Informs That Installation of Shunt Trip Attachment on Breakers in Reactor Trip Switchgear Completed,Per SER Confirmatory Item 26
ML20206J184
Person / Time
Site: Beaver Valley
Issue date: 06/23/1986
From: Carey J
DUQUESNE LIGHT CO.
To: Harold Denton, Tam P
Office of Nuclear Reactor Regulation
References
2NRC-6-067, 2NRC-6-67, TAC-62950, NUDOCS 8606270028
Download: ML20206J184 (1)


Text

_ _ _ . _ _ _ _ _ _ _ _ _ _ _

'Af Duquesm @

8eaver valley No. 2 Unit Project Organtration 2NRC-6-067 SEG ButIdi"9 (412) 643-5200

$ ho port. PA 15077 t 1 June 23, 1986 Mr. Harold R. Denton, Director Office of Nuclear Reactor Reaulation United States Nuclear Regulatory Commission Washington, DC 20555 ATTENTI01: Mr. Peter Tam, Project Manager Division of PWR Licensina - A Office of Nuclear Reactor Requi ation

SUBJECT:

Beaver Valley Power Station - Unit No. 2 Docket No. 50-412 Confirmatory Item No. 26 Gentl emen:

The i nstal l ation of the shunt trip attachment (S TA) on the breakers in the Reactor Trip Switchaear at Beaver Valley Unit No. 2 has been finished. Althouah this eouinment has not yet been turned over to Duquesne Liaht Comoany from the NSSS vendor oraanization, the STA modification was compl eted by FCN OMWM-10610 and is in el ace at Beaver Valley Unit No. 2.

This notification comol et es a confirmatory item request identified in Section 7.2.2.3 of the Reaver Valley Unit No. 2 Safety Evaluation Reoort.

DUQUESNE LIGHT C0dPANY 8

B g62 g g gg8g$312 By . . ,

{ J.'d. Carev PDR Vice President RWF/ijr NR/STA/RTS cc: Mr. Peter Tam, NRC Pro.iect Manaaer Mr. L. Prividv, NRC Resident Insoector 1\o ,