ML20205A424

From kanterella
Jump to navigation Jump to search
Insp Rept 50-410/86-33 on 860630-0711.Deviation Noted: Failure to Review Results of Preliminary Test MD.0100.A03, Standby Diesel Generator Reliability Test
ML20205A424
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 08/04/1986
From: Briggs L, Eselgroth P, Marilyn Evans
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20205A379 List:
References
50-410-86-33, NUDOCS 8608110365
Download: ML20205A424 (7)


See also: IR 05000410/1986033

Text

.

'=

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Report No.

50-410/86-33

Docket No. 50-410

License No. CPPR-112

Category B

Licensee: Niagara Mohawk Power Corporation

300 Erie Boulevard, West

Syracuse, New York 13202

Facility Name: Nine Mile Point Nuclear Station, Unit 2

Inspection At: Scriba, New York

Inspection Conducted: June 30 -July 11, 1986

Inspectors:

t

/d

j 28

$

L. BMgs, Lead Reactor Engineer

' date'

AN

f~Wu

Y Y5

s

M. Myans, Reactor Engineer

/ dat4

/

Approved by:

)

8- 9' f5

,

P. Eselgroth/Ghief, Test Programs

date

Section,01(DRS

Inspection Summary:

Inspection on June 30 -July 11, 1986 (Report No.

50-410/86-33)

Areas Inspected:

Routine, unannounced inspection by two region based inspec-

tors of licensee action on previous inspection findings, preoperational and

preliminary test results evaluation review, post maintenance test witnessing,

QA/QC interface with the preoperational test program, independent verification

and plant tours and meetings.

Results: One deviation was identified.

(Paragraph 3.3)

NOTE:

For acronyms not defined, refer to NUREG-0544, " Handbook of Acronyms

and Initialisms".

hbh

kDohk

O

G

.

.

DETAILS

1.0 Persons Contacted

Niagara Mohawk Power Corporation

  1. R. Abbott, Station Superintendent
  • G. Afflerbach, Startup Manager
  1. S. Agarwal, Special Projects

B. Bulger, Project Advisory Engineer (SWEC)

  • G. Doyle, Nuclear Quality Assurance (NQA) Operations, Supervising Quality

Engineer

    • J. Drake, Startup and Test (SUT) Special Projects Supervisor (SWEC)
  1. P. Eddy, Site Representaitve NY State PSC
  1. J. Gallagher, Site Licensing Engineer
    • W. Hansen, Manager, NQA
  • A. Kovac, Supervisor, Audits
    • T. Lee, Special Projects
  1. J. McKenzie, Supervisor, Quality Surveillance
  • D. Quamme, Project Director
    • M. Ray, Manager, Special Projects

L. Ringlespaugh, Test Coordinator

L. Schiavone, Test Engineer

    • C. Terry, Project QA manager (SWEC)
  • I. Weakley, Special Projects

Other NRC Personnel

  • W. Cook, Senior Resident Inspector, Operations
  • R. Gramm, Senior Resident Inspector, Construction
  • Denotes those present at the interim exit meeting on July 3,1986.
  1. Denotes those present at the final exit meeting on July 11, 1986.

2.0 Follow-up of Previous Inspection Findings

(0 pen) Unresolved Item (410/86-27-01) - Licensee to include list of de-

ficiencies, the status of the deficiencies, and the supporting closure

documentation in all preoperational test packages. The inspector reviewed

five recently approved preoperational test result packages during this

inspection (See paragraph 3.0).

For three test packages reviewed, the

inspector noted minor documentation errors in the MATRIX of deficiency

reports (DRs) and problem reports (prs) included in the test summary of

each package.

In two of the packages reviewed, the inspector noted that

several DR's and PR's were not annotated as Joint Test Group (JTG) open

action items on the licensee's Master Tracking System (MTS).

This anno-

tation is necessary to ensure that DR's and PR's receive JTG approval

prior to closure. The inspector discussed these findings with a licensee

representative and stressed the importance for adequate tracking of de-

ficiencies.

The licensee representative stated that more effort would

.

.

3

be given to deficiency tracking.

This item will remain open pending

additional review of approved preoperational test results during a sub-

sequent routine NRC inspection.

3.0 Preoperational and Preliminary Test Results Evaluation Review

3.1 Scope

The completed test procedures listed below were reviewed during this

inspection to verify that adequate testing had been conducted to

satisfy regulatory guidance, licensee commitments and FSAR require-

ments and to verify that uniform criteria were being applied for

evaluation of completed test results in order to assure technical and

administrative adequacy.

