MONTHYEARML20087N9321984-03-30030 March 1984 Forwards Proposed Schedule of Written Responses to Outstanding Issues Presented in Table 1.2 of Draft Ser,Per NRC .Requests NRC Schedule for Issuing Remaining Draft SER Sections in Support of Meetings by 840430 ML20097A0531984-09-0707 September 1984 Forwards Responses to Issues Provided in 840608 Draft Ser. FSAR Changes Described in Responses Will Be Incorporated Upon Acceptance.W/O Encl Project stage: Draft Other ML20134E2721985-08-0707 August 1985 Forwards Status Summaries of Open Issues,Confirmatory Issues & Commitment Issues for Final Draft Ser.Schedule for Issuance of SER Requested Project stage: Draft Other ML20206J1841986-06-23023 June 1986 Informs That Installation of Shunt Trip Attachment on Breakers in Reactor Trip Switchgear Completed,Per SER Confirmatory Item 26 Project stage: Other ML20209J1901987-04-24024 April 1987 Advises That Installation of Shunt Trip Coil Trip Attachment Complete,Closing Out SER Confirmatory Item 26 Project stage: Other ML20213F2351987-05-0707 May 1987 Forwards Response to 860627 Request for Addl Info Re Generic Ltr 83-28,Items 2.2.1,2.2.2,4.3,4.5.2 & 4.5.3.W/3 Oversize Drawings Project stage: Request ML20205S9951988-08-10010 August 1988 Forwards SER Accepting Licensee 831104 & 840330 & 870504 Responses to Generic Ltr 83-28,Item 2.2.1 Re Equipment Classification for All Other safety-related Components Project stage: Approval ML20206G0301988-11-17017 November 1988 Forwards Safety Evaluation Supporting Util 870424 Response to Generic Ltr 83-28,Item 4.3 Re Shunt Trip Design Project stage: Approval 1986-06-23
[Table View] |
Text
-- _
dTr
'A@
M 2NRC-7-094 (412)393 7546 Beaver Valley No. 2 Unit Project Organization Telecopy(412)393 7889 SgGBl April 24, 1987 g
eo Shippingport. PA 15077 United States Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 2055S
SUBJECT:
Beaver Valley Power Station Unit No. 2 Docket No. 50-412 Automatic Reactor Trip Using Shunt Coil Trip Attachment SER Confirmatory item #26 Gentlemen:
The modification to BVPS Unit 2 to install the Shunt Coil Trip attachment is completed.
The modification was completed by field change notice OMWM-10610.
DLC will consider that the completed installation of the Shunt Coil Trip attachment closes SER confirmatory item #26.
If you should have any questions, please call Mr. A. N. Dicesaro at (412) 393-7742.
DUQUESNE LIGHT COMPANY sto J. J. Carey
/
Senior Vice President AND/ijr NR/AND/ITM/26 AR/NAR cc:
Mr. P. Tam, Project Manager Mr. J. Beall, NRC Sr. Resident inspector Mr. L. Prividy, NRC Resident inspector INP0 Records Center NRC Document Control Desk J8 0