OPERATING DATA REPORT Docket No. 50-317 Date:
June 10, 1986 Completed by R. Porter Telephone: (301) 260-4868 OPERATING STATUS
- 1. Unit Name:
Calvert Cliffs No. 1
- 2. Reporting Period:
MARCH
- 3. Licensed Thermal Power (MWT):
2,700
- 4. Nameplate Rating (Gross MWe):
918
- 5. Design Electrical Rating (Net MWe):
845
- 6. Maximum Dependable Capacity (Gross Mwe):
860
- 7. Maximum Dependable Capacity (Net MWe):
825
- 8. Change ~in Capacity Ratings:
None
- 9. Power Level to Which Restricted (Net MWe):
N/A
- 10. Reasons for Restrictions:
N/A This Month Yr-to-Date Cumulative
- 11. Hours in Reporting Period 744 2,160 95,533
- 12. Number of Hours Reactor was Critical 596.8 1,993.4 74,858.9
- 13. Reactor Reserve Shutdown Hours 0.0 0.0 3,019.4
- 14. Hours Generator On-Line 588.0 1,973.5 73,333.0
- 15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 16. Gross Thermal Energy Generated (MWH) 1,549,862 5,231,325 182,555,518
- 17. Gross Electrical Energy Generated (MWH) 522,674 1,771,200 60,374,012
- 18. Net Electrical Energy Generated (MWH) 500,412 1,696,984 57,613,279
- 19. Unit Service Factor 79.0 91.4 76.8
- 20. Unit Availability Factor 79.0-91.4
-76.8 I
- 21. Unit Capacity Factor (Using MDC Net) 81.5 95.2 73.5
- 22. Unit Capacity Factor (Using DER Net)
.79.6 93.0 71.4
- 23. Unit Forced Outage Rate 21.0 8.6 9.0
- 24. Shutdowns Scheduled over Next Six Months (type, date and duration):
None
- 25. If Shutdown at End of Report Period, Estimated Date of Startup:
N/A 8606230199 860610 DR ADOCK 05000317
.PDR
. -. -. ~. -
OPERATING DATA REPORT Docket No. 50-318 Date:
June 10, 1986 j
completed by R. Porter Telephone: (301) 260-4868 1
OPERATING STATUS
- 1. Unit Name:
Calvert Cliffs No. 2
- 2. Reporting Period:
MARCH
- 3. Licensed Thermal Power '(MWT):
2,700 l
- 4. Nameplate Rating (Gross MWe):
918
- 5. Design Electrical Rating (Net MWe):
845
- 6. Maximum Dependable Capacity (Gross Mwe):
860 l
- 7. Maximum Dependable Capacity (Net MWe):
825
- 8. Change in Capacity Ratings:
None
- 9. Power Level to Which Restricted (Net MWe):
N/A
- 10. Reasons for Restrictions:
N/A i
This Month Yr-to-Date Cumulative l
- 11. Hours in Reporting Period 744 2,160 78,888
- 12. Number of Hours Reactor was Critical 719.7 2,118.6 65,561.6
- 13. Reactor Reserve Shutdown Hours 24.3 24.3 1,285.0
- 14. Hours Generator On-Line 716.9 2,113.4 64,524.7
- 15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
- 16. Gross Thermal Energy Generated (MWH) 1,899,062 5,544,578 162,026,614
- 17. Gross Electrical Energy Generated (MWH) 641,777 1,886,558 53,408,082
- 18. Net Electrical Energy Generated (MWH) 615,364 1,809,178 50,959,435
- 19. Unit Service Factor 96.4 97.8 81.8
- 20. Unit Availability Factor.
96.4 97.8 81.8
- 21. Unit Capacity Factor (Using MDC Net) 100.3 101.5 78.5
- 22. Unit Capacity Factor (Using DER Net) 97.9 99.1 76.4
- 23. Unit Forced Outage Rate 0.0 9.1 6.0
- 24. Shutdowns Scheduled Over Next Six Months (type, date and duration):
None
- 25. If Shutdown at End of Report Period, Estimated Date of Startup:
N/A