N2-P0T-29-1, Reactor Recirculation System, Revision 3, Station

Operations Review Committee (SORC) approved on June 12, 1986,

N2-P0T-29-2, Reactor Recirculation Flow Control System, Revision 2,

SORC Approved on May 30, 1986,

N2-POT-71, Uninterruptable Power Supplies - 2VBA*UPS2A/28, Revision

1, SORC approved on May 2, 1986,

N2-POT-100A-1, Division 1 Diesel Generator, Revision 2, SORC approved

on June 25, 1986,

N2-P0T-100A-2, Division II Diesel Generator, Revision 2, SORC ap-

proved on June 23, 1986,

MD.0100.A03, Standby Diesel Generator Reliability Test, Revision 0,

Test Group Manager (TGM) approved on January 14, 1986,

MD.0100.A04, Standby Diesel Generator Air Start Capacity Test, Re-

,

vision 0, TGM approved on March 21, 1986.

The inspector reviewed the test results and verified the licensee's

evaluation of test results by review of test changes, test except-

ions, test deficiencies, test summary "As-Run" copy of the test

procedure, acceptance criteria, performance verification, recording

conduct of test, QC inspection records, restoration of system to

normal after test, independent verification of critical steps or

parameters, identification of personnnel conducting and evaluating

test data, and verification that the test results have been approved.

,

e

_. . _ _ . . .

.r..,,,,_.m_.._.

,

-

._..,___._,___y

-,

,,_._._m

__._ _ _ . .-

r-,-

-_

_

-

,

__

_

.

.

4

3.2 Discussion

N2-POT-29-1

During the review of N2-POT-29-1 the inspector reviewed several Test

Summary entries that involved non intent procedure changes. Test sum-

mary entries involve minor non-intent changes and clarify information

concerning the preoperational test procedure.

The inspector noted

that the changes appeared more appropriately to fit the SAP-106C de-

finition of test exceptions; which are, changes to a procedure that

do not change intent or scope of acceptance criteria. Test exceptions

also require approval by a level III test engineer. Minor changes

can be made by test summary entries which do not require further

management review until the licensee results approval review.

This matter was discusse'; with one of the licensee's test group man-

agers (TGM). The TGM e>plained Sow, when and why a test exception

would be generated. He also infoimed the inspector how the manage-

ment of the startup and test departicent understands and interprets

the SAP-106C definition of what a test exception is and when it must

be used. The TGM explained that the first paragraph of Attachmerit

12.1 of SAP-106C requires a test exception to be used to change a

proced;re when unpredictable or uncontrollable events, system status

changes or field conditions that were not or could not have been in-

cluded in the procedure during its development occur. The test sum-

mary entries noted by the inspector, as explained by the TGM, were

not uncontrollable and would have been foreseen if a different set of

system prints (NSSS supplier vice architect engineer) from those used

to develop the test procedure, had been used.

The inspector agreed

that using the licensee's logic, a similar conclusion would be reached.

The inspector did note that when failures (unforeseen) occurred they

were noted as test exceptions.

The inspector agreed that the licensee was in literal compliance with

SAP-106C and that a clearly auditable trail of events was available

using the test summary.

3.2 Division I and II Standby Diesel Generators

During the review of the preoperational and preliminary test results

for the Division I and II Standby Diesel Generators, the inspector

noted that the results of preliminary test MD.0100.A03, Standby Diesel

Generator Reliability Test, had not been reviewed by the licensee's

Joint Test Group (JTG) although the preoperational test results had

already been jig reviewed and approved. This preliminary test veri-

I

fled diesel ger.erator reliability by means of 69 consecutive valid

starts (35 starts for each diesel generator) as required in Regula-

tory Guide (R.G.) 1.108, " Periodic Testing of Diesel Generator Units

Used as Onsite Electric Power Systems at Nuclear Power Plants",

1

_ - . _

m_

- _ . _ _

,. .

_

_,4

-,-_

y

- , , , _ _ _ _ . - _ . - - , , , - .

. , - , .

, _ , -

- _ _ - _ , . , . . . , , - ,

.

0

5

Revision 1, August 1977, paragraph C.2.a(9). The inspector held se-

veral discussions with the licensee concerning this item. The licen-

see stated that the reliability test is not listed as an acceptance

criterion in NMP-Unit 2 Final Safety Analysis Report (FSAR), Chapter

14, Table 14-2-125, Standby Diesel Generator. The licensee therefore

concluded that the preliminary test does not constitute preoperational

test acceptance criteria and does not require JTG results approval.

However, NMP-2 FSAR Section 1.8, Table 1.8-1 and Section 14.2.7 com-

mit to compliance with RG 1.108 which requires the 69 consecutive

starts (35 per diesel) during the preop program to demonstrate relia-

bility. NMP-2 FSAR Chapter 14 paragraph 14.2.4.1 states that test

results obtained during preliminary testing may be used in place of

retesting during preoperational testing provided the preliminary test

and its results are approved by the JTG.

It should also be noted

that FSAR Chapter 14 paragraph 14.2.12.1 qualifies the table 14 in-

formation as test abstracts with a summary of the acceptance criteria.

3.3 Findi'gl

Failure to JTG review the results of preliminary test MD.0100.A03,

" Standby Diesel Generator Reliability Test" is a deviation (410/

86-33-01) from a licensee commitment made in FSAR Chapter 14, Para-

graph 14.2.4.1.

