|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARML20217P3791999-10-21021 October 1999 Forwards NRC Form 396 & NRC Form 398 for Renewal of Licenses SOP-20607-1 & SOP-20610-1.Without Encls ML20217N2521999-10-20020 October 1999 Provides Supplemental Info Re 990405 Containment Insp Program Requests for Relief RR-L-1 & RR-L-2,in Response to 991013 Telcon with NRC ML20217K7541999-10-15015 October 1999 Forwards Rev 1 to Unit 1,Cycle 9 & Unit 2 Cycle 7 Colrs,Iaw Requirements of TS 5.6.5.Figure 5, Axial Flux Difference Limits as Function of Percent of Rated Thermal Power for RAOC, Was Revised for Both Units ML20217G6751999-10-13013 October 1999 Requests Withholding of Proprietary Info Contained in Application for Amend to OLs to Implement Relaxations Allowed by WCAP-14333-P-A,rev 1 ML20217G1071999-10-0707 October 1999 Informs That on 990930,NRC Staff Completed mid-cycle PPR of Vogtle & Did Not Identify Any Areas in Which Performance Warranted More than Core Insp Program.Nrc Plans to Conduct Core Insps at Facility Over Next Six Months ML20216J9041999-10-0101 October 1999 Forwards Response to RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves ML20216J9161999-10-0101 October 1999 Forwards Response to NRC 990723 RAI Re GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20217B0141999-10-0101 October 1999 Forwards Insp Repts 50-424/99-06 & 50-425/99-06 on 990725- 0904 at Vogtle Units 1 & 2 Reactor Facilities.Determined That One Violation Occurred & Being Treated as non-cited Violation ML20212E8751999-09-20020 September 1999 Forwards Response to NRC GL 99-02, Lab Testing of Nuclear Grade Activated Charcoal. Description of Methods Used to Comply with Std Along with Most Recent Test Results Encl ML20212E7481999-09-20020 September 1999 Requests Approval Per 10CFR50.55a to Use Alternative Method for Determining Qualified Life of Certain BOP Diaphragm Valves than That Specified in Code Case N-31.Proposed Alternative,Encl ML20212C2191999-09-16016 September 1999 Forwards NRC Form 536, Operator Licensing Exam Data, Which Is Current Need for NRC Operator Licensing Exams for Years 2000 Through 2003 of Plant Vogtle,Per Administrative Ltr 99-03 ML20211Q4801999-09-0101 September 1999 Informs That on 990812-13,Region II Hosted Training Managers Conference on Recent Changes to Operator Licensing Program. List of Attendees,Copy of Slide Presentations & List of Questions Received from Participants Encl ML20211J5291999-08-30030 August 1999 Forwards Snoc Copyright Notice Dtd 990825,re Production of Engineering Drawings Ref in VEGP UFSAR ML20211J5251999-08-30030 August 1999 Forwards Response to NRC 990727 RAI Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20211J7381999-08-27027 August 1999 Informs That Licensee Vessel Data Is Different than NRC Database Based on Listed Info,Per 990722 Request to Review Rvid ML20211E9251999-08-23023 August 1999 Forwards fitness-for-duty Performance Data for Jan-June 1999,as Required by 10CFR26.71(d).Data Reflected in Rept Covers Employees at Vogtle Electric Generating Plant ML20210V0881999-08-16016 August 1999 Forwards Insp Repts 50-424/99-05 & 50-425/99-05 on 990620- 0724.No Violations Noted.Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maintenance Practices ML20210Q4611999-08-0505 August 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 991006 for Vogtle.Requests Info Re Individuals Who Will Take Exam. Sample Registration Ltr Encl ML20210L2181999-08-0202 August 1999 Forwards NRC Form 396 & Form 398 for Renewal of Listed Licenses,Iaw 10CFR55.57.Without Encl ML20210N1191999-08-0202 August 1999 Discusses 990727 Telcon Between Rs Baldwin & R Brown Re Administration of Licensing Exam at Facility During Wk of 991213 ML20210G3351999-07-27027 July 1999 Forwards Second Request for Addl Info Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20210E0121999-07-23023 July 1999 Forwards Second Request for Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20210D9341999-07-22022 July 1999 Discusses Closure of TACs MA0581 & MA0582,response to Requests for Info in GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity ML20210C8011999-07-21021 July 1999 Provides Response to NRC AL 99-02,which Requests That Addressees Submit Info Pertaining to Estimates of Number of Licensing Actions That Will Be Submitted for NRC Review for Upcoming Fy 2000 & 2001 ML20210E0431999-07-15015 July 1999 Forwards Insp Repts 50-424/99-04 & 50-425/99-04 on 990502- 0619.Two Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20209H3881999-07-14014 July 1999 Forwards Revs 1 & 2 to ISI Program Second 10-Year Interval Vogtle Electric Generating Plant Unit 1 & 2 ML20209C4041999-07-0101 July 1999 Forwards Rev 29 to VEGP Units 1 & 2 Emergency Plan.Rev 29 Incorporates Design Change Associated with Consolidation of Er Facilities Computer & Protues Computer.Justifications for Changes & Insertion Instructions Are Encl ML20196H8081999-06-28028 June 1999 Discusses 990528 Meeting Re Results of Periodic PPR for Period of Feb 1997 to Jan 1999.List of Attendees Encl ML20212J2521999-06-21021 June 1999 Responds to NRC RAI Re Yr 2000 Readiness at Nuclear Power Plants.Gl 98-01 Requested Response on Status of Facility Y2K Readiness by 990701 ML20196F9171999-06-21021 June 1999 Forwards Owner Rept for ISI for Vogtle Electric Generating Plant,Unit 1 Eighth Maint/Refueling Outage. Separate Submittal Will Not Be Made to NRC on SG Tubes Inspected During Subj Outage ML20195F8031999-06-11011 June 1999 Forwards Changes to VEGP Unit 1 Emergency Response Data Sys (ERDS) Data Point Library.Changes Were Completed on 990308 While Unit 1 Was SD for Refueling Outage ML20207E7421999-06-0303 June 1999 Refers to from NRC Which Issued Personnel Assignment Ltr to Inform of Lm Padovan Assignment as Project Manager for Farley Npp.Reissues Ltr with Effective Date Corrected to 990525 ML20207F6201999-06-0202 June 1999 Sixth Partial Response to FOIA Request for Documents.Records in App J Encl & Will Be Available in Pdr.App K Records Withheld in Part (Ref FOIA Exemptions 7) & App L Records Completely Withheld (Ref FOIA Exemption 7) ML20207D9861999-05-28028 May 1999 Informs That,Effective 990325,LM Padovan Was Assigned as Project Manager for Plant,Units 1 & 2 ML20207D2701999-05-19019 May 1999 Forwards Insp Repts 50-424/99-03 & 50-425/99-03 on 990321- 0501.