ML20203F782

From kanterella
Jump to navigation Jump to search
Insp Rept 50-298/86-15 on 860421-26.Violations Noted Failure to Provide Tech Spec Required Fire Watches & Failure to Have Procedure That Properly Implements Requirements of Fire Protection Tech Spec
ML20203F782
Person / Time
Site: Cooper Entergy icon.png
Issue date: 07/16/1986
From: Hunter D, Jaudon J, Mullikin R, Murphy M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML20203F737 List:
References
50-298-86-15, TAC-61117, NUDOCS 8607310178
Download: ML20203F782 (25)


See also: IR 05000298/1986015

Text

,.

..

.

- _ _ _ _ _ -

,

.

APPENDIX B

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

NRC Inspection Report:

50-298/86-15

License:

DPR-46

Docket:

50-298

Licensee:

Nebraska Public Power District (NPPD)

P. O. Box 499

Columbus, Nebraska 68601

Facility Name:

Cooper Nuclear Station (CNS)

'

Inspection At:

CNS Site, Brownville, Nebraska

Inspection Conducted:

April 21-26, 1986

Inspectors:

[

7It!rt.

"

'R.' P. Mul fikin,/Pr@ct Inspector, Project

Dste'

-

Section B, Reactor Projects Branch

~7bf N

'

/

K. E. Nurphy,/ Project #Tnspector, Project

Date '

Section B, Reactor Projects Branch

Participating

-

'

in the

.

inspection:

D..Notley, Office of Nuclear Reactor Regulation

f

J. .Kudrick, Office of Nuclear Reactor Regulation

A. Coppola, Brook

en Nat onal Laboratory

'

i

}

K. Parki so , Br

haven

tional Laboratory

i

i

Approved:

4 x/ '

./ .Waudo , tiiief, Project Section A,

Date

l

[Ractor

ojects Branch

'

'

{

L

's

I

f

h)

~

Ni

M

'

D. R. Hunter, Chief, Project Section B,

Date

Reactor Projects Branch

h hh

J

f

l

..

________ - _-_- ___ _

'

.

2

1

I

Inspection Summary

Inspection Conducted April 21-25, 1986 (Report 50-298/86-15)

Areas Inspected:

Nonroutine, announced inspection for implementation of and

compliance to the safe shutdown requirements of 10 CFR 50, Appendix R.

Results: Within the areas inspected, three violations were identified (failure

to provide TS required fire watches, paragraph 3; failure to have a procedure

that properly implements the requirements of the TS, paragraph 3; and failure

to have a procedure that properly identifies, installs, and provides acceptance

l

criteria, paragraph 3.) Five unresolved items are identified in paragraphs 6.b,

6.c, 6.d

7.e, and 8.

!

i

!

i

!.

emn,

_ _ - -

_ m aw a w- w w-

e www wowee=

e-

o w

_ _ -_

_m

e-- n--r m e m w - ~-

, . _ . - . . .

.

- - - - - - _ _

- _ _

_ _ _ - _ _ _ _ _ _ - - - - _ _ - - - - - _ _ _ _ _

_ _ - - -


. _ - . - _ _

-

.

.

.

3

DETAILS

,

1.

Persons Contacted

-

-

NPPD

  • G. R. Horn, Division Manager, Nuclear Operations

.'

  • W. Swantz, Senior Engineer
  • K. Walden, Electrical /I&C Supervisor
  • D. Danielson, Electrical Engineer
  • J. Hackney, Lead Electrical Engineer
  • P. Burrows, Fire Protection Coordinator
  • E. M. Hace, Plant Engineering Supervisor
  • J. M. Meacham, Technical Manager

.

  • V. L. Wolstenholm, Quality Assurance Manager, CNS

-

  • J. V. Sayer, Technical Staff Manager
  • H. T. Hitch, Acting Administrative Services Manager
  • C. R. Goings, Regulatory Compliance Specialist
  • W. Crawford, Maintenance Supervisor

M. Ward, Shift Supervisor

,

W. Schrader, Operations Engineer

L. Bednar, Senior Staff Engineer

M. Span, Assistant to Operations Manager

R. Alexander, Lead Electrician

  • J. Willis, Draftsman
  • D. Fitzgerald, Draftsman
  • F. Alderman, Fire Protection Specialist
  • T. A. Wilson, Mechanical Engineer

..

