ML20207N942

From kanterella
Jump to navigation Jump to search
Application for Amend to License DPR-16,amending Tech Spec Change Request 126,Rev 1,by Deleting Tech Spec Section 4.5.C.2 Re Primary Containment Integrated Leak Rate Test
ML20207N942
Person / Time
Site: Oyster Creek
Issue date: 10/13/1988
From:
GENERAL PUBLIC UTILITIES CORP.
To:
Shared Package
ML20207N937 List:
References
NUDOCS 8810190490
Download: ML20207N942 (5)


Text

'

0YSTER CREEX NUCLEAR GENERATING STATION PROVISIONAL OPERATING LICENSE NO. OPR-16 DOCKET NO. 50-219 TECHNICAL SPECIFICATION CHANGE REQUEST NO. 126, Rev. 1 Applicant hereby requests the Commission to change Appendix A to the above-captioned license as below and, pursuant to 10CFR50.91, an analysis concerning the determination of no significant hazards considerations is also presented:

1 Section to be changed:

Section 3.5.A.3 and Section 4.5 and the corresponding bases.

2. Extent of change:

The revision to section 3.5. A.3 is actually the addition of 3.5. A.3.6 which is a Limiting Condition for Operation (LCO) concerning plant operations if the drywell airlock is not operable. The revisions made to Section 4.5 reflect the requirements of Appendix J of 10CFR50. This revision also incorporates a change to the paragraph numbers as necessary to correct inconsistencies caused by this and previous revisions. The specific changes requested are as follows: ,

(1) Specificat.cn 3.5.A.3 is modified as follows: Step 3.5.A.3.b is added to create an additional LCO concerning drywell airlock operability.

(2) Specification 4.5, "Applicability", is modified as follows: This section now lists the major system surveillances and tests described in this section.

(3) Specification 4.5, "Objectives', is modified as follows: This section now refers to Appendix J of 10CFR50.

(4) Specification 4.5. A is' modified as follows:

a) Step 1 concerning the pre-operational testing is deleted. Step 1 is no longer relevant, as it applies only to initial (pre-startup) testing of the containment.

b) Steps 2 and 3 are modified to reflect 10CFR50 Appendix J requirements. Part of step 2 has become the new step 1, and the rest of Step 2 along with step 3 are moved to 4.5.C.

c) Step 4 has remained essentially intact and renumbered Step 2.

d) Steps 3 and 4 are added to reflect the requirements of Appendix J. Step 3 establishes a stabilization period orior to beginning the PCILRT and step 4 establishes a verification test to confirm -

b - ibration of instruments.

~

8910190490 891013 PDR ADOCK 05000219 P PDC

n.

e) Step 3 re2ains the test duration requirement.

f) Step 6 is added to reflect the requirements of 10CFR50, Appendix J , Sec tion Y. A.

(5) Specification 4.5.B is modified as follows:

a) Step 1 remains essentially unchanged with minor subscript  ;

changes to parallel variables used in 4ppendit J. '

b) Steps 2 and 3 are modified to reflect the applicable standards.

c) Step 4 is added to establish an acceptance criteria for the verification test in accordance with section !!!. A.3(b) of Appendix J.

(6) Specification 4.5.C is modified as follows:

a) This section is the largest change and adds more restrictions than previously existed. These additions reflect compliance  !

with Appendix J. t (7) Specification 4.5.0 is modified as follows:

a) This /irst section concerning the first refueling outage is deleted, b) The remainder of this stiction is modified to more closely reflect the testing frequency limits as imposed by Appendix J.

(8) Specification 4.5.E is modified as follows:

a) Steps 1 through 4 are taken apart and rearranged, but technically are still stGps 1 through 4 with the addition cf a requirement to use normal valve closures. ,

b) Step 5 is added to define testing of the largest containment penetration, the airlock.

(9) Specification 4.5.F is modified as follows:

a) The heading is changed from "Corrective Action" to "Acceptance Cri teri a" .

b) Step 4.5.F.1 estabitshes the acceptance limits as presented in Appendix J.

c) Step 4.5.F.2 maintains the special case limits estabitshed for MS!Vs at Oyster Creek, d) Specification 4.5.F.3 includes the approved method fo. reduced pressure testing of the drywell airlock (Letter dated flarch 4, 1982, Re: Safety Evaluation Report and Technical Evaluation Report by Franklin Research Conter.)

(10) Specification 4.5.G is modified as follows:

a) The original specification 4.5.G is moved to specification 4.5.H. This is the beginning of the paragraph numbering change, b) The new specification 4.5.G is added to establish c local leak rate testing interval limit in accordance with the referenced standards.

(11 ) Specifications 4.5.H, I, J, K, and L in the proposed change correspond respectively to 4.5.G, H, I, J, and K in the present Technical Specifications. This change is nerely a change to the paragraph numbering system.

(12) Specification L in the present technical specification is deleted.

The proposed change to the Technical Specifications will utilize paragraph L. The rest of specification 4.5. is unchanged with the exception of the corresponding bases.