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206M5141999-05-11011 May 1999 Informs That NRC Ofc of Nuclear Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Rl Emch Section Chief for Vogtle. Reorganization Chart Encl ML20206U4061999-05-11011 May 1999 Confirms Telcon with J Bailey Re Mgt Meeting Scheduled for 990528 to Discuss Results of Periodic Plant Performance Review for Plan Nuclear Facility Fo Period of Feb 1997 - Jan 1999 05000424/LER-1998-006, Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Exi1999-05-10010 May 1999 Forwards LER 98-006-03 Re Motor Control Ctr Breaker Buckets Not Being Seismically Qualified.Rev Is Submitted to Document Results of Seismic Testing That Demonstrated That No Condition Outside Design Basis of TS Requirements Existed ML20206D6411999-04-29029 April 1999 Forwards Vogtle Electric Generating Plant Radiological Environ Operating Rept for 1998 & Vogtle Electric Generating Plant Units 1 & 2 1998 Annual Rept Annual Radioactive Effluent Release Rept ML20206D5881999-04-29029 April 1999 Forwards Rept Which Summarizes Effects of Changes & Errors in ECCS Evaluation Models on PCT for 1998,per Requirements of 10CFR50.46(a)(3)(ii).Rept Results Will Be Incorporated Into Next FSAR Update ML20206D6951999-04-28028 April 1999 Provides Update of Plans for VEGP MOV Periodic Verification Program Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs ML20206C2241999-04-21021 April 1999 Forwards Revised Monthly Operating Repts for Mar 1999 for Vogtle Electric Generating Plant,Units 1 & 2.Page E2-2 Was Iandvertently Omitted from Previously Submitted Rept on 990413 ML20206A6371999-04-21021 April 1999 Forwards SE Authorizing Licensee Re Rev 9 to First 10-yr ISI Interval Program Plan & Associated Requests for Relief (RR) 65 from ASME Boiler & Pressure Vessel Code ML20205Q3351999-04-15015 April 1999 Forwards Insp Repts 50-424/99-02 & 50-425/99-02 on 990214-0320.Three Violations Identified & Being Treated as Non-Cited Violations ML20205T2351999-04-0909 April 1999 Informs That on 990317,B Brown & Ho Christensen Confirmed Initial Operator Licensing Exam Scheduled for Y2K.Initial Exam Date Scheduled for Wk of 991213 for Approx 10 Candidates ML20205K7501999-04-0505 April 1999 Informs That Effective 990329,NRC Project Mgt Responsibility for Plant Has Been Transferred from Dh Jaffe to R Assa ML20209A3741999-04-0505 April 1999 Submits Several Requests for Relief for Plant from Code Requirements Pursuant to 10CFR50.55a(a)(3) & (g)(5)(iii).NRC Is Respectfully Requested to Approve Requests Prior to Jan 1,2000 ML20205H3481999-03-31031 March 1999 Forwards Georgia Power Co,Oglethorpe Power Corp,Municipal Electric Authority of Ga & City of Dalton,Ga Status of Decommissioning Funding for Each Reactor or Part of Reactor Owned for OLs NPF-68 & NPF-81 ML20205F9091999-03-29029 March 1999 Submits Rept of Number of SG Tubes Plugged During Plant Eighth Maintenance/Refueling Outage (1R8).Inservice Insps Were Completed on SGs 1 & 4 on 990315.No Tubes Were Plugged ML20205G0761999-03-26026 March 1999 Provides Results of Individual Monitoring for 1998.Encl Media Contains All Info Required by Form NRC 5.Without Encl 1999-09-20
[Table view] Category:NRC TO PUBLIC ENTITY/CITIZEN/ORGANIZATION/MEDIA
MONTHYEARML20237G0421987-08-11011 August 1987 Responds to 870707 Appeal Re Denial of FOIA Request for Documents.Appeal Granted.Portions of Six Documents Re Insp Rept 50-424/86-91 Concerning Drug Abuse at Facility Previously Withheld Encl ML20235K1541987-07-14014 July 1987 Responds to Appeal of Denial of FOIA Request for Documents Re 861113 Insp Rept 50-424/87-90 Concerning Drug Abuse at Plant.Previously Withheld Info Will Continue to Be Withheld (Ref FOIA Exemption 6) ML20235D3791987-07-0101 July 1987 Final Response to FOIA Request for Documents Re Plant Fitness for Duty Program.Forwards App F & G Documents. Documents Also Available in Pdr.App G Documents Partially Withheld (Ref FOIA Exemption 6) ML20237D2881987-06-15015 June 1987 Responds to Request for Info Re Proposed Rule Changes Dealing W/Emergency Planning for Nuclear Power Plants.Rule Provides Criteria by Which NRC Can Evaluate Whether Util Emergency Plan Adequate in Absence of Local Participation ML20214B6881987-05-14014 May 1987 Partial Response to FOIA Request for Documents Re Plant anti-drug & Alcohol Program.Encl App C Documents Also Available in Pdr.App D & E Documents Partially & Completely Withheld (Ref FOIA Exemption 6),respectively ML20213G8501987-05-12012 May 1987 Responds to Expressing Concerns Re Licensing of Plant Prior to Completion of Required Safety Tests.Nrc Authorized Schedular Relief from Certain Tests Which Are Not Necessary to Ensure Safety ML20212P1601987-03-11011 March 1987 Partial Response to FOIA Request Re Insp Repts.Forwards App B Documents.App a & B Documents Available in PDR ML20207P7351987-01-14014 January 1987 Ack Receipt of Notifying NRC That Recipient Will Represent Georgians Against Nuclear Energy in Oral Argument Scheduled for 870121.Served on 870115 ML20214F1711986-11-20020 November 1986 Responds to FOIA Request for Documents Re Insp Repts 50-424/85-04 & 50-425/85-04.Forwards Portions of App a & B Documents.Documents Also Available in Pdr.Portions of App a & B Documents Withheld (Ref FOIA Exemptions 6 & 7) ML20197C4531986-10-23023 October 1986 Responds to Appeal of Denial of FOIA Request for Documents Re Allegations.Seven of 11 App D Items Forwarded & Available in Pdr.Portions of Items 4-7 Withheld (Ref FOIA Exemption 7) ML20210T0621986-10-0303 October 1986 Forwards Response to Applicant Motion to Strike Notice of Appeal of Campaign for Prosperous Georgia ML20204G5971986-08-0101 August 1986 Responds to to DOE Re Startup of Plant.Specific Info Available at Lpdr.Unit 1 Fuel Load Estimated for 861215.Following Preoperational Testing,Unit Ready for Commercial Operation About 6 Months After Loading Fuel ML20203C2951986-07-11011 July 1986 Further Response to FOIA Request for Documents Re NRC Investigation Into Complaints of