ML20207T412

From kanterella
Jump to navigation Jump to search
Insp Repts 50-424/87-06 & 50-425/87-06 on 870112-16. Deviation Noted:Capacity Ratings of safety-related Batteries Not in Accordance W/Fsar Paragraph 8.3.2.11
ML20207T412
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 02/06/1987
From: Conlon T, Fillion P, Merriweather N, Ruff A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20207T399 List:
References
50-424-87-06, 50-424-87-6, 50-425-87-06, 50-425-87-6, IEB-85-002, IEB-85-2, IEB-86-003, IEB-86-3, IEIN-85-074, IEIN-85-74, IEIN-86-037, IEIN-86-37, NUDOCS 8703230546
Download: ML20207T412 (19)


See also: IR 05000424/1987006

Text

k'

x

. 3

'mafoo

UNITE 2 STATES

>

./

o

NUCLEAR REGULATORY COMMISSION

'

'

[, '

REGION 11

pl

. ;r

j

101 MARIETTA STREET.N.W.

o

j.

i

ATLANTA, GEORGI A 30323 *

'

\\,*****f

L

s

l

',

1*

i

.

Report Nos.: FO-424/87-06 and 50-425/87-06

.

.

,;

-

>

'

Licensee: Georgia-Power Company'

-

P. u. Box 4545

-

Atlanta, GA 30302,

.

Docket Nos.: 50-424 and 50-425

License Nos.:

PPR-108'and CPPR-109

'

~

Facility Name: Vogtle 1 and 2

-

.

,'

<

Inspection Conducted: January 12-16, 1987

.

-

Inspectors:

N /2

8

,)

7

A. B. Ruff

a 7

/Date' Signed

~

c>WY

s/sa m j r

'd-6-97

N. MerrTw' eat er "

'(~

Date Signed

'"

"

/

Ag

ch

$-[-M

Date Signed

P. Fillion

-

"

'

-

,

Approved by

C

/'h88

  1. - 4~ 87

T. E~ Conlon, Section Chief

Date Signed

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This special, announced inspection was conducted in the areas of

electrical items that could impact fuel load which included licensee identified

items, inspector followup items, enforcement items identified on previous

inspections and I/E Bulletin.

Results:

One deviation was identified, paragraph 5.J.

870323 % $ $$$24

PDR

A

PDR

G

..

.

s

L

1'

e

=

Y

%

g

i

REPORT DETAILS

1.

Persons Contacted

'

Licensee Employees

  • R. H. Pinson, Vice President, Construction

,

  • I. Greene, Plant Manager

~ '

>

  • D. Smith, Construction Engineer

O

s

  • C

Hayes, Quality Assur mce Manager

-

  • B. Harbin, Manager Quality Control
  • E. Groover, Quality Assurance site Manager, Construction
  • R. McManus, Readiness Review Program Manger

!'

  • C. McCarley, Project Compliance Coordinator

A. Rogers, Ccmpliance Representative

R. Perry, Corpliance Representative

{

S. Waldrup, Systems Engineer, Engineering Support

D. Edenfield, Electrical Engineer

J. Aufdenkampe, Engineering Supervisor

R. E. Hollands, Compliance Superintendent

H. Thomas, Plant Maintenance

S. Kersteins, Test Supervisor

Other licensee employees contacted included construction craftsmen,

engineers, technicians, operators, mechanics, security force members, and

office personnel.

Other Organizations

S. Pietrzyk, Bechtel Project Field Engineering Electrical Supervisor

R. Valdez, Quality Engineer, Bechtel

B. Woodley, Bechtel, Fire Protection Coordinator

D. Merriwether, Bechtei, Maintenance Engineer.ir )

J. Haratyk, Bechtel Engineer, Project Field E3e(rtrical Operation (PFEO)

5. Hayte, Bechtel Assistant Project Engineer"

D. Morrison, Westinghouse Engineer

i

NRC Resident Inspector

  • H.

Livermore

)l

  • Attended exit interview

S

2.

Exit :nterview

'

'

.,

The inspection scope and findings were summarized on January 16, 1987,

with those persons indicated in paragraph 1 above.

The inspectors described

the areas inspected and discussed in detail the inspection findings.

One

deviation was identified.

No dissenting comments were received from the

licensee.

.

p

g-

u

'

'

e

' .x '

f

2

N

a9

'

Oeviation 50-424/87-06-01, Discrepancy Between the FSAR Section

'

>

'

8.3.2.1.1 and the Actual Values for the Capacity of Safety-Related

'

Batteries, caragraph 5.J.

.

The licensee'did not identify as proprietary any of the materials provided

to or reviewed by the inspectors during this inspection.

t

3.

Licensee Action on Previous Enforcement Matters

s

a!s (Closed) Violation 50-424/86-61-13, Failure to Maintain Control of QC

Accepted Conduit Support CS-7C4-102-068.

The licensee has responded to

this violation by their letter no. GN-1076 dated September 17, 1986.

(The response has been reviewed by Region II staff and was acceptable.

l

A Deviation Report (DR) No. ED13377 was issued to track this deficient

condition.

The conduit support was reworked by craft personnel and

re-inspected by a QC representative.

The DR was closed.

A field

sighting by the NRC inspector confirmed that the support was assembled

properly and fasteners were observed to be tight.

To prevent similar

,

problems a work directive (N0E-01260) was issued to the Chicago Bridge

and Iron (CBI) Site Superintendent.

The directive specially addressed

'

the requirements that CBI personnel adhered to the work scope in the

(.,

Maintenance Work Order (MW0).

In addition, a similar memo, addressed

< \\ ,'

- to all construction personnel, was issued by the Project Construction

Manager.

This violation is closed.

g

b.

(Closed) Violation 50'424/86-31-08, Failure to Follow Procedures for

\\

Protecting Installed Equipment / Components.

This violation was the

result of construction personnel standing and/or walking in a cable

tray section.

The licensee responded to this violation by their

letter, GN-979, dated July 2,1986.

The response was reviewed by

Region II staff and was considered acceptable.

The defective cable

tray section was replaced bnd cables were checked for damage.

