March 5, 1987 Docket No. 50-334 DISTpIRtlTION A. Ton (shn vDocket Filei P. Tam NRC PDR~~ D. Miller Local PDR ACRS (10)

Mr. J. D. Sieber, Vice President PAD #2 Rdg. Gray File Duquesne Light Company T. Novak Nuclear Operation 0GC-Rethesda Post Office Box ~4 E. Jordan Shippingport, PA 15077 B. Grimes J. Partlow

Dear Mr. Sieber:

N. Thompson, DHFT

Subject:

Peaver Valley Unit 1 - Reouest for Additional Information on Generic Letter 83-28 Item 2.2.1 (TAC 53652)

By letters dated November 4 and November 21, 1983, May 10, 1984, March 18 and April P2,1985, you provided information responding to the sub.iect item.

Our' review of your submittals is ongoing. Enclosed are several questions that we developed as a result of the review. Please provide your response within 45 days of receipt of this letter.

This information request affects fewer than 10 respondents; therefore, OMB clearance is not required under PL 96-511.

Sincerely, Peter S. Tam, Project Manager PWR Proiect Directorate #2 Division of PWR Licensing-A

Enclosure:

As stated cc: See next page LAh PM: PAD # f PD: PAD #2 DM J rer PTam:he \ LPubenstein -

3/ /87 3/4/87 3/r/87 870305 rkIdOopy0500o334 P

PDR .

F Mr. J.- D. Sieber Beaver Valley 1 Power Station -

.Duquesne-Light Company ec:

Mr. W. S. Lacey Pennsylvania Power Company Station' Superintendent James R. Edgerly Duquesne Light Company- Post Office Box 891 Beaver Valley Power Station New Castle. Pennsylvania 16103 Post Office Eox'4-Shippingport, Pennsylvania 15007 Mr. Jess T. Shumate, Comissiorer State of West Virginia Department Mr. S. Sovick, Acting Supervisor of Labor.

of Licensing .

1800 Washington Street, East Duquesne Licht Company ~ Charleston, West Virginia 25305 Post Office Pox 4 Shippingport, Pennsylvania 15077 David K. Heydinoer, M.D.

State Director of Health Mr. John A. Levin State Department of Health Public Utility Comission : 1800 Washington Street, East

, Post Office Box 3265 Charleston, West Virginia 25305 Harrisburg, Pennsylvania 17120 Regional Administrator, Region I Gerald Charnoff, Esquire U.S. Nuclear Regulatory Comission Jay E.-Silberg, Esquire 631 Park Avenue Shaw, Pittman, Potts and Trowbridae King of Prussia, Pennsylvania 19406 2300 N Street, N.W.

Washington, DC 20037 Mr. R. Janati

, Bureau of Radiation Protection

Charles E. Thomas, Esquire Pennys1vania Department of Thomas and Thomas Environmental Resources 4

212 Locust Street P.O. Box 2063

, Box 999 Harrisburg, Pennsylvania 17170 y Harrisburg, Pennsylvania 17108 John D. Rurrows, P.E.

1[ Marvin Fein Director of Utilities

. Utility Counsel State of Ohio City of Pittsburgh Public Utilities Comission 313 City-County Building 180 East Broad Street Pittsburg, Pennsylvania 15219 Columbus, Ohio 43266-0573 P.esident Inspector U.S. Nuclear Regulatory Comission

< Post Office Box 298 Shippingport, Pennsylvania 15077 i

i

._,_.,_-....-,_-.m_._.-,...--_._.-,,,__.,_..,,-~,,_m.,__ .m .-.m.._,,_,___m._

7 1

+ ,. .

t

'; . ' Beaver Valles Power 5tation. Unit Hos. i ar.d 2

1. . Iten 2.2.1 - Progree The licensee s response does not confirm that alf saf ety-relatec cosponents are designated as safetv-related on plant documents such as procedures. svstem descriptions. test and asintenance instructions. cperating procedures. and to information handling systems so that. personnel perferning activities that af f ect such saf ety-related components are aware that tries are wori.ing on saf ety-related cor.ponents and are guided by safste-relatec procedures and constraints.
2. . Ites 2.2.1.2 - Inforsation Handling Systes The licensee ~s response has not con (traed that the information handling system includes a Inst of safetv-related equipment and that procedures exist which govern its development and validation.
3. Ites 2.2.1.4 - Management Controls The licensee s response t as not confirmed how manages,ent deters.tnes that the management controls utill:ed to versiv that the pror.edures for preparation, validation and routine utili:ation of the inforaation system hase been followed.
4. Iten 2.2.1.5 - Lesign Verification and Procurement The licensee s response does not confirm that their procurement specifications require that the appropriate design verification and qualification testing be provided by the supplier.