Partially Withheld Secy Paper Re Extension of Environ Qualification 851130 Deadline.Recommends That Commission Issue Encl Order Re Deadline Extension for Plant.W/O Encl
ML20209H963
Person / Time
Site: Sequoyah, 05000000
Issue date: 11/15/1985
From: Fitzgerald J
NRC OFFICE OF THE GENERAL COUNSEL (OGC)
To:
Shared Package
ML20209H821 List:
References
FOIA-86-810, TASK-PIA, TASK-SE SECY-85-335A, SECY-85-335A-01, SECY-85-335A-1, NUDOCS 8702060176
Download: ML20209H963 (2)


Text

__

jaa a'cg

.71 t

i <>*

1 ll) s i,.

,?

November 15, 1985 SECY-85-335A (Affirmation)

For:

The Commission From:

James A. Fitzgerald Assistant General Counsel

Subject:

ORDER REGARDING ENVIRONMENTAL QUALIFICATION EXTENSION OF THE NOVEMBER 30, 1985 DEADLINE FOR SEQUOYAH NUCLEAR PLANT, UNITS 1 AND 2 Discussion:

In accordance with the Commission's staff requirements memorandum on SECY-85-335, the NRC staff drafted an order that would deny the request of the Tennessee Valley Authority for an extension of the November 30, 1985 environmental qualification deadline for Sequoyah Nuclear Plant, Units 1 and 2.

That draft order, which incorporates cur comments as accepted by the staff, is attached hereto.

The Office of Policy Evaluation has reviewed the order and has no objections to its contents.

Recommendation:

Authorize the Secretary to issue the attached order.

'0

^

', r, W / /r-r-

James A. Fitt erald

' ' Assistant General Counsel

Attachment:

Order

Contact:

Paul Bollwerk, OGC 4-3224

>s s

Y 0702060176 870202 PDR FOIA WILLIAMS86-010 PDR g

F s

J' Commissioners' comments should be provided directly to the office of the Secretary by c.o.b. Monday, November 18, 1985.

Affirmation is scheduled for Tuesday, November 19, 1985.