OPERATING DATA REPORT Docket No. 50-317 Date:

June 10, 1986 Completed by R. Porter Telephone: (301) 260-4868 OPERATING STATUS

1. Unit Name:

Calvert Cliffs No. 1

2. Reporting Period:

MARCH

3. Licensed Thermal Power (MWT):

2,700

4. Nameplate Rating (Gross MWe):

918

5. Design Electrical Rating (Net MWe):

845

6. Maximum Dependable Capacity (Gross Mwe):

860

7. Maximum Dependable Capacity (Net MWe):

825

8. Change ~in Capacity Ratings:

None

9. Power Level to Which Restricted (Net MWe):

N/A

10. Reasons for Restrictions:

N/A This Month Yr-to-Date Cumulative

11. Hours in Reporting Period 744 2,160 95,533
12. Number of Hours Reactor was Critical 596.8 1,993.4 74,858.9
13. Reactor Reserve Shutdown Hours 0.0 0.0 3,019.4
14. Hours Generator On-Line 588.0 1,973.5 73,333.0
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 1,549,862 5,231,325 182,555,518
17. Gross Electrical Energy Generated (MWH) 522,674 1,771,200 60,374,012
18. Net Electrical Energy Generated (MWH) 500,412 1,696,984 57,613,279
19. Unit Service Factor 79.0 91.4 76.8
20. Unit Availability Factor 79.0-91.4

-76.8 I

21. Unit Capacity Factor (Using MDC Net) 81.5 95.2 73.5
22. Unit Capacity Factor (Using DER Net)

.79.6 93.0 71.4

23. Unit Forced Outage Rate 21.0 8.6 9.0
24. Shutdowns Scheduled over Next Six Months (type, date and duration):

None

25. If Shutdown at End of Report Period, Estimated Date of Startup:

N/A 8606230199 860610 DR ADOCK 05000317

.PDR

. -. -. ~. -

OPERATING DATA REPORT Docket No. 50-318 Date:

June 10, 1986 j

completed by R. Porter Telephone: (301) 260-4868 1

OPERATING STATUS

1. Unit Name:

Calvert Cliffs No. 2

2. Reporting Period:

MARCH

3. Licensed Thermal Power '(MWT):

2,700 l

4. Nameplate Rating (Gross MWe):

918

5. Design Electrical Rating (Net MWe):

845

6. Maximum Dependable Capacity (Gross Mwe):

860 l

7. Maximum Dependable Capacity (Net MWe):

825

8. Change in Capacity Ratings:

None

9. Power Level to Which Restricted (Net MWe):

N/A

10. Reasons for Restrictions:

N/A i

This Month Yr-to-Date Cumulative l

11. Hours in Reporting Period 744 2,160 78,888
12. Number of Hours Reactor was Critical 719.7 2,118.6 65,561.6
13. Reactor Reserve Shutdown Hours 24.3 24.3 1,285.0
14. Hours Generator On-Line 716.9 2,113.4 64,524.7
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWH) 1,899,062 5,544,578 162,026,614
17. Gross Electrical Energy Generated (MWH) 641,777 1,886,558 53,408,082
18. Net Electrical Energy Generated (MWH) 615,364 1,809,178 50,959,435
19. Unit Service Factor 96.4 97.8 81.8
20. Unit Availability Factor.

96.4 97.8 81.8

21. Unit Capacity Factor (Using MDC Net) 100.3 101.5 78.5
22. Unit Capacity Factor (Using DER Net) 97.9 99.1 76.4
23. Unit Forced Outage Rate 0.0 9.1 6.0
24. Shutdowns Scheduled Over Next Six Months (type, date and duration):

None

25. If Shutdown at End of Report Period, Estimated Date of Startup:

N/A