Register,L Price & JB Register Concerning Improper Practices at Facilities.App D Documents Withheld (Ref FOIA Exemption 7) ML20198E2181986-05-22022 May 1986 Informs That Wf Lawless & Hm Deutsch Affiliation W/Georgians Against Nuclear Energy Must Be Established by 860605 Before Filing of Proposed Findings Re Contentions 7 & 10.5,in Response to 860314 Hearing,Acceptable.Served on 860523 ML20197E2381986-05-0202 May 1986 Further Response to FOIA Request for Records on Register, L Price & JB Register Complaints Re Alleged Illegal & Improper Procedures.Portions of App B Records & All App C Records Withheld (Ref FOIA Exemptions 6 & 7,respectively) ML20210K4521986-03-28028 March 1986 Partial Response to FOIA Request for Documents Re NRC Investigation Into Register,L Price & J Register Allegations of Illegal & Improper Procedures at Facilities. Documents on App a in PDR ML20141G4951986-03-25025 March 1986 Further Response to FOIA Request for Documents Re NRC Investigation of Allegations of Intimidation & Harassment of Inspectors by Pullman Power Products Employees.Forwards App D Documents.Documents Also Available in PDR ML20138R0621985-12-26026 December 1985 Returns 851220 Transmittal of 11 Page Unsigned Document Entitled, Analysis of ASLB 851212 Memorandum & Order.... Document Does Not Conform to NRC Rules of Practice & Is of No Use in Case.W/O Encl.Served on 851227 ML20134A5251985-10-28028 October 1985 Final Response to FOIA Request for Documents on 850726 Briefing by Util Re Readiness Review Program,Including Transcript of Briefing.App D Documents Withheld (Ref FOIA Exemption 5).Action on Request Complete ML20136D4051985-10-11011 October 1985 Final Response to FOIA Request for Five Categories of Documents Re Pollution Control Bonds for Plants.Forwards App E Documents.Documents Listed in App F & App E Available in PDR IA-85-599, Partial Response to FOIA Request for Documents Re Util 850726 Briefing on Readiness Review Program,Including Transcript.Documents Listed in Apps a & B Available in Pdr. App C Documents Withheld (Ref FOIA Exemption 5)1985-10-0303 October 1985 Partial Response to FOIA Request for Documents Re Util 850726 Briefing on Readiness Review Program,Including Transcript.Documents Listed in Apps a & B Available in Pdr. App C Documents Withheld (Ref FOIA Exemption 5) ML20138C1041985-10-0303 October 1985 Partial Response to FOIA Request for Documents Re Util 850726 Briefing on Readiness Review Program,Including Transcript.Documents Listed in Apps a & B Available in Pdr. App C Documents Withheld (Ref FOIA Exemption 5) ML20133Q1851985-07-11011 July 1985 Further Response to FOIA Request for Documents Re Charleston Earthquake of 1886 & Seismic Design for Vogtle. Documents 1 & 2 Available in Pdr.Document 3 Encl IA-84-430, Further Response to FOIA Request for Documents Re Charleston Earthquake of 1886 & Seismic Design for Vogtle. Documents 1 & 2 Available in Pdr.Document 3 Encl1985-07-11011 July 1985 Further Response to FOIA Request for Documents Re Charleston Earthquake of 1886 & Seismic Design for Vogtle. Documents 1 & 2 Available in Pdr.Document 3 Encl ML20210K4901985-06-20020 June 1985 Forwards for Review,Results of 850522 Interview Concerning Allegations RII-85-A-0016.Concerns May Be Referred Back to Util & Subj to NRC Audit.Info Will Be Forwarded to Technical Staff for Review.W/O Encl.Related Info Encl ML20210K4821985-06-20020 June 1985 Forwards for Review,Results of 850522 Interview Concerning Allegations RII-85-A-0016.Concerns May Be Referred Back to Util & May Be Subj to NRC Audit.Info Will Be Forwarded to Technical Staff for Review.W/O Encl ML20210K4701985-06-20020 June 1985 Forwards for Review,Results of 850522 Interview Concerning Allegations RII-85-A-0016.Concerns May Be Referred Back to Util & May Be Subj to NRC Audit.Info Will Be Forwarded to Technical Staff for Review.W/O Encl ML20126D8001985-02-28028 February 1985 Further Response to FOIA Request for Six Categories of Documents Re Charleston Earthquake of 1886 & Seismic Design for Vogtle Nuclear Power Plant.App B Documents Forwarded & Available in Pdr.Review Continuing ML20197E2961985-02-26026 February 1985 Partially Withheld Ltr Re Abuse of Drug Screening Program & Const Deficiencies Discussed During Feb 1985 Telcons.Actions to Develop Facts & Circumstances of Encl Identified Concerns Initiated ML20197E2661985-02-26026 February 1985 Partially Withheld Ltr Re Abuse of Drug Screening Program & Const Deficiencies Discussed During Jan 1985 Telcons.Actions to Develop Facts & Circumstances of Encl Identified Concerns Initiated ML20125E3381985-02-19019 February 1985 Third Partial Response to FOIA Request for Six Categories of Documents Re Charleston,Sc Earthquake of 1886 & Seismic Design for Plant.Forwards App a Documents ML20214F5541984-11-0808 November 1984 Partially Withheld Memo Re QC Concerns at Plant.Notification If Concerns Not Completely or Accurately Reflected in Encl Requested.Complaint Re Discrimination Should Be Filed W/Dol. Related Info Encl ML20214F3911984-06-12012 June 1984 Partially Withheld Ltr Confirming Understanding of Concerns Re Deficiencies Concerning Case RII-84-A-0094.Notification If Concerns Not Completely or Accurately Reflected Requested.Records of 860531,0601 & 0608 Telcons Encl 1987-08-11