It was

determined that no harm occurred to the cables in the damaged tray

section.

Additional inspections were performed on other cable tray

'

6

installations.

As a result of this inspection, minor cable tray

section damage was identified but rework was not required in that the

'

damage was minor and did not affect the function of the cable trays on

cables.

To prevent similar problems, site personnel were made aware of

this violation by memoranda and meetings.

Also, an article was included

in the plant newspaper (Blazer) on May 10,1986.

This article

! discussed the issue and provided the do s and don'ts for cable tray

,

[ protection.

Monthly surveillance were conducted by the Vogtle

3

[

electrical contractor to insure that damage and trash accumulations to

,

,

and in c'able trays were identified and resolved.

The replaced tray

'

'

r

section of the violation was verified to be reworked and several

.\\montnlysurveillanceswereexamined

This violation is closed.

'

I

.

6

>

s

>

,\\

\\

6

s'

_ - - - _ - - . - - - - _ - . - - - _ - - - - - - - - - - - - - - - - . - - - - _ - - - - - - . - . - -

- - . - - - - - . _

- - - - - - - - . - - . - - - - -

'

r

,,

.

3

i

,

,~

,

,

-

(Closed) Violation 50-424/86-95-01, and 50-42S/86-45-01, PFE Failed to

Follow Procedures for Processing FCRs and Inccraorating DCNs into

Design Drawings. The licensee responded to this item in a letter dated

December. 19, 1986.

The inspector reviewed this response for complete-

ness and found it to be acceptable.

Part 1 of this violation concerns

the failure to properly incorporate Design Change Notice (DCN) No. 5-4

(FCR No. E-FCRB-15409) into vendor instruction manual AX3AJ118-24-3.'

To correct this violation, the vendor's stanual was reviewed for unincor-

porated: design changes. The review identified three additional changes

which were not properly incorporated.

Revision 4 of the vendor manual

was issued on August 12, 1986, to correct all discrepancies identified

in the review.

The inspectors reviewed Revision 4 of the manual in the

site drawing control area and found it to be acceptable.

Additionally,

the licensee reviewed the special splice design FCR for impact on

installed hardware.'

This review concluded that splices installed

between issuance of the omitted design changes and their incorporation

were not impacted.

The licensee was in full compliance on August 12,

.

1986.

Part 2 of this violation was attributed to inadequate implementation of

l

the project procedure for processing FCRs.

A review was performed to

"

determine the scope of the problem involving issuing generic NA/NA

'

FCRs.

The review concluded that the total number of open NA/NA FCRs

that did not identify _ an unique component or installation is approxi-

mately 36 out of a total of 1662.

Thus, the cause was attributed to

isolated personnel errors.

The 36 NA/NA FCRs that did not identify a

unique component or installation were corrected by either issuing a

new FCR to supersede the existing FCR and identifying that a CSCN is

required; or for those cases where the construction specification had

already been revist:0 incorporate the generic concern, a new FCR

was issued to supersede le existing FCR.

To prevent recurrence,

responsible engineering personnel were reinstructed in the procedure

requirements for processing NA/NA FCRs.

l

1

d.

(Closed) Violation 50-424/86-95-02 and 50-425/86-45-02, Failure to

Provide Training for Electrical Engineering and QC Staff on the use of

Rai : hem "roducts.

The licensee responded to this item in a letter

dateo Dwember 19, 1986.

The inspector reviewed this response for

completeness and found it to be acceptable.

The major contributor to

this violation was that Project Field Engineers (PFE) approving FCRs

related to Raychem Splices had not received sufficient training to

become proficient in the use of Raychem.

As part of the corrective

action, the licensee had Raychem conduct training for engineers in

GPC-Construction and PFE in 3 and 4 way splice designs.

This training

was documented in letters from Raychem and is maintained at the site

in project file X7BP03.

All special 3 and 4 way splice designs were

reviewed to verify that they met Raychem's "use-range" criteria.

The

review resulted in identifying 8 FCRs which did not meet Raychem

.

-

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

4

,

/

4

'

- cri t'eria."

Field change request no. E-FCRB-18-072 was issued to void

those eight FCRs that were technically incorrect.. A Change Control

Package (No. F10140E, Revision 0) was issued on. September 16, 1986,

- to: correct the identified conditions.

Maintenance Work Orders (MWO)

were issued and rework was completed by October 9,1986.

To prevent

recurrence, Construction Specification X3AR01-E9 has been revised to

require that "special splices not covered by manual - AX3AJ118-24 be

specified by FCR, verified :and approved by engineers, who- have

successfully completed Raychem's special products training."

The

'

licensee has also enhanced the instructions provided on FCRs to now

specify minimum sleeve lengths, shim lengths, and hardware restrictions

-

where required to assure compliance with the seal . lengths and other

criteria by Raychem.

In addition, generic FCRs for 3 and 4 way splices

were incorporated in Construction Specification X3AR01-E9 by E-FCRB-18,

056.

This will. eliminate the need to generate several FCRs for

- splicing on Unit 2.-

Regarding the training of contract QC personnel, the licensee denied

~

this part of the violation.

The response was reviewed and determined

to be acceptable.

However, the licensee did take_ steps to enhance

its training program by adding specific Raychem. training for cable

termination certification requirements.

All QC personnel in termina-

tion inspection have received this training.

All corrective actions have been completed and the licensee is now in

full compliance.

!

e.

(Closed). Violation 424/86-95-03 and 425/86-45-03, Inadequate Inspection

of NSCW Cable Splices. The licensee responded to this item in a letter

dated December 19, 1986.

The inspectors reviewed this response and

determined it to be acceptable.

The cause of the violation was

attributed to isolated cases of human error.

This was concluded after

GPC's. electrical engineering evaluated a sample of 149 QC accepted cable

- splices with only two errors identified that were attributable to QC .

inspection.

However, to prevent recurrence, additional training has

been provided for craft instructors, QC inspectors, and engineers.

The

NSCW cable deficiencies were documented on.0perations Deficicncy Report

Nos. T-1-86-3867 and T-1-86-3868.