  • R. Brungardt, Operations Manager

,

!

Other Licensee Personnel

  • S. Burke, Project Engineer, Engineering Planning and Management (EPM)
  • K. Cloran, Electrical Engineer, EPM
  • R. Lemos, Appendix R Project Engineer, EPM

,

A. Morisi, Electrical Engineer, EPH

{

[

  • Denotes those attending the exit interview cor. ducted on April 25, 1986.

The NRC inspectors also interviewed other CNS personnel during the

inspection.

!

,

a-. -

_-

__._ _ .=_.

.

-

.--

-

-

_

-

= -

. - -

.

_ -.

,

.

4

'

2.

List of Documents Reviewed

a.

Letters, Reports, and Procedures

Title

Date

CNS/NRC Record of telephone conversation for clarification of

04/30/84

10 CFR 50, Appendix R Safety Evaluation Report

Cooper Nuclear Station Critical AC Bus Coordination Study

10/85

Volumes I and II

'

Cooper Nuclear Station Critical DC Bus coordination Study

02/86

Volume III

Maintenance Procedure 7.3.1, Revision 9, Protective Relays

11/14/85

Setting and Testing

Maintenance Procedure 7.3.2, Revision 9, Low Voltage Circuit

09/15/85

Breakers, Setting, Testing, and Maintenance

MDC No. 84-7, Appendix R - Fire Protection for the Cable

05/17/84

Expansion Room

MDC No.84-180 Diesel Generators - Addition of Isolation

04/22/85

Switches to Engine Panels

MDC No. 84-93 Fire Dampers:

DC Switchgear Rooms

05/23/84

MDC No. 84-5, Appendix R - Fire Protection for the Cable

06/07/84

Spreading Room

i.

MDC No. 84-8 Control Building Basement Fire Barriers to

03/21/84

Protect 125 VDC and 4160 VAC Cables

MDC No.84-006 Cable Expansion Room - Fire Barrier

05/10/84

f

MDC No.84-004 Cable Spreading Room Fire Barriers to Protect

04/26/84

125/250 VDC and 4160 VAC Cables

'

MDC No. 85-01 Halon'1301 Fire Suppression System for Service

03/19/85

Water Pump Room and Fire Door Addition

MDC No. 85-01, Revision 1, Installation of Fire Doors, Da.mper

04/18/85

and Breathing Sets Associated with the Halon Fire Suppression

System.in S.W. Pump Room

.

j

Appendix R Associated Circuits of Concern

03/86

Selection of Cables Associated with Appendix R Safe Shutdown

11/85

Components, Volumes 1 and 2

/

. - -

- - , -

, . - , - . . - ,

.

. , , . . - - . , - . - - - . - ,

- - - - - - - - - . - . - . , - - - - - -

_ - - , _ _ _ - . , , .

-

'.

.

,

5

Fire Hazards Analysis

09/85

Response to 10 CFR 50, Appendix R, " Fire Protection of Safe

12/02/83

Shutdown Capability - Volume III"

Appendix "R" Alternate Shutdown System Basis of Design

12/85

Document, NED BODD No. 85-02, Revision 0

NRC letter to CNS, Safety Evaluation for Appendix R to

04/16/84

10 CFR Part 50, Items II.G.3 and III.L, Alternate or

Dedicated Shutdown Capability

CNS letter to NRC, Appendix R - Schedular Exemptions; Request

06/07/85

for

NRC letter to CMS,' Outstanding Fire Protection Modifications

08/21/85

CNS letter to NRC, Appendix R - Analysis of Cooper Nuciear

05/09/85

Station

,

Procedure 5.4.1, Revision 19, Diesel Fuel Oil Transfer Pump

10/03/85

Repair

Procedure for Battery Charger and Exhaust Fan Repair

Current

Revision

" Fire Protection of Safe Shutdown Capability" CNS response to

06/28/82

10 CFR 50, Appendix R, Volumes I and II

CNS Emergency Procedure 5.4.1 " General Fire Procedures,"