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARML20217G1071999-10-0707 October 1999 Informs That on 990930,NRC Staff Completed mid-cycle PPR of Vogtle & Did Not Identify Any Areas in Which Performance Warranted More than Core Insp Program.Nrc Plans to Conduct Core Insps at Facility Over Next Six Months ML20217B0141999-10-0101 October 1999 Forwards Insp Repts 50-424/99-06 & 50-425/99-06 on 990725- 0904 at Vogtle Units 1 & 2 Reactor Facilities.Determined That One Violation Occurred & Being Treated as non-cited Violation ML20211Q4801999-09-0101 September 1999 Informs That on 990812-13,Region II Hosted Training Managers Conference on Recent Changes to Operator Licensing Program. List of Attendees,Copy of Slide Presentations & List of Questions Received from Participants Encl ML20210V0881999-08-16016 August 1999 Forwards Insp Repts 50-424/99-05 & 50-425/99-05 on 990620- 0724.No Violations Noted.Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maintenance Practices ML20210Q4611999-08-0505 August 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 991006 for Vogtle.Requests Info Re Individuals Who Will Take Exam. Sample Registration Ltr Encl ML20210N1191999-08-0202 August 1999 Discusses 990727 Telcon Between Rs Baldwin & R Brown Re Administration of Licensing Exam at Facility During Wk of 991213 ML20210G3351999-07-27027 July 1999 Forwards Second Request for Addl Info Re GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design Basis Accident Conditions ML20210E0121999-07-23023 July 1999 Forwards Second Request for Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20210D9341999-07-22022 July 1999 Discusses Closure of TACs MA0581 & MA0582,response to Requests for Info in GL 92-01,rev 1,suppl 1, Reactor Vessel Structural Integrity ML20210E0431999-07-15015 July 1999 Forwards Insp Repts 50-424/99-04 & 50-425/99-04 on 990502- 0619.Two Violations of NRC Requirements Identified & Being Treated as non-cited Violations Consistent with App C of Enforcement Policy ML20196H8081999-06-28028 June 1999 Discusses 990528 Meeting Re Results of Periodic PPR for Period of Feb 1997 to Jan 1999.List of Attendees Encl ML20207E7421999-06-0303 June 1999 Refers to from NRC Which Issued Personnel Assignment Ltr to Inform of Lm Padovan Assignment as Project Manager for Farley Npp.Reissues Ltr with Effective Date Corrected to 990525 ML20207F6201999-06-0202 June 1999 Sixth Partial Response to FOIA Request for Documents.Records in App J Encl & Will Be Available in Pdr.App K Records Withheld in Part (Ref FOIA Exemptions 7) & App L Records Completely Withheld (Ref FOIA Exemption 7) ML20207D9861999-05-28028 May 1999 Informs That,Effective 990325,LM Padovan Was Assigned as Project Manager for Plant,Units 1 & 2 ML20207D2701999-05-19019 May 1999 Forwards Insp Repts 50-424/99-03 & 50-425/99-03 on 990321- 0501.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206M5141999-05-11011 May 1999 Informs That NRC Ofc of Nuclear Regulation Reorganized Effective 990328.As Part of Reorganization,Div of Licensing Project Mgt Created.Rl Emch Section Chief for Vogtle. Reorganization Chart Encl ML20206U4061999-05-11011 May 1999 Confirms Telcon with J Bailey Re Mgt Meeting Scheduled for 990528 to Discuss Results of Periodic Plant Performance Review for Plan Nuclear Facility Fo Period of Feb 1997 - Jan 1999 ML20206A6371999-04-21021 April 1999 Forwards SE Authorizing Licensee Re Rev 9 to First 10-yr ISI Interval Program Plan & Associated Requests for Relief (RR) 65 from ASME Boiler & Pressure Vessel Code ML20205Q3351999-04-15015 April 1999 Forwards Insp Repts 50-424/99-02 & 50-425/99-02 on 990214-0320.Three Violations Identified & Being Treated as Non-Cited Violations ML20205T2351999-04-0909 April 1999 Informs That on 990317,B Brown & Ho Christensen Confirmed Initial Operator Licensing Exam Scheduled for Y2K.Initial Exam Date Scheduled for Wk of 991213 for Approx 10 Candidates ML20205K7501999-04-0505 April 1999 Informs That Effective 990329,NRC Project Mgt Responsibility for Plant Has Been Transferred from Dh Jaffe to R Assa ML20205B9601999-03-24024 March 1999 Seventh Partial Response to FOIA Request for Documents. Records in App N Already Available in Pdr.App O Records Being Released in Entirety & App P Records Being Withheld in Part (Ref FOIA Exemptions 7C,2 & 5) ML20205A2771999-03-19019 March 1999 Advises of NRC Planned Insp Effort Resulting from Vogtle PPR on 990208.PPR for Plant Involved Participation of All Technical Divs in Evaluating Insp Results & Safety Performance Info for Period of Dec 1997 - Jan 1999 ML20207L8281999-03-0808 March 1999 Forwards Partially Withheld Insp Repts 50-424/99-01 & 50-425/99-01 & Notice of Violation ML20207J0431999-03-0303 March 1999 Forwards Insp Repts 50-424/98-10 & 50-425/98-10 on 981227- 990213.No Violations Noted.Licensee Conduct of Activities at Vogtle Facility Generally Characterized by safety-conscious Operations,Sound Engineering & Maint Practices ML20203G5691999-02-0505 February 1999 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licensing Exam on 990407. Representative of Facility Must Submit Ltr Indicating No Candidates or Ltr Listing Names of Candidates for Exam ML20202H9691999-01-29029 January 1999 Forwards Safety Evaluation Authorizing Rev 8 to First 10-year Interval Inservice Insp Program & Associated Requests for Relief for Vogtle Electric Generating Plant, Unit 1 ML20199J7931999-01-20020 January 1999 Forwards Insp Repts 50-424/98-09 & 50-425/98-09 on 981115-1226 at Vogtle Units 1 & 2.No Violations Were Identified.Conduct of Activities at Vogtle Was Generally Characterized by safety-conscious Operations ML20199K1381999-01-12012 January 1999 Informs That on 990117,Region II Implemented Staff Reorganization as Part of agency-wide Streamlining Effort, Due to Staffing Reductions in FY99 Budget.Organization Charts Encl ML20198S1601998-12-31031 December 1998 Forwards SER of Licensee Second 10-year Interval Inservice Insp Program Plan & Associated Requests for Relief for Vogtle Electric Generating Plant Submitted on 970529. INEEL/EXT-98-01007 Rept Also Encl ML20199E4741998-12-23023 December 1998 Provides Summary of 981105 Training Managers Conference Held in Atlanta,Georgia.Conference Agenda,List of Conference Attendees,Presentation Slides & Preliminary Schedule for FY99 & FY00 Encl ML20199J9781998-12-22022 December 1998 Responds to 981209 Meeting Re Installation of Seismic Clips on Cutler Hammer Electrical Circuit Breakers.Forwards List of Attendees & Handouts ML20198F6711998-12-11011 December 1998 Forwards Insp Repts 50-424/98-08 & 425/98-08 on 980927-1114. No Violations Identified ML20198N9431998-12-10010 December 1998 Ack Receipt of Response, to NOV Issued on 980112 Re Surveillance Testing of Reactor Trip Sys P-4 Interlock Feature at Licensee Facility.Nrc Agrees That Surveillance Testing Not Required ML20196J2181998-12-0101 December 1998 Advises of Planned Insp Effort Resulting from 981102 Insp Planning Meeting.Historical Listing of Plant Issues Called Plant Issues Matrix & Insp Plan,Including Specific