Forwards Safety Insp Rept 50-219/86-24 on 860818-1005 & Notice of Violation.Action to Establish 24 H Mgt Coverage of Plant During Rept Period Is Positive Step Towards Assuring Satisfactory Conclusion to Outage
ML20213E975
Person / Time
Site: Oyster Creek
Issue date: 11/04/1986
From: Kister H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Fiedler P
GENERAL PUBLIC UTILITIES CORP.
Shared Package
ML20213E979 List:
References
NUDOCS 8611130396
Download: ML20213E975 (2)


See also: IR 05000219/1986024

Text

!

NOV 41986

Docket No. 50-219

License No. OPR-16

GPUNucle[rCorporation

ATTN: Mr. P. B. Fiedler

Vice President and Director

Oyster Creek Nuclear Generating Station

P. O. Box 388

Forked River, New Jersey 08'11

Gentlemen:

Subject: Inspection Report No. 50-219/86-24

This refers to the routine safety inspection by Messrs. W. Bateman,

J. Wechselberger and W. Baunack from August 18 - October 5,1986 at the

Oyster Creek Nuclear Generating Station. The inspections consisted of document

reviews, interviews and observations of activities as documented in the enclosed

inspection report. The findings were discussed with you and other members of

your staff at the conclusion of the inspection.

An apparent violation of NRC requirements is cited in Appendix A and categorized

under the General Statement of Policy and Procedure for NRC Enforcement Actions,

10 CFR Part 2, Appendix C (Enforcement Policy 1986). Additionally, a concern

arose during review of Licensee Event Reports regarding an excessive time lapse

between initiation of a safety concern and its resolution. The safety concern

that took approximately 18 months to resolve involved the connection of two

non-seismic pipe lines to Emergency Service Water piping. In your response to

this report, please provide additional information relative to (1) the delay in

reporting and addressing this safety concern and (2) steps you will take to

improve the timeliness of your evaluation process.

We acknowledge receipt of your September 5,1986 response to the Violation cited

in Inspection Report 86-17 and the September 11, 1986 response to the Violations

cited in Inspection Report 86-12. Your corrective actions will be verified in a

future NRC inspection.

Your action to establish twenty-four hour management coverage of the plant during

this report period is considered a positive step toward assuring a satisfactory

conclusion to the outage.

A review of the completion status of commitments you made in your December 5,

1985, response to NRC Systematic Assessment of Licensee Performance (SALP)

Report 85-99 was performed and is documented in this report. In general it

appears you have initiated steps and made progress toward accomplishing your

commitments, although not all of your corrective action schedules were met.

8611130396 861104

PDR ADOCK 05000219

G PDR

urrtCIAL-RECORD COPY IR OC 86-24 - 0001.0.0

10/30/86

y

n es j  ;

r

GPU Nuclear Corporation 2

.

The response directed by this letter and the accompanying Notice are not

subject to the clearance procedures of the Office of Management and Budget as

required by the Paperwork Reduction Act of 1980, PL 96-511.

Your cooperation with us in these matters is appreciated.

Sincerely,

Original Signed By:

Harry B. Kister, Chief

Projects Branch No. 1

Division of Reactor Projects

Enclosure:

(1) Notice of Violation

(2) NRC Region I Report No. 50-219/86-24

cc w/ encl:

BWR Licensing Manager

Licensing Manager, Oyster Creek

Public Document Room (PDR)

local Public Document Room (LPDR)

Nuclear Safety Information Center (NSIC)

NRC Resident Inspector

State of New Jersey

bcc w/ encl:

Region I Docket Room (with concurrences)

Management Assistant, DRMA (w/o encis)

DRP Section Chief

DRS Director

DRSS Director

J. Wiggins, DRS

P. K. Eapen, DRS

M. Shanbaky, DRSS

9

RI:DRP RI.:DRP RI: RP

[xBateman Blough Kister

10/ h'86 10/A/86 1$/d/86

- 0FFICIAL RECORD COPY IR OC 86-24 - 0001.1.0

10/30/86

,_-