In addition to the above, several open test deficiencies require

resolution by the licensee.

Deficiency Reports (DRs) 13569, 15353

and 13928 concerning N2-P0T-100A-1 and DR's 15106 and 15122 con-

cerning N2-POT-100A-2 will be carried as an unresolved item (410/

86-33-02) pending licensee resolution and subsequent NRC review.

4.0 Post Maintenance Test Witnessing

4.1 Discussion

The inspector witnessed a portion of the Emergency Diesel Generator

(EDG) No. 3 post maintenance testing being conducted per Interim Oper-

ations Surveillance Procedure N2-0SP-EGS-M001, " Diesel Generator Oper-

ability Test Division 1/2", Revision 1 and Interim Operating Procedure,

N2-IOP-100A, " Standby Diesel Generators", Revision 0. Maintenance was

recently performed on the EDG (No. 1 and 3) air start valve seals as

discussed in NRC IR 50-410/86-31. The testing was conducted to verify

system operability after maintenance.

4.2 Findings

No violations were identified.

.

. .-

.

.

6

5.0 QA/QC Interface with the Preoperational Test Program

The inspector reviewed several recent Nuclear Quality Assurance Surveil-

lance Reports (QASR) regarding different activities of the licensee's

startup department. The following QASR's were reviewed:

--

QASR 86-10442 and 10472, Test Results Review of N2-P0T-100A-1,

" Division 1 Diesel Generator" (review completed June 20, 1986) and

N2-POT-78, " Remote Shutdown System" (review completed June 4, 1986).

The QA inspectors used QA checklist SQA-S-145-86, Revision 1, to

check various attributes of the completed procedure. All QA comments

and open items were adequately resolved.

QASR 86-10522, review of preventive maintenance for crane 2MHR-CRN

--

4, completed on June 17, 1986. The QA inspector found the preventive

maintenance performed to be in compliance with QA checklist

PO-MM-86-001, Revision 0.

- --

QASR 86-10546, surveillance of the performance of preoperational test

N2-POT-61-1, Primary Containment Purge System, conducted on June 25,

1986.

The QA inspector noted that no Field Revision Forms or Test

Exceptions were written during testing.

Several deficiencies were

encountered and documented on deficiency reports (DRs) 20502, 20961,

20962, 20970 and 21022. All attributes of QA checklist SQA-S-090-85,

Revision 1 were adequately satisfied.

5.1 Findings

No violations were identified within the scope of this review.

6.0 Independent Verification

The inspector independently compared the status of DR's and PR's as noted

in preoperational test result packages to the status listed on the lic-

ensee's Master Tracking System as discussed in paragraph 2.0.

7.0 Plant Tours and Meetings

7.1 Plant Tours

The inspector toured various areas of the facility to observe work

in progress, housekeeping, cleanliness controls and status of con-

struction and testing activities.

During one of the tours the inspector noted that a small cable (No.

2SVVNGX037) had been disconnected from the acoustic monitor for

safety / relief valve 2SVV*NBE229. The inspector also noted what

appeared to be three electrical wall penetrations (2WX113N03,

2WC113N02 and 2WK113N01) that did not appear to have a fire seal of

adequate depth. The items were discussed with the licensee.

The

.

. , . , - .


_ _ . . .

,

r -

,. , , - ,

, - - -

-

-

rv

.w

,

e


r

-*-

,--e

-

r-"-

'

_

.

.

7

problem with the disconnected cable had been identified by the lic-

ensee on Deficiency Report (DR) 19968 on May 30,1986.

For the three

penetrations the licensee provided information (Dwg NMP-F-01-03) that

showed the minimum depth of fire barrier' or air barrier foam to be

twelve (12) inches.

The penetrations in question were 42 inches

deep and although foam sealant was not full depth it did contain at

least a 12 inch depth of foam. The licensee also provided the com-

pleted installation and inspection record forms for the penetrations

in question.

7.2 Meetings

The inspector randomly attended the licensee's morning Startup Plan

of the Day meeting during which the current status of preoperational

testing activities and any holds or delays are discussed. Other

items such as surveillance and outage activities are also discussed.

7.3 Findings

No unacceptable conditions were observed.

8.0 Unresolved Items

Unresolved items are matters about which more information is required in

order to ascertain whether they are acceptable, an item of noncompliance

or a deviation. The unresolved item identified during this inspection is

discussed in Paragraph 3.3 of this report.

9.0 Exit Interview

A management meeting was held at the conclusion of the inspection on

July 11, 1986 to discuss the inspection scope, findings and observations

as detailed in this report. An interim exit meeting was also held on

July 3,1986 to discuss preliminary inspection findings (see Paragraph I

for attendees at both meetings). No written information was provided to

the licensee at any time during this inspection.

The licensee did not

indicate that any proprietary information was contained within the scope

of this inspection.