Amend 73 to License NPF-5,supporting Waiver to Tech Spec Requirement Granted Orally on 870126 in Order to Permit Unit 2 to Restart Following Forced Outage That Occurred Earlier Same Day
ML20209G939
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 01/30/1987
From: Muller D
Office of Nuclear Reactor Regulation
To:
City of Dalton, GA, Georgia Power Co, Municipal Electric Authority of Georgia, Oglethorpe Power Corp
Shared Package
ML20209G942 List:
References
NPF-05-A-073, TAC 64460, TAC 64562 NUDOCS 8702050494
Download: ML20209G939 (5)


Text

.

o UNITED STATES g

NUCLEAR REGULATORY COMMISSION n

E WASHINGTON, D. C. 20555

%...../

GEORGIA POWER COMPANY OGLETHORPE POWER CORPORATION MUNICIPAL ELECTRIC AUTHORITY OF GEORGIA CITY OF DALTON, GEORGIA DOCKET N0. 50-366 EDWIN I. HATCH NUCLEAR PLANT, UNIT NO. 2 Af1ENDMENT TO FACILITY OPERATING LICENSE Amendment No. 73 -

License No. NPF-5 1.

The Nuclear Regulatory Commission (the Commission) has found that:

A.

The application for amendment by Georgia Power Company, et al.,

(the licensee) dated January 27, 1987 complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B.

Th'e facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.

The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

2.

Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. NPF-5 is hereby amended to read as follows:

8702050494 870130 PDR ADOCK 05000366 P

PDR 1.

, (2) Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No. 73, are hereby incorporated in the license. The licensee shall operate the facility in accordance with the Technical Specifications.

3.

This license amendment became effective January 26, 1987.

FOR THE NUCLEAR REGUI ATORY COMMISSION f

k.Ad

,Q sm Daniel R. Muller, Director BWR Project Directorate #2 Division of BWR Licensing

Attachment:

Changes to the Technical Specifications Date of Issuance: January 30, 1987 a

de e

_.__,,,,7

.%rw.. - - __.

s_mm._-._.______--.---ae

ATTACHMENT TO LICENS5 AAENDMENT NO ~

FACILITY OPERATING LICENSE NO. NPF-5 DOCKET N0. 50-366 Replace the following page of the Appendix A Technical Specifications with the enclosed page. The revised areas are indicated by marginal lines. The overleaf page is provided for convenience Pages 3/4 7-3 P

l l

l i

PLANT SYSTEMS C

SERVICE WATER SYSTEMS LIMITING CONDITION FOR OPERATION Two independent plant service water system loops and the standby l

3.7.1.2

-l, service water subsystem shall be OPERABLE with:

a.

The river level at the intake structure > 61.7 feet Mean Sea j.

Level USGS datum, t:

b.

Each plant service water system loop containing two OPERABLE

~..

plant service water pumps, and c.

The standby service water system containing one OPERABLE stand-by service water pump.

APPLICABILITY: CONDITIONS 1, 2, 3, 4, and 5.

k i

ACTION:

a.

In CONDITION 1, 2, or 3:

(!..,

1.

With one plant service water pump inoperable, operation may continue and the provisions of Specification 3.0.4 are 1

not applicable; restore the inoperable pump to OPERABLE E:

A:

status within 30 daye or be in a least HOT SHUTDOWN within

[

the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and in COLD SHUTDOWN within the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

i,

  • 9 #.:

2.

With one plant service water pump in each loop inoperable.

t:-

operation may continue and the provisions of Specification

c. p 3.0.4 are not applicable; restore at least one inoperable Lr u pump to OPERABLE status within 7 days or be in at least I

HOT SHUTDOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and in COLD SHUTDOWN

?,

within the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

IL%

3.

With one plant service water system loop inoperable, restore the inoperable loop to OPERABLE status with at least one OPERABLE pump within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or be in at least HOT SHUT-l..

DOWN within the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and in COLD SHUTDOWN within

/-

the following 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

4.

With the standby service water subsystem inoperable

  • I for up to 60 days, provide Hatch - Unit 1 service water cooling to the 1B Diesel generator by verifying OPERABILITY of the Hatch - Unit 1 service water cooling source per Hatch - Unit 1 technical specifications within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. Otherwise, declare the 1B diesel generator inoper-able and take the ACTION required by Specification 3.8.1.1.

'l N

  • The provisions of Specification 3.0.4 are not applicable for the startup from the January 26, 1987 outage.

a.

y.

HATCH - UNIT 2 3/4 7-3 Amendment No. 73

PLANT SYSTEMS l

LIMITING CONDITION FOR OPERATION (Continued 4

'p:

ACTION (Continued) b.

In CONDITION 4 or 5:

I 1.

With up to three plant service water pumps or one plant service water loop inoperable, or Ll 2.

With two plant service water pumps and the standby service i..

water subsystem inoperable, i

5' restore both plant service water loops with at least one pump in each loop and the standby service water subsystem to OPERABLE status within 7 days or declare the core spray system, the LPCI system and the associated diesel generators inoperable i,

and take the ACTION required by Specifications 3.5.3.1, 3.5.3.2 and 3.8.1.2.

s c.

With the river level at the intake structure < 61.7 feet Mean Sea Level USGS datum, declare the plant service water system and the standby service water subsystem inoperable.

['

SURVEILLANCE REQUIREMENTS The plant service water system and the standby service water

?

4.7.1'. 2

-,I subsystem shall be demonstrated OPERABLE:

!4y a.

By verifying the river water level at the intake structure is

> 61.7 feet MSL; p;

3 J

1.

At least once per 14 days when the level is above 63 feet MSL, and 9

N

2.

At least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> when the level is $,63 feet

..?;;

MSL.

4 b.

At least once per 31 days by verifying that each valve (manual, power operated or automatic) servicing safety related equipment that is not locked, sealed or otherwise secured in position, is in its correct position.

c.

At least once per 12 months by verifying the river bottom conditions in the vicinity of the intake structure.

iI d.

At least twice per 12 months by verifying the river stage discharge rating curve in the unit vicinity.

i b

HATCH - UNIT 2 3/4 7-4

,