Corrective actions were completed by

~ Maintenance Work Orders (MW0s) 18622269 and 18622270.'

The MW0s were

closed on January 14 and January 5, 1987, respectively.

The licensee

is now in full compliance. This item is closed.

f.

(Closed) Violation 50-424/86-109-01, Inaccurate Values for Electrical

Penetration Assemblies (EPA) Loading Calculations.

The licensee

promptly revised the EPA moment calculation sheets when this violation

was identified by the inspector.

The inspectors reviewed the corrective

actions taken during the latter portion of that inspection.

Corrective

actions have been taken and actions to preclude the recurrence of the

condition for Unit 2 have been taken.

This violation is closed.

I

_ - _ - _ -

- _ _

_ _ _ _ _ _ _ _ _ _

_ _ _ _

  • -

.

.

5

g.

(Closed) Unresolved Item (URI) 50-424/86-61-05, Review Commitment to

Regulatory Guide (RG) 1.89 Rev. O versus Regulatory Guide 1.89 Rev.1.

The above item was identified as part of NRC Readiness Review.

RG 1.89, 1974 was committed to by Vogtle in the FSAR and in Design

Criteria (DC) 1000-E prior to Revision 6.

In Revision 6 (August 29,

1985) to DC 1000-E RG 1.89, Revision 1 was inadvertently incorporated

during the revision process.

DC-1000-E has since been revised by

DMCN 1000-E-4 dated July 16, 1986, to reflect RG 1.89, 1974.

The

licensee stated that this change does not impact design / qualification

documents being used to satisfy safety related equipment since the

project is complying with the intent of RG 1.89, 1974 as committed in

the FSAR. This URI is closed.

h.

(Closed) Unresolved Item (URI) 50-424/86-61-10, Review FSAR Commitments

to IEEE 317/1976, Electrical Penetration Assemblies (EPA) for Chemical

Spray.

During an NRC Vogtle Readiness Review Team inspection, a

discrepancy was noted concerning environmental qualification of EPA

with regard to chemical spray testing.

The System Component Evaluation

Work Sheet (SCEW) for Medium Voltage Electrical Penetration Assemblies

was not tested and in the chemical spray section, Note 1 was refer-

,

l

enced.

The justification given in Note 1 of the SCEW sheet was

'

"The effects of chemical spray on seal and electrical integrity is

negligible.

The penetration is equipped with a termination enclosures

on the inboard side which precludes spray impingement."

In response to

NRC concerns, c'uring a separate EQ inspection / audit, the file was

changed to justify qualification of the penetration by a series of type

tests for another similar penetration.

The SCEW sheet now references

Conax Test Report IPS-585.5 and 473 and Note 1 was changed to "6200 ppm

Boron,'50 ppm Hydroxide, PH 9.94."

This item is closed.

i.

(Closed) Unresolved Item 50-424, 425/84-35-04, Discrepancy Punch Lists

for Cable Terminations.

The concern involved the original punch list

for cable terminations in that it failed to docuaent the person who

performed the electrical terminations and the tools used.

In response

to this item, the licensee committed to review their EL-16 Electrical

Termination punch lists versus termination cards for appropriate

documentation.

The licensee reviewed the punch list for twelve

attributes compared to the one attribute identified in Inspection

Report 84-35.

The scope of this review included a check of class 1E

Punch Lists records for their retrievability, completeness, acceptance

requirements, necessary information for tracking, and documentation of

work completed.

Discrepancies identified by the licensee were

documented and closed in Corrective Action Report (CAR) No. E-076 which

was closed on December 17, 1985.

Deviation Report (DR) No. ED-07803

was written to document and disposition those punch list items where it

was indeterminate as to who recrimped the items or what crimp tools

were used in reworking pre-dispositioned items on the punch list.

CAR E-076 identified the root cause was due to an inadequate procedure.

_ _ ___ ___

__

_ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ . .

,

-

-

. .

.

6

Therefore, to prevent recurrence Inspection Procedure No. ED-T-08,

" Cable Termination" was revised to clarify required documentation. All

'

corrective actions. were completed on DR-7803 on December 11, 1985.

Procedure ED-T-08-is currently at Revision 9.

Based on the above, this

liten-is considered closed.

5.

Licensee Identified Items .(Construction Deficiency Reports _ - CDR) 10 CFR 50.55(e)

a.

(Closed) CDR 85-78, Westinghouse -Safety Grade Core _ Exit Thermocouples

for Unit 1 and Unit 2.

A final report concerning the accuracy require-

ment on this _ item was submitted on November 20, 1986, by Georgia Power

Company to Region II.

The report was reviewed and determined to be

acceptable. .The inspectors held discussions with responsible licensee

representative and. reviewed supporting. documentation to verify that the

corrective actions. identified in the report have been completed.

Westinghouse Electric Corporation (WEC) by letters to the NRC dated

May 9,1985 reported a Part 21 item involving the Core Exit Thermo-

couples.

WEC reported that 'during'the performance of environmental

qualification testing of the safety grade core exit thermocouples (T/C)

a significant potential total system error was identified which exceeds

the acceptable values of_ certain functions.

The licensee has modified

the core exit thermocouple Emergency Operating Procedure setpoints

to reflect' the plant specific core exit T/C monitoring system post-

accident induced errors.

The Reactor Vessel Level Indicating System

(RVLIS) . temperature compensation was _ changed to loop Resistance

-Temperature Detectors (RTD). Additional information on.this subject.is

'in Appendix 4A-of the FSAR. MW0s 1-86-8307 and 1-85-14057 were issued

and completed as part of this corrective action.

Based on the above,

this' item is closed.

b.

(Closed) CDR 86-103, Separation of. Field Wires in Isolation Trans-

~

formers (Unit #1).

A final report was submitted on June 12, 1986. The

report has been reviewed and determined to be' acceptable.

The inspec-

tors held discussion with responsible licensee representatives, and

reviewed supporting document- to' verify that the corrective action

identified in the report have been completed.

The CDR addressed the

minimum 6 inch separation distance of -field routed wiring within the

enclosure of - the isolation ~ transformers.

The wiring was initially

ral.ed for 90*C but was changed to wiring rated at 130*C.