Insps Such as in Security & Radiological Protection Areas Encl ML20196J2581998-12-0101 December 1998 Confirms Arrangements Made Between J Bailey & B Holbrook, Re Info Meeting Scheduled for 990210 to Discuss Licensee Performance,New Initiatives & Other Regulatory Issues Pertaining to Listed Facilities ML20196B1231998-11-23023 November 1998 Confirms Telephone Conversation Between J Bailey & P Skinner on 981120 Re Info Meeting Which Has Been Scheduled for 981209 in Atlanta,Ga,To Discuss Issues Re Seismic Retainer Clips ML20196D4981998-11-13013 November 1998 Informs That on 981007,NRC Administered Gfes of Written Operator Licensing Examination.Copy of Answer Key & Master Bw/Pwr GFE Encl,Even Though Facility Did Not Participate in Exam.Without Encl ML20195B3391998-11-0909 November 1998 Forwards Partially Withheld Insp Repts 50-424/98-12 & 50-425/98-12 on 981005-09 (Ref 10CFR73.21).No Violations Noted.Conduct of Activities Generally Characterized by safety-conscious Operations & Sound Engineering ML20155H2501998-10-21021 October 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-424/98-05 & 50-425/98-05 Issued on 980723.Concluded for Reasons Stated That Example 2 Violation Occurred as Stated in NOV ML20155A7491998-10-15015 October 1998 Forwards Insp Repts 50-424/98-07 & 50-425/98-07 on 980816-0926 & Nov.Insp Generally Characterized by Safety Conscious Operations,Sound Engineering & Maint Practices & Appropriate Radiological Controls ML20155B7771998-10-0909 October 1998 Extends Invitation to Attend Training Manager Conference on 981105 in Atlanta,Georgia.Conference Designed to Inform Regional Training & Operations Mgt of Issues & Policies That Effect Licensing of Reactor Plant Operators ML20155B4621998-09-25025 September 1998 Discusses OI Investigation Which Completed on 980728. Investigation Reviewed Circumstances Surrounding Apparent Disabling of Fire Computer Trouble Alarm by Unit Shift Supervisor.Concludes Enforcement Discretion Warranted ML20153B0401998-09-17017 September 1998 Responds to 980904 e-mail Message Making Certain Observations Re Apparent Increase in Reactor Trips at Plant, Units 1 & 2.NRC Concluded That Licensee post-trip Reviews Adequately Conducted & That No Adverse Trends,Apparent ML20153B9311998-09-16016 September 1998 Forwards RAI Re GL 97-01, Degradation of Crdm/Cedm Nozzle & Other Vessel Closure Head Penetrations, Responses for Plant,Units 1 & 2 ML20153F7081998-09-11011 September 1998 Provides Summary of 980909 Meeting Held to Discuss TS & Other Regulatory Issues Re Vogtle Electric Generating Plant. List of Meeting Attendees & Copy of Presentation Slides Encl ML20154C4871998-09-10010 September 1998 Forwards Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815 & Nov.One Violation Involved Failure to Implement Adequate C/As for Repeated Failures to Enter Applicable TS Limiting Conditions for Operation ML20151U7901998-09-0909 September 1998 Discusses 980615 Request for Exemption from Requirement of 10CFR73.55(e)(1) & (f)(1) to Provide Continuous Staffing of Plant CAS During Contingency Events.Request Denied ML20151S7291998-09-0202 September 1998 Discusses Evaluation of Util Response to GL 97-05 for Plant, Units 1 & 2.NRC Did Not Identify Any Concerns W/Sg Tube Insp Techniques Employed at Plant ML20239A4251998-08-27027 August 1998 Informs of Change Being Implemented by Region II Re Administrative Processing of Licensee Responses to Nov.Nov Responses Will Be Formally Ack as Part of Periodically Issued Integrated Insp Repts 1999-09-01
[Table view] |
Text
UNITED ST ATES
[ . nog \ JCLEAR CEGULATCY COMMIS$10N y "
C E:@h ll
- 101 c'A2tETTa STRE ET.C.C.
%, s ee
- JUN 121984 IDENTITYING DATA OMITTED
SUBJECT:
RII-84-A-OO94 This refers to our telephone conversations in which you expressed concerns related to construction deficiencies at the Vogtle Nuclear Power Flant.
An enclosure to this letter documents your concerns as I understano them based on our conversations. We have initiated actions to develop and examine the facts and circumstances of your concerne; therefore, if the -
enclosure does not completely and accurately reflect all of your concerns, please contact me collect as soon as possible at (404) 221-4193 so we can assure that they are adequately addressed during our review. If you should call and I am not available, please ask to speak to my associate, Mr. Bruno Uryc or, if you prefer, leave a message so that I can return your call.
You indicated that you would like tc send us copies of documentation relating to your concerns. I have enclosed an envelope for your use in mailing this information to us.
Regarding your request for confidentiality, let me assure you that we will make every effort to handle this matter in such a way so as to maintain your anonymity. Sone of our procedures to ensure anonymity include limiting access to documents which contain your identity, preparing documentation in which your identity is concealed, and other internal procedures which limit the dissemination of your identity on a strict need-to-know basis. I would like to point out however, that licensees can and do sometimes correctly guess the identity of individuals who provide infornation to us because of the nature of the information, or other factors beyond our control. In such cases our policy is to neither confirm or deny the accuracy of their guess.
In closing, let me assure you that every effort will be made to resolve these issues. The U. S. Nuclear Regulatory Commission is responsible for the protection of the public health and safety and the environment in the uses of nuclear facilities and materials, and assuring industry conformance to regulatory requirements. We engage in major efforts on a daily basis to ensure that we fulfill our mandate. It is concerned citizens such as yourself, who in bringing concerns to our attention, help us to meet these demanding responsibilities. We appre late your bringing your concerns to hojl2 0 88 861120 FOWLFHgS-221 PDR (1 .
______t___-_-_-
D JUN 12 1984 our attention and should you have additional questions, or if I can be of further assistance in this matter, please do not hesitate to contact me.
