Text
_
OPERATING DATA REPORT DOCKET NO.
50-369 DATE 12/15/86 COMPLETED BY
.T A naavis TELEPHONE 704-373-7567 OPERATING STATUS
- 1. Unit Name:
McGuire 1 Notes
- Nameplate Rating
- 2. Reporting Period: Novamher 1. 1986-November 30. 1986 (Gross MWe) calculated as
- 3. Licensed Thermal Power IMWt):
3411 1450.000 MVA x.90 power 1305*
factor per Page lii,
- 4. Nameplate Rating (Gross MWe):
- 5. Design Electrical Rating (Net MWe):
1150 1
- 6. Maximum Dependable Capacity (Gross MWe):
- 7. Maximum Dependable Capacity (Net MWe):
1150
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:
Nose None
\\
- 9. Power Level To Which Restricted. If Any (Net MWe):
- 10. Reasons For Restrictions,if Any:
i This Month Yr..to-Date Cumulative
!I. Hours In Reporting Period 720.0 8 016.0 43 824.0
- 12. Number Of Houn Reactor Was Critical 47.3 4 278.0 29 283.9
- 13. Reactor Resene Shutdown Hours
- 14. Hours Generator On.Line 35.8 4 172.0 28 883.5
- 15. Unit Resene Shutdown Hours
- 16. Gross Thermal Energy Generated (MWH) 44 556 13 071 081 80 437 656 12 453 4 534 810 27 846 043
- 17. Gross Electrical Energy Generated (MWH)
- 18. Net Electrical Energy Generated (MWH) 39 4 306 880 26 458 894
- 19. Unit Service Factor 5.0 52.1 65.9
- 20. Unit Availability Factor 5.0 52.1 65.9
- 21. Unit Capacity Factor (Using MDC Net) 0.0 46.7 51.4
- 22. Unit Capacity Factor (Using DER Net) 0.0 46.7 51.4
- 23. Unit Forced Outage Rate 95.0 18.4 15.0
- 24. Shutdowns Schedaled Oser Nest 6 MonthslType, Date,and Duration of Eacht:
Nnno
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup:
- 26. Units in Test Status IPrior to Commercial Operation):
Forecast Achiesed INITIA L CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPER ATION 8612220200 861215 (9 77i PDR ADOCK 05000369 R
AVERASE DAILY UNIT POWER LEVEL DOCKET NO.
50-369 UNIT McGuire !
DATE December 15,1996 COMPLETED BY J. A. Reavis TELEPHONE 704-373-7567 MONTH NOVEMBER,1986 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWE-Neti (MWE-Net) 1 0
17 0
2 0
18 0
z....
-_=._--
3 0
19 0
4 0
20 0
5 0
21 0
6 0
22 0
7 0
23 0
8 0
24 0
=
9 0
25 0
..............=-- --
10 0
26 0
=.............
I1 0
27 0
12 0
28 0
13 0
29 79 14 0
30 364 15 0
31 I6 0
m.-
v---- - -. - - -, - - - - - - -, - - -
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET N0.
50-369 UNIT NAME McGuire 1 3
DATE 12/15/86 REPORT PONTH November 1986 COMPLETED BY J. A. Reavis TELEPHONE 704-373-7567 "uo o o,$
License y
Cause & Corrective e37 "c
ofa g
g Event
,Be, g
No.
Date
%h Action to o-o usE a
no e
i N 55 S
$5S Report #
- 8
$y Prevent Recurrence 8
12 86-11-01 F
684.17 A
4 XX VALVEX Rotork Valve Actuator Check-Out 46-p 86-11-29 S
F ZZ ZZZZZZ Dispatcher Requirements i
1 2
3 4
Reason:
Method:
Exhibit G - Instructions S
led A-Equipment Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER)
D-Regulatory Restriction 4-Other (Explain)
File (NtREG-0161)
E-Operator Training 6 License Examination F-Administrative 5
G-Operational Error (Explain)
Exhibit I - Same Source H-Other (Explain)
(9/77)
DOCKET NO: 50-369 UNIT: McGuire 1 DATE: 12/15/86 NARRATIVE
SUMMARY
Month: November 1986 McGuire Unit I returned to service on 11/29/86 after completing its Rotork valve inspection outage. The unit was held at 30% power because of low load demand until 11/30, when increased load requirements allowed the unit to increase power at 3% per hour.
s
~
OPERATLNG D ATA REPORT DOCKET NO.