This higher

rating cable type (Kapton) satisfies the temperature requirements

under normal and/or secondary short circuit operations.

This item is

discussed more fully in FSAR Table 8.3.1-4 and in Amendment 15 dated

March 7, -1985, in response to NRC Question PSB Q430.61C.

The 6 inch

separation is no longer required since there is no degradation of

the cable in this application.

A sample of MW0s 18615721, 18617744,

18613484 and 18613448, associated with this corrective action were

reviewed. This item is closed.

. .-

.

-

-

_ -

_ - _ - _ _ _ _ _ _ _ -

.

.

.

-7-

~

(Closed) CDR '86-126, Conax Electrical Penetration Assemblies (EPA),.

~

c.

,

Units.:1 and 2. 'During_ Unit 1 containment building structural integrity

<

.

testing ~ it was discovered that air was ' leaking from the. containment

building into- the control building. .GPC notified the NRC of a

potential -deficiency with Conax EPA.

A final report was submitted on

November 312,.1986.

The report- has been reviewed and determined to be

acceptable. . The inspector held discussions with responsibleLlicensee

representatives, and revieweit supporting - documents to ! verify the

corrective actions' specified in the report have been completed.

The

- Conax EPA assemblies for Unit I were repair welded in accordance with

Field- Change Request E-FCRB-686-N.

Work was accomplished on MWO

~

1-86-15881.'

The licensee' stated that Unit 2 penetrations.were checked

and all;were. satisfactory.

The Unit 2 containment building structural

integrity test will be performed sometimes in the future.

This' item-is

closed.

~

d.

.(Closed)_CDR.86-133, Balance-of-Plant / Engineered Safety Features

Actuation' System (BOP /ESFAS( Channel Voltage - Unit 1.

During a Vogtle

design review by GPC, a potential reportable condition was-identified

concerning the above item.

Maintenance / Isolation fuses were installed

in B0P/ESFAS circuit.

These circuits are identified in GPC report.

Since - a . failed fuse (s) in these circuits were not annunicated, an-

undected channel voltage loss could occur with the 30P/ESFAS circuits.

A final report was submitted on December 23, 1986.

The~ report has

'

-

been reviewed and- determined to be acceptable.

The inspector held

'

' discussions with- responsible licensee representatives, reviewed

supporting documentation, and observed representative samples of work

i

to verify that corrective actions identified in the report have been

completed;

The maintenance / isolation fuses have been. replaced with

copper- bus- bars that fit into the fuse clip. his modification still

allows the design intent for maintenance / isolation. of the circuits.

The- modified design retains the 'over current protection as a function

l

of the existing dedicated distribution panel breakers.

The existing

control room annunciation now provider voltage loss detection for the

subject' circuits.

This modification was accomplished by Change Control

'

!

Package (CCP) #B10312E.

A field sighting verified the installation of

the' copper bus bars and MW0s 18623799, A8605069 and A9605070 for this

modification were reviewed.

This item is closed.

!-

e.

(Closed) CDR 86-120, Valcor Solenoid Valves (SV) - Unit 1.

Valcor

i

Engineering Corporation notified GPC that springs in their SV could

fail when exposed .to high temperature reactor coolant containing

>

hydrogen.

NRC issued Information Notice 86-72 of August 19, 1986, on

'

the same subject.

As result of Valcor's notification, GPC notified

a

L

Region'II on July 2,1986, of this potential reportable condition at

[

Plant Vogtle.

After the preoperational test program and subsequent to

the report, another ccndition was encountered associated with the use

'

'

of underrated seal-in contracts (Magnetic Reed Switch) on Valcor SV.

.

- __

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ - _ _ _ _ _ _ _ _ . .-

_ _ _

. _ _

.

,

8

A . final report was. submitted on September 17, 1986.

The report has

been reviewed and determined to be acceptable.

The inspectors held

discussions with responsible licensee representative and reviewed a

sample of supporting documentation to verify that the corrective action

identified in the report have been completed.

GPC determined that two

of the six SV identified had to have their springs replaced. The other

valves were acceptable, as supplied, for their service condition.

The underrated seal-in contact failures were corrected by a circuit

modification.

The modification allows the SV magnetic reed switch to

carry only the- holding (seal-in) current for the interposing Potter and

Brumfield (MDR137-8) auxiliary relay.

The holding (seal-in) current

for the auxiliary relay plus the holding current for SV is now routed

through an additional two MDR 137-8 relay contacts rather than the SV's

magnetic reed switch.

The spring replacement was implemented by Change

Control Package (CCP) B10284J and MW0s 18616225 and 18617902.

The

circuit modifications were specified by Field Change Requests, examples

as follows, EFCB 346N, 347N, 348N, 349N, 351N, 352N, 353N, 356N, 357N,

358N and 361N.

This item is closed.

f.

(0 pen) CDR 86-105, Support of Cable in Vertical Raceways - Units 1 and

2.

During an Independent Design Review (IDR) conducted for Vogtle by a

GPC consultant, an item was identified concerning the support of cable

in long vertical raceway runs.

The NRC raised some questions relative

to this concern and meeting were held on this subject.

GPC letter of

January 9,1987, discusses the engineering evaluation and corrective

actions.

The evaluation of cable supports in long vertical conduit

runs is considered satisfactory.

The evaluation was performed by

walkdown of all conduit as part the Electrical Raceway and Cable

Walkdown Finalization Program (FP-5) and Calculation No. X3CK20.

The

evaluation for cable supports (tie-wraps) in cable trays for long

vertical runs is considered adequate for one cycle of plant operation.

Further evaluation will assess the adequacy of the tie wrap supports,

in their various application, for the long term.

If additional

corrective actions are required, an implementation program will be

established. _GPC stated, in their letter of January 9,1987, that the

long term assessment of tie wrap supports would be provided to the NRC

during the Summer of 1987.

This item remain open pending receipt of

that response and NRC's future assessment.

g.

(0 pen) CDR 86-134, Solid State Protection System (SSPS) Relays -

Units 1 and 2.

On December 4,1986, GPC identified and notified the NRC

of a potential problem associated with SSPS relays.

