ML20212P098

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for Dec 1986
ML20212P098
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 12/31/1986
From: Bregni L
DETROIT EDISON CO.
To:
Shared Package
ML20212P094 List:
References
NUDOCS 8703130277
Download: ML20212P098 (3)


Text

OPERATING DATA REPORT DOCKET NO.

50-341 COMPLETED BY L.P.Bregni DATE January 12, 1987 TELEPHONE (313)586-5313 OPERATING STATUS 1.

UNIT NAME:

Fermi 2 INotes l

2.

REPORTING PERIOD: December l

l 3

LICENSED THERMAL POWER (MWt): 3292 l

l 4.

NAMEPLATE RATING (GROSS MWe):

1215 l

l 5

DESIGN ELECT RATING (Net MWe): 1093 I

I 6.

MAX DEPENDABLE CAP (GROSS MWe):

l l

7 MAX DEPENDABLE CAP (Net MWe):

l l

8.

IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUMBER 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS: None 9

POWER LEVEL TO WHICH RESTRICTED, IF ANY (MWe Net):

218.6

10. REASONS FOR RESTRICTION, IF ANY: Fermi 2 is in the startup test phase and is currently authorized to operate not in excess of 20% of rated thermal power.

(Ref. J. G. Keppler letter of September 12, 1986)

THIS MONTH YR TO DATE CUMULATIVE

11. HRS IN REPORTING PERIOD 744 2,433 9 2,433 9
12. HRS REACTOR WAS CRITICAL 308.9 869.8 869.8
13. REACTOR RESERVE SHUTDOWN HRS 0

0 0

14. HOURS GENERATOR ON-LINE 33 3 129.1 129.1
15. UNIT RESERVE SHUTDOWN HOURS 0

0 0

16. GROSS THERMAL ENERGY GEN (MWH) 55,680 223,248 223,248
17. GROSS ELECT ENERGY GEN (MWH) 2,810 10,450 10,450
18. NET ELECT ENERGY GEN (MWH)

-8,693

-25,959

-25,959

19. UNIT SERVICE FACTOR N/A N/A N/A
20. UNIT AVAILABILITY FACTOR N/A N/A N/A i
21. UNIT CAP FACTOR (USING MDC NET)

N/A N/A N/A

22. UNIT CAP FACTOR (USING DER NET)

N/A N/A N/A

23. UNIT FORCED OUTAGE RATE N/A N/A N/A
24. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, DURATION OF EACH)

None l

25. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A
26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION):

FORECAST ACHIEVED INITIAL CRITICALITY 06/20/85 06/21/85 INITIAL ELECTRICITY 10/01/86 09/21/86 COMMERCIAL OPERATION 05/01/87 8703130277 870112 PDR ADOCK 05000341 R

PDR

AVERAr?E DAILY UNIT PC'/ml IEVEL DOCKET No.

50; p.1,. _ _ _

UNIT FERMI 2 DATE January 12, 1987 COMPLETED BY L. P. Bregni TELEPHONE (313) 586-5313 MONTH December DAY AVERAGE DAII.Y POWER LEVEL DAY AVERAGE DAILY POWER LEVEL

)

(MWe-Net)

(HWe-Net) 1 0

17 0

2 0

18 0

3 0

19 0

4 0

20 0

5 0

21 0

6 0

22 0

7ii 0

23 0

j 8

0 24 0

9 0

25 0

10 0

26 0

11 0

27 0

12 0

28 0

13 0

29 0

14 0

30 68.4 15 0

31 54.5 16 0

1

e.-

c,

. UNIT SHUTDOWNS AND POWEQ REDUCTIONS DOCdET NO.

50-301

.'DATE January 12. 1987 UNIT NAME Fermt 2 COMPLETED BY.. L.

P.

Breoni TELEPHONE (313)586-5313 REPORT MONTH December i

METHOD OF LER SYS COMP.

CAUSE & CORRECTIVE l

NO.

DATE TYPE DUR REASON SHUTTING DOWh.

NO.

CODE CODE ACTION TO PREVENT 1

(1)

(HRS)

(2)

THE REACTOR (4)

(5)

RECURRENCE l'

(3)'

a.

I I-86-06 861201 F

435.1 A

2 N/A HC HTEXCHD Shutdown continued from last moe i t ti to repair the cause of e=cesslve.

air in-leakage into the condenser and to install new relief valves.

to prevent future overpressuriza-tion of the condensate return line.

I (1) F: FORCED (2) REASON:

(3) METHOD:

(4) EXHIBIT G - INSTRUCTIONS S SCHEDULED A - EQUIPMENT-FAILURE (EXPLAIN) 1 - MANUAL FOR PREPARATION OF DATA B - MAINTENANCE OR TEST 2 - MANUAL SCRAM ENTRY SHEETS FOR-LICENSEE C - REFUELING 3 - AUTOMATIC SCRAM EVENT REPORT (LER) FILE D - REGULATORY RESTRICTION 4 - CONTINUED (NUREG-0161)

E - OPERATOR TRAINING & LICENSE EXAMINATION 5 - REDUCED LOAD F - ADMINISTRATIVE 9 - OTHER G.- OPERATIONAL ERROR (EXPLAIN)

H - OTHER (EXPLAIN)

(5) EXHIBIT I - SAME SOURCE