. Sincerely, 8 M J. B. Lank ord Investigative Coordinator
Enclosure:
Statement of Concerns 9
e
e o
RII-84-A-OO94 JUN 1 2 WE' STATEMENT OF CONCERNS
- 1. The co crete pipe portion of the intake structure had hairline cracks which were to be chisled out for repair. The workers used 10 to 12 pound chipping machines to remove the cracks. These machines created excessive vibration which may have resulted in additional damage to the pipe.
- 2. Three areas were identified where concrete had been poured prior to the removal of all trash. These areas were as follows: *
- Around the reactor where neutron detectors are located
- Embed area of the reactor where #18 rebar came out of the reactor cavity and tied into the shield wall
- Blockouts for the placement of equipment such as HVAC units on Level 3 of the Control Building .
The failure to remove all trash prior to the concrete pours resulted because some OC inspectors were more lenient than others.
- 3. The containment shell wall may contain voids. A GPC employee was obstaved po*Jnding on the containment shell wall. In some places, the wall sounded different, as if there was no concrete against the metal linte.
4 When the walls were poured for the control building, abcut a 5 inch gap between the control building and the fuel handling building was filled with ether fotm for an expansion joint. After the walls lad been poured to a height c~ about 60 feet, it wa? determined that the ether foam was supposed to have been removed. In about March 1903, work began to remove the foam but it was very difficult to do. Later, at was observed that the walls were charred. Apparently sonicone had set the foam afire in an attempt to burn it out.
- 5. In about May 1983, a fire occurred next to the north face of the containment building near the penetration area. Some bundleb of lumber which were to be used for building scaffolding caught fire from welding.
The concrete on the side of the containment building got very hot and pieces of concrete approximately 2 inches in diameter flaked off.
- 6. There was a pipe in the control building from which water runs continuously. It was rumored that there was an underground spring at the plant site and hac caused problems with backfill sinking when the construction began. It was not known whether the water from the control building was associated with tie underground spring.
l l
t UNITED ST ATES
, /,gna aseg'g ..JCLEAR CECULATGY COMMIS&lON 4 [ 3 ,, o CE260N II
{ f 101 MAalETTA STREET.N.W.
ATLANTA.OEDA0lA So3o3
\ Seee*
.. JUN 121984
> 0
~ '
Dear ~ "
- SL'BJECT : RII-84-A-OO94 This refers to our telephone conversations in which you expressed concerns I related to construction deficiencies at the Vogtle Nuclear Power Flant.
An enclosure to this letter documents your concerns as I understand them based on our conversations. We have initiated actions to develop and examine the facts and circumstances of your concerns; theref ore, if the '
enclosure does not completely and accurately reflect all af your concerns, please contact me collect as soon as possible et (404) 221-4193 so we can assure that they are adequately addressed during our review. If you should
- call and I am not available, please ask to speak to my associate, Mr. Bruno Uryc or, if you prefer, leave a message so that I can return your call.
You indicated that you would like to send us copies of documentation relating to your concerns. I have enclosed an envelope for your use in mailing this information to us.
Regarding your request for confidentiality, let me assure you that we will make every effort to handle this matter in such a way so as to maintain your anonymity. Some of our procedures to ensure anonymity include limiting access to documents which contain your identity, preparing documentation in which your identity is concealed, and other internal procedures which limit l
the dissemination of your identity on a strict need-to-know basis. I would like to point out however, that licensees can and do sometimes correctly guess the identity of individuals who provide information to us because of the nature of the information, or other factors beyond our control. In such cases our policy is to neither confirm or deny the accuracy of their guess.
In closing, let me assure you that every effort will be made to resolve these issues. The U. S. Nuclear Regulatory Commission is responsible for the protection of the public health and safety and the environment in the uses of nuclear facilities and materials, and assuring industry conformar.te to regulatory requirements. We engage in najor efforts on a daily basis to ensure that we fulfill our mandate. It is concerned citizens such as yourself, who in bringing concerns to our attention, help us to meet these demanding responsibilities. We appreciate your bringing your concerns to
, - - - - - - - - , - - w_ - . - y , _ _,n.y,- , - _ _ . - . , , - , - . , , - . _ - . - , , . - -
A JUN 2 - i':: '
cur, atteettee aa c s ec.,; yo., have accatie al questi:-s, er :' I car ca of further' assistance 1 *. this matter, pleas.e c: r.c t hetstate to certact me.
Sincerely,
^
Qb J. 8. Lank c r .1
!cwestigative Cocrd:nator d
Enclosure:
Statemer.t of Concerns b
t
((gT/f /E D $0.
De q ,p ,
Y,
o RIl-84-A-OO94 JUN12 EF!
STATEMENT OF CONCERNS
- 1. The concrete pipe portion of the intake structure had hairline cracks which were to be chisled out for repair. The workers used 10 to 12 pound chipping machines to remove tt.e cracks. These machines created excessive vibration which may have resulted in additional damage to the pipe.
l
- 2. Three areas were identified where concrete had been poured prior to l the removal of all trash. These areas were as follows:
- Around the reactor where neutron detectors are located
- Embed area of the reactor where #iB rebar came out of the, reactor cavity and tied into the Shield wall
- Blockouts for the placement of equipment such as HVAC units on Level 3 of the Control Duilding The failure to remove all trash prior to the concrete pours resulted because some OC inspectors were more ler.ient than others. ,
- 3. The containment shell wall may contain voids. A GPC employee was observed pounding on the containment shell wall. In some places, the wall sounded different, as if there was no concrete against the metal liner.
4 When the walls were poured for the control building, about a $ inch gap between the co9 trol building and the fuel handling building was filled with ether foam for an, expansion joint. Af ter the walls had been poured to a height of about 60 feet, it was determined that the etner foam was supposed to have been removed. In about March 1983, work began to remove the foam but it was very difficult to do. Later, it was observed that tne walls were charred. Apparently someone had set the foam afire in an attempt to burn it out.
l 5. In about May 1983, a fire occurred next to the north face of the containment building near the penetration area. Some bundles of lumber I which were to be used for building scaffolding caught fire from welding.
The concrete on the side of the containment building got very hot and pieces of concrete approximately 2 irches in diameter flaked off.
I l
- 6. There was a pipe in the control building from which water runs continuously. It was rumored that there was an underground spring at the plant site and had caused problems with backfill sinking when the construction began. It was not known w5 ether the water from the control building was associated with the underground spring.
\ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _
o i
(
MEMORANDUM TO CASE FILE .