These relays are

Potter and Brunfield MDR rotary type relays and the relay contacts

.

control the operation or non-operation of other components.

Excessive

i

current (higher than manufacturer's rating) was going through the relay

'

contacts in certain circuit applications at Vogtle.

This excessive

current caused the nylon operating cam to melt sufficiently to prevent

the relays from performing its intended function.

This problem was

_-

- _ _ - _ - _ _ - _ _ _ _ - _ _ - _ _ _ _ _

_ - _ - - _ _ _ - _ - _

__

_ _ _ - _ _ _ _ _ _ _ _

. _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _

w,

,

.

9

,

' identified by a'.'GPC ESFAS - test that is performed. to -insure that

circuits / component operate .and function as intended.

GPC submitted

an interim report ! dated January 10, 1987,- to the_NRC.

This report

describes - a two .part evaluation program regarding the SSPS relays.

The . report has - been reviewed and determined to be acceptable.

The

inspector . held discussions with responsible licensee representative ~

concerning two part evaluation.

The first part-(short. term fix), which-

may, after further evaluation, be satisfactory for the -long term fix

-involved a modification of the affected. circuits.

The modification

put two MDR relays contacts (instead of one) in series and a surge

suppression rectifier across the solenoid valve coil.

This modifica-

tion was shop tested (200 cycles) to confirm that the relay contacts

would interrupt 'the inductive circuit and reset as required. .GPC

stated that NRC would. be notified of the long term assessment by

November 1,1987. - This ; item remains open pending receipt of that'

notification and NRC's inspection and evaluation of GPC assessment.

h.

(Closed) ' Item 424/CDR 86-100, Spliced Instrument Cables Inside the

-Containment and MSIV Areas.

This item was reported by the licensee-

,

under the reporting requirements of 10 CFR 50.55(e) and 10 CFR 21

in a letter dated June 30,- 1986. The irspectors reviewed the response

and determined it to be acceptable.

Tnis condition concerning the

protection of instrument cables inside areas subject to a harsh-

environment was initially . identified in Deviation Report (DR)

,

No. ED-11309.

The DR indicated that no design criteria existed for

'

reconstituting the _ cable jacket for spliced instrument cables in harsh

environments. . A broadness review determined - that this condition

'

could exist inside containment and in the : Main Steam Isolation Valve

.(MSIV) areas of the plant.

This review identified approximately 120

.

instrument cables which are located in the potential accident environ-

ment that required either one end or both ends .of 'the cable to be.

sealed. This is documented on Construction Specification Change Notice

No. 476 to Specification X3AR01, Section E9.

The cables were reworked

and documented on DR-ED-12,274 (The licensee's response dated June 30,

1986, incorrectly identified the DR as #12247,

DR-12,274 was closed

"

out as complete on September 30, 1986, for Unit .1 only.

Action is

still pending for Unit 2.

This item is considered closed for Unit 1.

i.

(Closed) Item 424/CDR 86-124, Raychem Site Designed Electrical Splices.

This item was initially reported to NRC on August 12, 1986 and a final

L

report was submitted on October 9,1986.

The final report has been

reviewed-and determined to be acceptable.

The inspector held discus-

sions with licensee representatives and reviewed supporting documenta-

tion to verify that the corrective actions have been completed. The

condition was caused by the misapplication of the Raychem "use-range"

criteria on three and four way splice designs which were dispositioned

and approved by Project Field Engineers.

The problem was discovered

during a design review conducted by Raychem personnel and an NRC audit.

_

_ - _ _ _ _

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _

~

.

10

A broadness review of three and four way splice designs identified four

additional FCRs to be in error to make a total of nine FCRs involving 80

circuits.

To resolve this matter the licensee undertook the following.

. corrective actions:

(1) FCR #E-FCRB-18072 was issued for those FCRs that were not

technically correct.

Change Control Package No. F10140E was

issued to correct all, with one exception, of the improperly

applied heat shrinkable material on the splices listed in Table 2

of the October 9,1986 response.

The one exception on FCR

E-FCRB-11, 441 was evaluated by Raychem and determined to be

acceptable.

The work was completed by MW0s 18617984, 18617985,

18617986, 18617987, 18517988, 18617989 and 18618730.

(2) Special Raychem training was held at the site during January 1986

and August 1986, for GPC-Construction and PFE engineers clarifying

the implementation of the heat shrink requirements and providing

additional information on the "use-range" criteria.

Attendees who

successfully completed the training were provided certifications

'

from Raychem.

The training records are documented and on file in

the Bechtel Project training file no. X7BP03.

(3) Raychem special splice applications data has been logged into the

project's data files under a new log number AX3AJ118-39.

(4) To prevent recurrence of the condition on Unit 2, construction

specification X3AR01, Section E9 was revised by FCR #E-FCRB-18056

to require that special splice designs be verified by certified

engineers prior to the normal approval cycle defined in the

present project procedure, and to require that the site keep the

certified engineers training records on file.

Based on the

above, this item is closed.

j.

(Closed) CDR 86-118, Flaking of Positive Straps On 125 Volt DC

Batteries.

During a monthly inspection by the licensee of the Class 1E

batteries, metal flakes were observed falling off the straps of the

positive plates.

The flaking phenomenon continued for several months.

It was concluded that, if left uncorrected, the flaking would lead to

,

significant degradation of the battery's capacity.

Each of the four (4) safety-related batteries at Vogtle Unit 1 comprise

59 cells to produce a nominal

125 VDC.

The batteries are lead-acid

i

I

flat plate type with lead plates pasted onto calcium alloy grids.

l

Straps interconnect the plates and the bus bar within the cell jars.

Wclding was used to connect the straps.

The flaking phenomenon

occurred in 37 cells out of 236 total.

. _ _ _ _ .

.

_ _ _ _ - _ - - _ _ _ - _ _ _ _ - _ - _ .

,

-

,:

a

~ -

.

.

11

w

. Analysis by the vendor, C&D Power Systems', determined that the presence

Lof antimony:in the plate to strap weld area caused the flaking problem.