(13) Several typographical errors have been corrected as follows:

Section Corrections

4. 5.J . 4. b 3.5.A.3.4 changed to 3.5.A.4.a
4. 5.J . 5. b. ( 3 ) 3.5 A.4.a enanged to 3.5.A.5.a 4.5.Q.1.a 124 months changed to 124 days (14) The section 4.5 basis has been revised to eliminate reference to the preoperational containment test pressures since this is no longer applicable.
3. Changes requested:

Replace the old pages 3.5-3 with new pages 3.5-3 and 3.5-3a, and replace the old section 4.5 with the new section 4.5 in its entirety.

4 Discussion:

Appendix J to 10 CFR Part 50 was published on February 14, 1973. On August 7,1975, the NRC requested Jersey Central Power and Light (JCP&L)

Company to rev!ew its containment leakage testing program for Oyster Creek and the associated technical specifications, for compliance with the requirements of Appendix J.

JCP&L responded by letter dated December 24, 1975, which was supplemented by letters dated August 12, 1976, November 22, 1978 and June 27, 1980.

NRC letter dated March 4, 1982 trans.mitted their Safety Evaluction of the Appendix J review for the Oyster Creek Nuclear Generating Station.

Consistent with that safety evaluation, and by latter dated September 25, 1984, General Pubite Utilities (GPU) Nuclear (now the licensee) submitted Technical Specification Change Request No.130 to change caragraph 4.5.F.1.b. After the NRC staff June / July Progress Review meeting with GPUN on July 31 and August 1,1985, the licensee agreed to withdraw Technical Specification Change Request No.130. The witndrawal was confirmed by NRC *etter dated August 26, 1985.

GPUNisno$st. .'tting Technical Specification

.nge Request No.126.

Change No.126 addresses the program which verifies that the leakage from the Primary Containment, both integrated and local, is maintained within specific values as outlined in Appendix J of 10CFR50. The major modifications incorporated in the Integrated Leak Rate Testing Program are the establishment of a stabilization period for internal containment pressure, and a verification test to check the accuracy of leakage detection methods. The leakage limits are also more closely defined in this proposed revision. The new section on "Corrective Action" gives detailed options as to hat may be done to limit leakage during the PCILRT. This specification allows for repairs and local testing of the repairs. It also allows for the re-commencement of the PCILRT without the )

required stabilization period if containment was not depressurized. The testing frequency of three times in ten years, or approximately every 40 months is established and the reference to doing the pre-operational test is eliminated.

The major modification to the LLRT prooram is the modification to the drywell airlock test. The 35 psig peak pressure airlock test required by Appendix J is established, but because of concerns described in NUREG/CR-4398 the frequency of airlock tests at 35 psig will be limited.

When permissible a 10 psig test will be utilized. The acceptance criteria for the LLRT program is established as well as a testing frequency. The change also adds an LCO in section 3.5. The LCO limits plant operation j when t.1e airlock is not operable.

There is no olant configuration change involved with this technical specification change request. The testing described here is merely a '

l surveillance program designed to verify primary containment integrity.

l The program outlined here is desigr.ed to bring the current program in line with the requirements of Appendix J to 10CFR50.

5. Determination l

l The Commission has provided guidance concerning the application of the l standards of 10CFR50.92 for determining whether a significant hatards I consideration exists by providing certain examples as discussed in the l Federal Register on April 6,1983 (48 FR 14870) under the heading i Examples of Amendments That Are Considered Not Likely to involve Significant Hazards Considerations". Example (1) relates to a purely administrative change to Technical Specifications: 1.e., a change to achieve consistency throughout the Technical Specifications, correction of an arre , or a change in nomenclature. Example (11) relates to a change that constitutes an cdditional limitation, restriction, or control not presently included in the Technical Specifications; i.e. , a more stringent surveillance requirement. Example (vii) relates to a change to make a license conform to changes in the regulations, when the license change i results in very minor changes to facility operations clearly in keeping with the regulations, f In this case, each component of the proposed change described above is similar to at least one of the three examples. The change in the numbering schene is clearly in administrative change as described in example (1). The addition of Specification 3.5. A.3.b is consistent witi both examplas (li) and (vii). The modifications and additions made to Specifications 4.5. A through 4.5.0 a'to relate easily to example (ii) in

that a more stringent and comprehensive surveillance requirement is establ'i shed. Example (vii) also relates in that the surveillance program, in the form presented in this proposal, is defined by a regulation to which the licensee is conforming.

The proposed modification to the Technical Specifications will.not involve a significant hazards consideration because operation of Oyster Creek Nuclear Generating Station in accordance with this change would not:

(1) involve a significant increase in the probability or consequences of an accident previously evaluated. This change merely re-defines the leak rate testing program for Primary Containment. This program is designed to ensure that the Primary Containment is able to perform its design function. That function is to contain the energy and the radioactive release of the design basis loss of coolant accident.

Therefore, this change cannot increase the probability or consequences of an accident previcusly evaluated.

(2) create the possibility of a new or different kind of accident from any previously analyzed. It has been determined that, because this revision more clearly establishes the requirements and methods of testing the Primary Containment Integrity and does not involve a change to the containment configuration, this change will not create ce possibility of a new or different kind of accident from any previously evaluated.

(3) involve a significant reduction in a margin of safety. This change has increased the requirer.tnts as established in Appendix J that the primary containment must meet to be considered operable. Therefore, this change will not reduce the margin of safety.

This change reflects t'he requirements of Appendix J to 10CFR50.

,