- (x) Telecon i
Participants:
- Fales RII-84-A-OO94
( ) Mtg i J. E. Lantford ! Date: 06/08/84
( ) Review V. W. Panciers ! Times 3:30 pm Confidentiality Reg: Yes ALGR was contacted to obtain clarif ying inf ormation regarding his concerns. He provided the following:
CONCRETE POURS - ALGR identified 3 areas where he had seen trash which was not removed praor to concrete pours. One area was around the reactor shell where neutron detector slots are located.
- He ss1d there was a lot of #18 rebar which made it difficult to get to the trash. He also, indicated that there was a communication problem between the different crews to ensure that I the trash was removed. ALGR could not specify how much trash there was. Another arer, was around the embed around the reactor.
He described this area to consist of 4 foot pieces of #18 rebar -
wh1ch came out from the reactor and tied into the shield wall.
The third area was the blockouts in the control building. ALGR dad not know the amount of trash in the blockouts. He stated that he doubted that there was enough trash to cause equipment sitting on the blockouts to shift. ALGR had difficulty describing the specific areas of the pours which contained trash. He explained '
that the primary reason he had mentioned the trash in the pours was to describe how some DC inspector were more lenient than others. He again' described how one DC inspector might come by in the morning and not sign off on a pour because of trash. That
. afternoon a different DC inspector would come by and sign off to allow the pour, al though the tr ash had not been removed.
EyF ANSION JOINTS - ALGR stated that when walls were poured for the control building. there was about a L inch gap be: ween the control building and the fuel handling building. This gap was filled with ether foam for an expansion joint. ALGR had heard that the foam 1 allowed for enpansion in case of aa parthquate. He said the pours
- for the control building wall were made in about 20 foot lifts.
1 After about 3 sections had been poured (about 60 feet high), it 3
was decided that the etner foam was supposed to have been removed.
i ALGR said that Mr. McCarty, the Walsh Project Manager put out a paper regarding this issue. In about February or March 1983 they began trying to remove the foam but it was very difficult to do.
. One day the ALGR came to work and noticed the wall was charred.
Apparently someone had set the foam on fire and tried to burn it j out. ALGR said some of the foam may still be there.
i lC)
'a COrJT Al rJME NT WJ._' L FIRE - A fare oc urred ne:: t to the north 4 ace of the ccntainment building near the penetration ers3, gem, j
bundles of lutcGr which were to be used for building staffegegng caught fare from some welding. The concrete on the side of the
. containment building got very hot and pieces of concrete about the sace of silver dollars popped off. This occurred about May 19E7, A cimallar fire oct*urred on the Unit I side but ALGR doesn 't inc.
If any damage occurred.
WATER IN COrJTFOL BUILDING - ALGR said there was a pipe an the '
control buil:1ng with water running from it all the time. He did not Inow whe'e the water was coming from. ALGR said he had heard that there was an underground spring at the plant site and had caused problems with the bacif111 sin!Ing when the construct 1on began.
ALGR'S - ALGR discussed the information he had previousl y prcvided regarding the circumstances surrounding his N He said his primary concern.is the way he was treated after he identified concerns to GPC Ovality Concerns Program. He said he felt he had been betrayed by GPC.
Frepared By: J. Lantford Date: 06/08/04
+ .~.-
- z. , , , _ _
, **m, ,
f
y MEMORANDUM TO CASE FILE (x) Teleqon
Participants:
- Files RII-84-A-OO94
( ) Mtg l J. B. Lankford : Date: 06/08/84
( ) Review ! V. W. Panciera : Time: 3:30 pm Confidentiality Reg: Yes ALG,R was contacted to obtain clarifying information.regarding his concerns. He provided the followings CONCRETE POURS - ALGR identified 3 areas *where he had seen trash which was not removed prior to concrete pours. One area was around the reactor shell where neutron detector slots are located.
He said there was a lot of #18 rebar which made it difficult to get to the trash. He also indicated that there was a communication problem between the different crews to ensure that the trash was removed. ALGR could not specify how much trash there was. Another area was around the embed around the reactor.
He described this area to consist of 4 foot pieces of #18 rebar which came out from the reactor and tied into the shie J wall.
The third area was the blockouts in the control building. ALGR did not know the amount of trash in the blockouts. He stated that he doubted that there was enough trash to cause equipment sitting on the bloclouts to shift. ALGR had difficulty describing the spectfac areas of the pours which contained trash. He explained that the primary reason he haa mentioned the trash in the pours was to describe how some OC inspector were more lentent than others. He again described how one DC inspector might come by in the morning and not sign off on a pour because of trash. That afternoon a different DC inspector would come by ano sign off to allow the pour. although the trash had not been removed.
EYPANSION JOINTS - ALGR stated that when walls were poured for the control building. there was about a 5 inch gap between the control building and the fuel handling building. This gap was filled with ether foam for an expansion joint. ALGR had heard that the foam allowed for e,pansion in case of an earthqual e. He said the pours for the control building wall were made In about 20 foot lifts.
After about 3 sections had been poured (about 60 feet high). it was decided that the ether foam was supposed to have been removed.
ALGR said that Mr. McCarty, the Walsh Project Manager put out a paper regarding this issue. In about February or March 1983 they began trying to remove the foam but it was very difficult to do.
One day the ALGR came to wort: and noticed the wall was charred.
Apparuntly someone had set the foam on fire and tried to burn it out. ALGR said some of the foam may still be there.
It
CONTAINMENT WALL FIRE - A f i re occurred ne): t to the north face of the containment building near the penetration area. Some bundles Qf lumber which were to be used for building scaffolding caught fire from some welding. The concrete on the side of the containment bu11 ding got very hot and pieces of concrete about the size of silver dollars popped off. This occurred about May 198!. .
A similiar fire occurred on the Unit 1 side but ALGR doesn't 6now if any damage occurred.
WATER IN CONTROL BUILDING - ALGR sand there was a pipe an the control building with water running from at all the time. He did not lnow where the water was coming from. ALGR said he had heard that there was an underg<ound sprang at the plant site and had caused problems with the bact.f111 sa nl ing when the construction began.
ALGR'S DISMISSAL - ALGR discussed the information he had revi ousl y provided regarding the circumstances surrounding llh He said has primary concern is the way he was treated after he identified concerns to GFC Ouality Concerns Program. He said he felt he had been betrayed by GFC.
Prepared By: J. Laniford Date: 06/08/84
t b
- (:: ) Tolocon : Ferticipants: : Filot RII-E4-A-OO94 k ( ) Mtg ,,
i J. B. Loniford l Dstet 05/!1/E4
( ) Review : : 06/01/84
- T 1,ne : 5/01 11:30 am Confidentiality Reg: YES : 6/1 2:00 pm led to discuss the ~
circumstances surrcunding his from ~ - ~ ,
at Vogtle. ALGR had been a for about "*
years. His primary concern regarded his being ~
identifying construction concerns to GPC. His description of the construction discrepancies follow. The information regarding his does not appear to warrant NRC action. I did provide him the tele no of the Atlanta DOL office and suggested that he discuss this matter with them.