Obviously, antimony should.not have been present, but.it was determined

that'some _1_ead-antimony burning- sticks =were ; inadvertently, substituted -

for lead calcium burning sticks 'during.the manufacturing process.

C&D:

reached this conclusion after analyzing three of the defective. cells in

their laboratory.

C&D . recommended to ~ replace:the defective cells' and -

to maintain visual inspections for flaking. 'Both of these recommenda-

tions have been implemented by .the licensee.

The question of generic

implicationi of this problem has been addressed by the . 0ffice of

Inspection and Enforcement.

While evaluating ~CDR 86-118, the NRC inspectors found it useful to make

-

a chronology of events as follows:

,

Date

Etent

March-June, 1984

Class 1E batteries for the Vogtle plant,

_ '

Unit 1, were manufactured.

'

. December, 1984

Flaking first detected.'

Refer to' Georgia

Power-Compeny Deficiency: Report-

No. T-1-84-336.

July,-1985

Georgia Power Company decided to return

three (3) defective cells to C&D for analysis

of the flaking problem.

Refer to'DR T-1-85-

742.

September 16, 1985

Last time that-any additional flaking ~of the

Class 1E batteries was observed.

April 17, 1986

C&Ds analysis of the three (3) defective

cells was received by Georgia Power Company.

May-20,-1986

NRC first officially informed of the flaking

problem.

< .

June 26, 1986

The licensee's final report was submitted to

l'

the NRC pursuant to 10 CFR 50.55(e).

!

September, 1986

Cells with flaking in Unit 1 batteries were

replaced with cells manufactured for Unit 2

Class 1E batteries, which were being stored by

l

C&D.

Refer Work Order No. 18607664.

'

.

l'

November 1, 1986

Pre-Operational Test (Procedure 1-3PK-02) for

l-

the Class 1E 125 VDC System was begun.

l-

,

January 2, 1987

Procedure 1-3PK-02 was successfully completed.

l

r

I

!

,

,- . - . - , . - , . - < . . , . - - -

y.. - - ,

- , - - - , , , , ,

, . - , - , , . . . - . *

v.--.,--,-,---,--,--.2,,,,,-<,--m

e , .,

c

m,--

s

-

.

__

_

_

.

_

__

_ ___

_-

_

> .

.u

.e

>

.

,

,

12-

-

i,

.l

~

i

About .nine months after manufacture, the fhking problem was first;

-

,

noticed.

Then over a period of nine monN, additional. cells started

'to Lflake,:but after that time - the- number of defective cells remains

i

' fixed. _. The original E Unit 1 cells in which f1aking' has . not been

observed (199 : cells) are now about 31: months . old.

Since e the

l

time: frame for the observed flaking phenomenon was _9 -J18 months, the

.

original non-flaking cells must not have the lead antimony alloy which

causes flaking.

.

A test engineer employed by the licensee stated that over a period of

nine months, the float voltage decreased from 2.24-volts (normal) to as

low as 2.07 volts in cells having the worst flaking problems.

Specific

gravity values. also gradually decreased in the cells having flaking.

'

Whereas the battery maintenance procedure _at the Vogtle plant calls.for--

!

- monthly measuring and recording of all cell' float voltages, battery

,

. degradation would be revealed should the flaking problem recur.

The

4

- maintenance procedure also calls for monthly visual inspection for

4

,

flaking.

~ About seventy cells were inspected by the.NRC inspector for flaking,

~and none of these exhibited flaking.

In light of the above conclusions

-

f and observations,' _CDR 86-118 " Flaking of Positive Straps on 125 Volt DC

Batteries" is closed.

During review of documentation related to CDR 86-118, the'NRC inspector

~ noticed -that the installed capacity . of- each of- the four Class 1E--

batteries is -less than stated in the FSAR.

The values are' tabulated-

below:

.

Installed Capacity

Capacity. Stated

'

(Amp-hours)

in FSAR (Amp-hours)

Channel

2.75 Hr. rate (2)

3.00 Hrs. rate (z)

3 Hrs. rate (3)

A

1584

1674

1947

'

B

1584

1674

1947

-

C

880

911

983

-D

591

590

650

,

Notes:

h

.(1) When discharged from full voltage to 1.8 Volts per cell: in

2.75-hour period at 77*F.

Value determined by manufacturer and

engineer.

Verified by test.

(2) Determined by the NRC inspector for comparison with the three-hour

rate given in the FSAR.

(3) From VEGP-FSAR-8.3.2.1.1

~

=

.

.

.- - - .

. .

-. . - -. - -.

L

'

_.

.

-

.

.

13

Once it was noticed during the inspection that there was a discrepancy

between actual values and FSAR values with respect to battery capacity,

the NRC inspector reviewed the battery sizing calculations and the

pre-operational _ test results.

The pre-operational test did in fact

confirm the installed battery capacity (acceptance test) and demon-

strated the capability of the battery to carry the project load

(service test). The sizing calculations show that the batteries were

sized for the project load and have extra . capacity for load growth,

aging and operation at 55'F. The capacity was determined in accordance

with the FSAR and IEEE 485.

However, it is considered of some

significance by the NRC that the values in the FSAR for the capacity of

the safety-related batteries are in error. Therefore, this matter is

identified as Deviation 50-424/87-06-01, Discrepancy between the FSAR

(8.3.2.1.1) and the Actual Values for the Capacity of the Safety-

Related Batteries.

The following documents were reviewed or referred to in evaluating CDR

86-118:

1.

FSAR page 1.9-100 Commitment to Regulatory Guides

2.

FSAR Section 8.3.2 DC Power Systems

3.

FSAR pages 14.2.8-81 and 82 Pre-Operational Test

4.

Vogtle Unit 1 Technical Specification 3/4.8.2 DC Sources

5.

Regulatory Guide 1.128 Installation Design and Installation of

Large Lead Storage Batteries for Nuclear Power Plants

6.

Regulatory Guide 1.129 Maintenance, Testing, and Replacement of

Large Lead Storage Batteries for Nuclear Power Plants

7.

IEEE Std 484-1975, Recommended Practice for Installation Design

and Installation of Large Lead Storage Batteries for Genersting

Stations and Substations

8.