50-370 DATE 12/15/86 CO31PLETED BY J.A. Reavis TELEPHONE W -171-7567 OPERATING STATUS
- 1. Unit Name:
McGuire 2 Notes
- Nameplate Rating
- 2. Reporting Period: Novamhnr 1. 1986-Nnvomher 30. 1986 (Gross MWe) calculated as
- 3. Licensed Thermal Power (5 twt):
3411 1450.000 MVA x.90 power
- 4. Nameplate Rating (Gross 5tWc):
1305*
r Page lii,
- 5. Design Electrical Rating (Net SIWE):
1150
- 6. Staximum Dependable Capacity (Gross 31We):
- 7. Staximum Dependable Capacity (Net SIWE):
1150
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report.Give Reasons:
- 9. Power Level To which Restricted. if Any (Net 31We):
- 10. Reasons For Restrictions.If Any:
This Stonth Yr..to.Date Cumulative 8 '16.0 24 120.0 i1. Hours in Reporting Period 720.0 0
- 12. Number Of Hours Reactor Was Critical 303.4 5 026.4 16 655.0
- 13. Reactor Reserve Shutdown flours
- 14. Hours Generator On.Line 280.2 4 860.6 16 126.2
- 15. Unit Reserse Shutdown Hours
- 16. Gross Thermal Energy Generated (>IWH) 834 670 16 010 098 52 160 475
- 17. Gross Electrical Energy Generated (AlWH) 2Ro 050 5 594 210 18 294 777
- 18. Net Electrical Energy Generated (5tWH) 269 768 5 344 907 17 498 560
- 19. Unit Service Factor 38.9 60.6 66.9
- 20. Unit Asailability Factor 38.9 60.6 66.9
- 21. Unit Capacity Factor (Using SIDC Net) 32.6 58.0 62.0
- 22. Unit Capacity Factor iUshg DER Net) 32.6 58.0 62.0
- 23. Unit Forced Outage Rate 61.1 12.5 19.6
- 24. Shutdowns Scheduled Over Next 6 Stonths (Type. Date, and Duration of Each t:
None
- 25. If Shut Down At End Of Report Period. Estimated Date of Startup:
- 26. Units in Test Status (Prior to Commercial OperationI:
Forecast Achiesed INITIA L CRITICA LITY INITIAL ELECTRICITY CO\\lNIERCIA L OPER ATION (9/77) l
AVERABE DAILY UNIT POWER LEVEL DOCKET NO.
50-370 UNIT McGuire 2 DATE December 15, 1986 COMPLETED BY J. A. Reavis TELEPHONE 704-373-7567 MONTH NOVEMBER,1986 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWE-Net)
(MWE-Net) 1 0
17 0
2 0
18 35 3
0 19 581 4
0 20 441 5
0 21 307 6
0 22 984 7
0 23 1144 8
0 24 1145 9
0 25 1149 10 0
26 1145
......=
11 0
27 1145 12 0
28 1141 13 0
29 1145
....__..--=
14 0
30 1150 15 0
31 16 0
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-370 UNIT NAME McGuire 2 DATE 12/15/86 REPORT PONTH November 1986 COMPLETED BY J. A. Reavis TELEPHONE 704-373-7567 "s_
O I o,[u License y
Cause & Corrective e32 "c
o3E Ns.
Date
~.
%h yg Event
,Be, g
Action to o
H; 5E E
%Sb s,3 83 S
o~
m zwo Report #
mu ou Prevent Recurrence 14 86-11-01 F
408.20 A
4 XX VALVEX Rotork Valve Actuator Work 15 86-11-18 F
13.82 H
4 EB ELECON Generator Breakers & Disconnects Opened Due to Excess Moisture in the Bus Lines (Reactor Critical) 30-p 86-11-19 F
H EB ELECON "A" Bus Line Inspection 31-p 86-11-19 F
A CH VALVEX Work on "B" Feed Pump Recirculating Valve 16 86-11-20 F
17.82 G
3 CB PUMPXX Reactor Coolant Pump "A" Coasted Down on the Loss of Power Fro.n Bus "2TA" 1
2 3
4 Reason:
Method:
Exhibit G - Instructions S
uled A-Equipnent Failure (Explain) 1-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refueling 3-Automatic Scram Event Report (LER)
D-Regulatory Restriction 4-Other (Explain)
File (NUREG-0161)
E-Operator Training 6 License Examination F-Administrative S
G-Operational Error (Explain)
Exhibit I - Same Source H-Other (Explain) i(9/77)
~
DOCKET NO:
50-370 UNIT:
McGuire 2 DATE:
12/15/86 NARRATIVE SUbefARY Month: November 1986 McGuire Unit 2 returned to service on 11/18 following the completion of its Rotork valve inspection outage. While preparing to swap from the auxiliary feed nozzles to the main feed nozzles, a generator lockout occurred. The lockout was caused by moisture in the "B" train isolated phase bus.
The "B" bus was dried and the unit returned to service on 11/19.
It held power at 50% while waiting for the "A" train isolated phase bus to be dried and placed in service. The unit tripped from 100% power on 11/20, when a technician inadvertently caused a 6900 volt switchgear to lose power. The unit returned to service on 11/21 and increased power to 100% where it operated for the remainder of the month.
l l
MONTHLY REFUELING INFORMATION REQUEST 1.
Facility name: McGuire, Unit 2 2.
Scheduled next refueling shotdown:
May, 1987 3.
Scheduled restart following refueling:
July, 1987 4.
Will refueling or resumption of operation thereafter require a technical specification change or other license amendment? Yes If yes, what will these be?
Technical Specification Revision If no, has reload design and core configuration been reviewed by Safety Review Committee regarding unreviewed safety questions? N/A 5.
Scheduled date(s) for submitting proposed licensing action and supporting information: N/A 6.
Important licensing considerations (new or different design or supplier, unreviewed design or performance analysis methods, significant changes in design or new operating procedures).
7.
Number of fuel assemblies (a) in the core:
193 (b) in the spent fuel pool:
177 8.
Present licensed fuel pool capacity:
1463 Size of requested or planned increase:
9.
Projected date of last refueling which can be accommodated by present licensed capacity:
August, 2010 DUKE POWER COMPANY DATE: December 15, 1986 Name of
Contact:
J. A. Reavis Phone:
704-373-7567
p McGUIRE NUCLEAR STATION MONTHLY OPERATING STATUS REPORT 1.
Personnel Exposure For the month of October, no individuals exceeded 10 percent of their allowable annual radiation dose limit.
2.
The total station liquid release for October has been compared with the Technical Specifications maximum annual dose conmitment and was less than 10 percent of this limit.
The total station gaseous release for October has been compared with the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.
^