Intale Structure - ALGR described the intal e structure as a metar and concrete pipe (about 10' high) which runs from the turbine ~ ~ ~ " ~
building to the cooling tower. In ALGN uas ,
transferred to the intal e structure assigned to the.
While assigned to this area. he observed that the concrete pipe portion of the intal e structure had hairline cracts. The cracts were most prominent near the Joints of the pipe. Worters were in the process of chipping out the hairline cracts to mal e rep airs. The worlers were using 10 to 12 pound chipping machines with a bit about 1 inch in diameter. ALGR euplained that these chipping machines were too big and may have resulted in more damage to the pipe. The chippers caused pieces of concrete about one foot in diameter to fall from the pipes.
ALGR said there was so much vibration that concrete would fall from sections of the pipe which were 5 or 6 joints away from where the actuel chipping was being done. ALGR f elt the wori:ers were using the big chippers to create more work which was inefficient and were also doing more damage to the pipe by using the big chippers. ALGP said he e:rpressed his concern to a GPC engineer e and then tool his concern to the GPC OC Concerns Frogram. ALGR said the worlers eventually began using smaller chipping machines (1 to 2 pound with a small bit). The small chippers were used on the last 50 to 75 yards of the pipe.
but the large chippers had been used on the first 15Q yards.
Concrete Fours - ALGR stated that he had seen concrete pours for bloclouts without all trash being removed prior to the pour. He described a blocl.out as a space in a slab for setting equipment on such as HVAC equipment. He enplained that some OC inspectors were more strict than others. He described how one OC inspector
. l M h h b h } h k N N M k h h h EI$ M b
r ., 1 e
might come by an the morning to do a precour inspection fc" a k bloclout and not epprove it beccuse the blocl out was dir <. Later in the day a different DC Inspector might com2 by cnd a;;-ove the pour although the bloclout had not been cleaned. ALGR said cf he thewas involved in several pours for for blocd outs eni control building. He said he did nct want to mal e a big deal out of this issue. he was only using this as an enample ALGR to shew saidthat there some OC Inspectors were more lensent than others.
were 2 or 3 OC inspectors that were more lenient than other He could not remember their nemes. thought che was inspectors.
named Containment Shell Wall Concrete Four - ALGR stated thet when the initial pours were made for the shell wall for containment building one. he observed a GPC employee pounding on t7e outside of thethere shellwas wall. In some places. the wall sounded different.
as if no concr ete against the metal. . butALGR mentioned he said it was*
this to has superintendent, not a void. to Just forget it. This occurred the end of 1981 or early 1982. ALGR said there could have been a 1/4 inch gap or there might be a big gap. Algr said he had heard that radiation travels left to right. instead of up and down. and he was concerned that the concrete might not be thicl. enough to stop the radiation, bed the f ollowing circumstances r s ,,
After discussing his concerns with the GFC engineer abcet the wcel being performed on the intal.e structure. ALGR was approached by the General Foreman of the finishers who told ALGR te leep his mouth shut and to not give out any informatten. In Decercer 1987 ALGR e.:oressed his concerns about the worn. being perforced on the int al e structure to the head of the GFC OA Department. In
. he was called in to discuss his concern with the head of the OA Concerns Frogram. Mr. Miles. About the end of Januery he t ool' one of the large bats and a small bit and showed them to the head of the CA Department. and eupounced on what being he started was
After ALGR had reported his concerns. cursed harassed by his coworlers. One individual. ALGF felt him. ALGR was then transferred to the the transfer was made to try and get rid of him, he enc'ained that there was always a good chance of being l aid of f 3 rom the On January 20. 1984. ALGR wroteand a mem:
beang to document his complaints about being transferred
- harassed on the job. He gave a copy of the letter toread the, the letter and t'old ALGR the the problem was rot stated in the letter. Apparantly. ALGA had only discussed his perscnal problems in the letter and had not discussed theatproblem got very mad him. The withnent the intal e structure. ALGR said day. ALGR tool a copy of the letter to Mr. Miles. Heac ci CC Concern Frogram. Mllet wouldn't read the l etter (ALGA 4elt Miles i et i4 e
i f f .
a
g had elreads been briefed by. but t all ed about getting h : c.
cnothcr job. MILES then called Manager cnd discussed the pcssibility of getting ALGR enother
- job. end asled him cbout c new Job.
Later ALGR caw
~~' said it was out of the Question now. Onf ALGR had another meeting with MILES at which time ALGR wes Osled to sign a memo which stated that ALGR had expressed his .
concerns and the concerns had been adequately addressed, etc.
ALGR said he signed the memo but later had second thoughts and decided to write another memo. This memo referenced the February ,
29 memo and e :pl ained thet he could not sign the memo because he had not worled in the intal e structure area for the past 1 and 1/2 n.onth and therefore could not inow whether or not the corrective action was adequate. He also stated that he was still apprehensive about his future. He requested that this letter be appended to the memo which he had stgned and stated that his signeture on that memo would only be valid if this letter was attached. He also requested a copy of the memo he had signed. On about March 1. ALGR was called to MILES office and the GFC -
Attorney. Mr. WHITNEY was present. WHITNEY wanted to know who ALGRs attorney was.
. ALGR said he did ,
not have an attorney. During March and April there were no new ,
developments. A few days ago ALGR saw a dumping concrete. ALGR went and got a union steward and filed a grievance. There was a big meeting about this and apparantly caused some hard feelings. On Wednesday.. ALGR requested to see Mr. MILEE. A few ntnutes later a co-worter.
called ALGR ALGR refused and ALGR said ALGR went to about this incident. McCARTY talled to the other woriers who were witnesses and later told ALGR that the woriers said that . ALGR but had not[
ALGR went to the and got a report which indicated that he hed some . On 5/!1/84 ALGF went in to wor 6 and went to see ALGR told that he wanted to get the nemet of the . refused mad '"--
cave ALGR has termination ollp which = ' '
he y[ggg[gf ALGR asled what was the but.he,was not told.
ALGR asled that the NRC net act on his cencerns for a weel or so.
Ho sold he planned to mal e one more phone call to see if he might get his job bocl .
JEFFRd C. uwx WVESTIGATIVE COORDINATOR
.,. . , , - , ,. ..- - v . . - . ~.. ,.. c .. x 3..,. . .
( f : f ik jf f( *