IEEE Std 450-1975, Recommended Practice for Maintenance, Testing,

f

and Replacement of Large Lead Storage Bau.eries for Generating

l

Station and Substations

9.

IEEE Std 485-1978, Recommended Practice for Sizing Large Lead

Storage Batteries for Generating Stations and Substations

10.

10 CFR 50.55(e) Report, Evaluation of a Potentially Reportable

Condition 125V DC Station Batteries, Transmitted June 26, 1986

l

l

,

.--.

_ _ _ -

.-

---

.. . .

-.

.

-

..

a

14

11.

C&D Power Systems Drawings:

D-841 Discharge Characteristics for LC Cell Model

D-842 Discharge Characteristic for KC Cell Model

D-843 Discharge Characteristic for LCY Cell Model

12.

Calculation by Bechtel Power Corporation, Calc No. X3CF02 Rev. 5

for Class 1E Battery. Systems

13.

Letter by Bechtel Power Corporation, dated December 23, 1985, log

BG34106, transmitting battery amp-br ratings and battery load

profiles

14.

Pre-operational Test Procedure (and results) 1-3PK-02 for Class 1E

125 V DC System for VEGP Unit 1

15.

Letter by Southern Company Services from L. W. Williams, Jr. ,

Manager, Quality Assurance, to J. A. Bailey, Vogtle Project

Licensing Manager, dated June 12, 1986 on " Potential Significant

Deficiency Evaluation C&D Batteries - Flaking Positive Straps"

16.

Letter by C&D Power Systems (Plymouth Meeting, PA) to Bechtel

Power Co. (c/o Georgia Power Co.) dated April 17, 1986 on " Battery

Cells Returned to C&D for Laboratory Analysis of Flaking Positive

Straps"

17.

General Battery Maintenance Procedure 27915-C dated November 20,

1986

18.

Battery Installation and Operating Instruction Manual, Bechtel Log

No. AX3AD01-25-2

19.

C&D Specification Sheets (Catalogue Information) for the LC, KC

and LCY model ce is

20.

IE Information Notice IN 86-37:

Degradation of Station Batteries

21.

IE Information Notice IN 85-74:

Station Battery Problems

22.

M. W. Migliaro, " Sizing Batteries for Generating Stations," IEEE

Transactions (Energy Conversion), Volume EC-1, Number 4,1986,

pp 25-30

23.

J. F. Montalbono and R. V. Casalaina, " Installation and Mainte-

nance of Lead Acid Stationary Batteries for Generating Stations."

IBID pp, 57-61

24.

J. W. Anderson, " Testing of Large Lead Storage Batteries," IEEE

Transactions (Energy Conversion), Volume EC-1, No. 3, pp 76-79.

. - _ - _ _ _ - _ _

-

  1. .

.i~}

t

y

Y

.7. .

.

15

c

k.

(Closed) 'CDR 86-123', GE Re1ay . Type '12NG15AG3. in- DG Panels - Unit 1.

. CDR 86-123 was ~ closed. in consideration of the licensee's final report -

submitted pursuant to 10 CFR 50.55(e).

The report was transmitted

via - Georgia Power Company letter from Mr. P.D. . Rice, Vice President

Vogtle Plant, to Mr. J. Nelson Grace, Region II, Administrator, dated

November -20,1986, log GN-1187. - The = General ' Electric Company . relays

(Model NGA .15AG3) were . wired in reverse polarity by the diesel

- -

generator panel fabricator causing burnout of some of the relays. The

licensee's ! corrective action Lincluded re-wiring, replacement of

resistors, testing and revising of drawings.

1.

(Closed) CDR 86-131, Turb'. Driven Aux. _ Feed Pump Governor Malfunction -

. Units'1 and 2.

CDR 86-131 is clo' sed in consideration of the licensee's

final report submitted pursuant to 10 CFR 50.55(e)._ The report was

transmitted via Georgia Power Company letter from Mr. P.D. Rice, Vice

President .Vogtle Plant, to Mr.

J.. Nelson Grace, Region II Adminis-

.

'trator, dated December 16, 1986,. log GN-1234.

Incorrect springs were

installed in the governor for the turbine driven auxiliary feed pump.

The vendor;' supplied a new governor for Unit 1 which was installed,

tested and operated properly.

Unit 2 will be the same.

m.

(Closed) CDR 86-137, Diesel Generator Exciter Circuitry - Unit 1.

CDR

86-137 is closed in ' consideration of. the licensee's final report

submitted' pursuant to 10 CFR 50.55(e).

The report was transmitted

via Georgia Power Company letter from Mr. P. D. Rice, Vice President,'

Vogtle Plant, Mr. J. Nelson Grace, Region II Administrator, dated

January 10, -1987, log GN-1314.

The Unit 1 diesel. generator exciter

circuitry has been modified to reset (enable) the exciter circuit upon

receipt of an emergency start signal independent of the engine speed

at the time.

Upon reset (enable) of the exciter circuit the field

flashing circuit is enable and if the generator voltage is insufficient

that field circuit is flashed again.

Design drawing changes will be

. issued for the Unit 2 required design changes.

This action will be

tracked by means of Program of Completion of Work (PCW) action item

2B-1614.

This item is closed. for Unit 1.

Unit 2's corrective action

-

will be examined during a future NRC inspection.

n.

(Closed) CDR 86-99, No Calculations for Cable Internal Resistance

During Loca - Units 1 and 2.

CDR 86-99 is closed in consideration of

the licensee's final report submitted pursuant to 10 CFR 50.55(e) and

associated maintenance work reports.

The report was transmitted via

Georgia Power Company letter from Mr. R. E. Conway, Senior Vice

President, to Mr.- J. Nelson Grace, Region II Administrator, dated

November 6,

1986, log GN-1165.

Readiness Raview Finding 22-F16

indicated that cable insulation resistance cas not factored into

-

estimates of instrumentation loop losses.

When the calculations were

performed it was found that some cables had to be replaced and some

instruments adjusted.

The work of replacing the identified cables has

been completed.

