MONTHYEARML20137B2701986-01-0606 January 1986 Submits Results of Visual Insp of Core Spray Spargers, Associated Piping & Installed Clamping Device,Per IE Bulletin 80-13 & NRC .Approval for Continued Facility Operation Requested Project stage: Other ML20154D5211986-02-28028 February 1986 Discusses Discovery of Addl Shop Weld in Recirculation Sys Loop a During Inservice Insp & IGSCC Mitigation Activities. Util Statements Re Performance of Stainless Steel Piping Weld Exams Conducted During 1984 Outage Require Correction Project stage: Other ML20154J1591986-02-28028 February 1986 Provides Addl Info Re Results of Recent Core Spray Sparger Exam Reported Per IE Bulletin 80-13 in .Extent of Insp Performed on Crack Discovered During Last Refueling Outage & Air Bubble Testing Discussed Project stage: Other ML20154L6451986-03-0606 March 1986 Rev 0 to Evaluation of IGSCC Flaw Indications & Weld Overlay Designs for Ei Hatch Unit 1 - Fall 1985. Maint/Refueling Outage Project stage: Other ML20154M4821986-03-10010 March 1986 Notification of 860318 Meeting W/Util,Southern Svcs & Structural Integrity Assoc in Bethesda,Md to Discuss Results of Insp of Piping & Resolution of IGSCC Indications Project stage: Meeting ML20205M9461986-04-24024 April 1986 Safety Evaluation Supporting Plant Operation in Present Configuration for 18-month Fuel Cycle.Plans for Insp &/Or Mod of Svc Sensitive Austenitic Stainless Steel Piping Sys Requested 3 Months Before Start of Next Refueling Outage Project stage: Approval ML20205M9381986-04-24024 April 1986 Forwards Safety Evaluation Based on Util 860106,0228 & 0310 Submittals Re Insp & Repairs of Recirculation,Rhr,Rwcu Sys Piping,Recirculation safe-ends & Core Spray Spargers During 1985 Outage.Unit Can Be Run for 18-month Fuel Cycle Project stage: Approval ML20211K6381986-06-23023 June 1986 Forwards Comments in Response to NRC 860424 SER Re Repair & Insp of Reactor Coolant Piping Sys & Core Spray Spargers Conducted During Fall 1985 Maint/Refueling Outage Project stage: Other ML20209D4221986-09-0505 September 1986 Forwards Response to Util 860623 Comments on NRC Safety Evaluation Re Insp & Repair of Reactor Coolant Piping Sys & Core Spray Spargers During 1985 Outage.Addl Info Requested Re Qualifications of Southern Co Svcs UT Subcontractors Project stage: Approval ML20213F0191986-11-0606 November 1986 Forwards Response to NRC 860905 Request for Addl Info Re Qualifications of Subcontractors Performing Ultrasonic Exams of Stainless Steel Piping & Components During Winter 1985-86 Maint/Refueling Outage Project stage: Request ML20209A8931987-01-23023 January 1987 Advises of Visual Insp of Core Spray Spargers (CSS) & Associated Piping During Recently Completed Maint & Refueling Outage Per IE Bulletin 80-13.No Cracking of CSS or Piping Between Inlet Nozzle & Vessel Shroud Observed Project stage: Other 1986-03-06
[Table View] |
Similar Documents at Hatch |
|---|
|
Text
Georgia Power Company 333 Piedmont Avenue Atlanta, Georgia 30308 Telephone 404 526-6526 Mailing Address:
Post Offece Box 4545 Atlanta, Georgia 30302 Georgia Power L T. Gucwa tre southem elecFe sp'em Manager Nuclear Safety SL-1835 and Licensing January 23, 1987 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C.
20555 NRC DOCKETS 50-321, 50-366 OPERATING LICENSES DPR-57, NPF-5 EDWIN I. HATCH NUCLEAR PLANT UNITS 1 AND 2 NRC I&E BULLETIN 80-13 Gentlemen:
Pursuant to the requirements of NRC ISE Bulletin 80-13, " Cracking In Core Spray Spargers," please be advised that a visual inspection was performed on the Hatch Unit 2 Core Spray Spargers and associated piping during the recently completed maintenance and refueling outage.
No cracking of the Core Spray Spargers or section of piping between the inlet nozzle and the vessel shroud was observed.
If you have any questions in this regard, please contact this office at any time.
Sincerely, frC~=
L. T. Gucwa GKM/lc c: Georgia Power Company V. S. Nuclear Regulatory Commission Mr. J. P. O'Reilly Dr. J. N. Grace, Regional Administrator Mr. J. T. Beckham, Jr.
Mr. P. Holmes-Ray, Senior Resident Mr. H. C. Nix, Jr.
Inspector - Hatch GO-NORMS Mr. G. Rivenbark, Licensing Project Manager NRC Office of Inspection and Enforcement, Division of Reactor Operations Inspection 1039C fl!