4.2

Review of the method of

Closed

Review Plan 1901 was

selecting thermal transients

modified to include

in Class 1 stress analysis for

a review of the

compliance with FSAR commitments

method of selecting

should be included in the audit.

thermal transients in

Class 1 stress analysis

to ensure compliance

with FSAR commitments.

4.3

Stress Design Group interface

Open

Verification of the

with the Power Engineering

interface between the

discipline should be evaluated.

Stress Design Group and

Power Engineering

concerning stress

intensification factors

has not been completed.

This item will be

followed during the

next NRC inspection.

4.4

Supports welded to Class 1

Closed

The EA team has

piping should be analyzed.

determined that there

are no welded supports

to Class 1 piping.

4.5

A review should be performed

Closed

The audit now includes

for each type of pipe support.

an analysis of each

type of pipe support

used on the BV2

proj ect.

-

.

.

OBS.NO.

SUMMARY OF CONCERN OR QUESTION

STATUS

COMMENTS

.

4.6

The interface between the Pipe

Closed

The scope of Review

Support Group and Pipe Stress

Plan 1909 haa been

Group should be evaluated.

expanded to include an

evaluation of the

interface between the

Pipe Support Group

and the Pipe Stress

Group.

4.7

The considerations of vendor

Closed

The vendor supplied

seismic qualification information

seinmic qualification

for the RSS pump should be

information for the

evaluated.

RSS pump was evaluated

and found to be

satisfactory.

,

'

4.8

RSS cooler support design should

Open

Review of the analysis

be analyzed.

of the cooler support

design has not been

completed.

It will be

reviewed by the NRC

team during the next

inspection.

CIVIL / STRUCTURAL

5.1

The effect of nonsafety-related

Closed

The effect of non-

equipment structural failure on

safety related doors

adjacent safety-related equipment

in the hazards program

should be considered in the EA

was reviewed as part of

review.

the audit.

5.2

The design of a two-way rein-

Closed

A calculation for a

forced concrete slab should

concrete slab was

be analyzed,

added to the

j

calculations being

reviewed.

[

5.3

Effect of RSS cooler support

Closed

An analysis of the

reactions on the structural

embedment plate in the

design of walls or slabs should

wall supporting the

be reviewed.

RSS cooler was

performed and found

to be adequate.

i

5.4

Effect of RSS pump and motor

Closed

RSS pump and motor

support reactions on slab

support reaction was

design should be analyzed.

analyzed for its

,

effects on the design

of the supporting slab.

The analysis is

satisfactory.

,

1

._-

,

.,

i

%'

b_ution:

DCS y

YUK

Local PDR

QAB Reading

DQAVT Reading

JMTaylor, IE

BKGrimes, IE

,

HJMiller, IE

GTAnkrum, IE

EVImbro, IE

HBWang, IE

PSTam, NRR

DGMedonald, NRR

LSRubenstein, NRR

LETripp, RI

PKEapen, RI

f

ON

g

f

QAB:DQAVT:IE

QAB:DQAVT:IE

C:QA

AVT:IE

AVT:IE

.

HBWang

EVImbro

GT

UMiller

08/pf/86

08//f/86

08

6

08//l/86

D:DQ

E

BKGr ' es

08/

/86

'

l

!

r

.

.-

-.

-

. . . , , . , , .

--

,

. - - ,

. ~ - .

- . - - - -

- - , , , - . , ..

- , -

. , .

, . , - - - , - - -