A few instrument had to be replaced because it was not

possible to change the range as originally intended.

i

l

l

_ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ .

.-

.

16

6.

Inspector Followup Item (IFI)

a.

(Closed) IFI 50-424, 425/85-10-03, Review Inspection Records that may

.

be - Incomplete Due . to DR Closecut. .The inspectors had two concerns:

(1) that there are not cross references between inspection records and

DRs that permit immediate access to these types of records, and

. (2) when inspecting class 1E items, QC inspectors will sometimes not

proceed with an inspection if many non-conformances or a large

non-conformance is identified.

Thus, when later action is taken to

resolve the DR, the entire inspection procedure is recorded as closed

out, despite the fact that the original inspection may or may not have

been completed.

Results:

Concern No. 1

A similar concern was identified by the licensee's QA organization in

Audit Finding Report No. 790-II, Finding No. 3.

The root cause of the

problem was determined to be an " inadequate program for retrievability

of a single document from large number of like documents." To resolve

this audit finding, a massive backfit effort was undertaken to review

record storage program and to enter all construction DRs into NORMS to

cross reference the DRs to other documents.

This was demonstrated to

the inspector by Operations QA Record's staff. This work is complete

and is being kept curre:st.

Concern No. 2

To resolve this item rework and DR number are recorded on the

inspection document.

IF EE580 cards were previously accepted, dummy

cards with EE580 numbers and any rework or DRs will be generated by EQC

to be filed with the previous card in the vault.

By annotating the

rework and DR numbers on the inspection documents, it assures that all

inspection items have been completed,

b.

(Closed) IFI 50-424, 425/85-20-02, Review the Documentation Require-

ments for Cable C: amps and Entry Fittings.

The concern involved the

lack of QC acceptance criteria for the inspection of clamps holding

armour lock cable on unistruts or other hangers (Specifically, no

torque values are listed in the use of cable clamps mounted on unistrut

for support of armored cable).

To resolve this concern, the licensee

issued FCR No. E-FCRB-10,314 (CSCN 370) which revised Construction

Specification X3AR01, Section E9 adding the following acceptance

criteria:

" Cable clamps mounted on unistrut used for securing armored cable

shall be snug-tight; that is a solid connection obtained using

standard tools applied by a qualified craftsmen"

This item is considered closed.

I

_J

..

..

. . ..

- - ------------_-_____--_ --_-- -

_

-_

.

-

e

,

- ^

.=

-

.

17

c.

(Closed) . IFI 50-424/86-88-04,- Revise Control Fuses-In 4KV Switchgear.

This. item was closed by the NRC inspector because the-licensee .showed .

evidence that the fuses were replaced with ones having the proper

.- rati ng.

-d.

-(Closed) IFI 50-424/86-88-05, Justify Repair Required to Maintain Hot'

Shutdown.

SSER 4,. Section 9.5.1.4, gives justification for allowing .

the repair in question and, therefore, this item is closed.

.

e.

(Closed) IFI/50-424/86-88-06, Revise Repair Procedure 27579-C.

The NRC

inspector determined that the 'NRC's concerns expressed by this . item

have been resolved by reviewing a copy of the latest emergency repair

- procedure 27579-C and inspecting motor control center 1BBF.

This item-

is closed.

f.

(Closed) IFI 50-424/86-16-03, Incomplete Verification on Six Commit-

ments.

This item was identified during the early inspection of the

Readiness Review Module 19 (Elect _rical Supports). . During the review

of items by .the NRC, just prior to issuing the Module 19 Report 86-48,

_

the determination was made that -this finding did not constitute a-

weakness in the licensee's program and with the licensee's commitment

to followup on this condition, this item can now be closed.

g.

(Closed) IFI 50-424/86-46-01. - Review 'the NESC Requirements for

Off-Site Power Source Ice and Wind Loading.

During- the - review of

design commitment for Readiness Review Module #6 (Electrical Equipment)

it was noted that FSAR, when discussing the 230kv and 500kv system wind

and ice loading conditions, did not reference any particular edition-

of the National . Electrical Safety Code when addressing the design

requirement for buses.

Steps have been taken to change the FSAR to

resolve this IFI as follows:

. Revise the last paragraph of FSAR 8.2.1.1 to read:

The transmission line structures of both the- 230 - and 500-kV

systems are designed to withstand standard light loading

. conditions as specified in National Bureau of Standards handbook,

Number 8 (ANSI, C2.2-1960, National Electrical Safety Code).

This item is closed.

-7.

IE. Bulletins

a.

(Closed) IEB 85-02, Undervoltage Trip - Attachments (UVTA) of Westing-

house DB-50 Type Reactor Trip Breakers - Units 1 and 2.

This bulletin

was not applicable to plant Vogtle since it was not an operating plant

at the time the bulletin was issued.

However, Generic Letter 83-28,

" Required Actions Based on Generic Implications of Salem ATWs Events"

-

.. . ..

..

..

_ _ - _

_

_ _ _ _ _ _ _ _ _ _ .

____-

T-

--

$

.

.

.

18

required the licensee to install -the. au'to shunt. modification on the-

reactor. trip switchgear (This is the same modification discussed in the

bulletin). -The shunt modification was accomplished on Vogtle Unit 1 by

Field Equipment Change Order (FECO) No. N-142-BF and was completed on

April 2,.1986.

Nuclear.' Operations has developed test procedures which

independently . test the UVTA' and shunt trip devices.

Additionally,

Plant Vogtle uses type DS-416 reactor trip breakers. . Routine mainte-

nance of the breakers is in accordance with the. commitments made to NRR-

"in a. letter dated: August 1, 1985.

Based on the above,' this item is ~

closed.

b.

(Closed) IEB 86-03, Potential Failure of ECCS Pumps

. Units 1 and 2.

This - outstanding item was closed by the NRC -in consideration of a

Georgia Power Company letter from Mr. P. D. Rice, Vice t resident Vootle

Project, . to Mr. J. Nelson Grace, Region II Administ..itor, dated

November .11, 1986, Log. GN-1173.

This letter states that the Vogtle

plant does not have .the particular piping configuration described in

Bulletin 86-03.