09/30/85

Revision 19

CNS Emergency Procedure 5.8 " Emergency Operating Procedures"

Current

E.0.P. Sections 1 through 12

Revision

NRC letter to NPPD re Exemption Requests

09/21/83

" Report on Core Uncovery due to Depressurization" - for CNS

07/15/85

by EPM

" Report on emergency lighting, alternate shutdown equipment

03/10/86

accessibility and portable communications systems" - for CNS

by EPM

-

Maintenance Procedure 7.3.12, Revision 3, Emergency Lighting

03/11/85

Units Inspection

CNS Procedure 0.16, Revision 1, Control of Fire Doors

12/19/84

.

.

.

6

CNS Procedure 0.23, Revision 0, Fire Protection Plan

08/08/85

CNS Procedure 2.2.30, Revision 24, Fire Protection System

10/17/85

CNS Procedure 2.2.72, Revision 4, Smoke, Temperature, and

02/29/84

Flame Detection

CNS Procedure 2.3.2.37, Revision 8, Fire Protection -

02/20/84

Annunciator 1

CNS Procedure 2.3.2.38, Revision 5, Fire Protection (Manual

05/02/85

Pull Alarms) - Annunciator 2

CNS Procedure 2.3.2.39, Revision 5, Fire Protection

01/16/86

(Sprinkler System Actuation and CO ) - Annunciator 3

2

CNS Procedure 2.3.2.40, Revision 10, Fire Protection -

10/30/85

Annunciator 4

CNS Procedure 2.3.2.40, Revision 5, Fire Protection -

03/27/86

Annunciator 5

CNS Procedure 2.3.2.54, Revision 0, Pump House Fire Detection

04/17/84

Panel FP-PNL-5

CNS Procedure 2.3.2.55, Revision 0, Pump House Local Control

04/17/84

Panel FP-PNL-4

CNS Procedure 3.6.1, Revision 2, Fire Barrier Seal Activities

04/10/86

Control

CNS Procedure 5.~4.2, Special Fire Procedures (5.4.2.1 thru

5.4.2.28) (Reviewed Selected Procedures)

l

CNS Procedure 6.4.5.1, Revision 38, Fire Protection System

11/07/85

Annual Inspection

CNS Procedure 7.10, Revision 4, Flame Process Control

10/18/85

b.

Drawings

l

Title

Date

!

Flow Diagram - Residual Heat Removal System No. 2040,

02/11/74

l

Revision 13

Flow Diagram - Reactor Core Isolation Coolant System

04/15/74

No. 2043, Revision 14

l

l

Flow Diagram - Reactor Building - Main Steam System

03/05/78

No. 2041, Revision 21

.

.

T

7

,

Flow Diagram - High Pressure Coolant Injection System

04/15/85

No. 2044, Revision 16

Flow Diagram - Core Spray System No. 2045, Revision 18

01/24/75

' Flow Diagram - Reactor Building - Service Water System,

-- -- 74

Revision 20

125-DG2-1,-125 Volt DC Panel DG2-1 Fuel Oil Booster Pump

11/15/85

125-DG2-7, 125 Volt DC Panel DG2-7 DG2 Exciter Panel

11/15/85

125-PNL-AA2-10, 125 V. DC PNL AA2-10

11/20/85

250-SWGR-18-1 (Rec.), 250 V. DC SWGR 1B-1 (Rec.)

03/05/86

250-SWGR-1B-4 (Rec.), 250 V. DC SWGR 1B-4 (Rec.)

03/05/86

4160-1G-SWP1B(1), 4160 SWGR 1G - Breaker SWP-1B

10/04/85

4160-1G-SWP1B(2), 4160 SWGR 1G - Breaker SWP-1B

10/04/85

4160-1G-SWPIB(3), 4160 SWGR 1G - Breaker SWP-1B

10/04/85

I

4160-1G-RHRP10(1), 4160 SWGR 1G - Breaker RHRP-10

10/04/85

4160-1G-RHRP1D(2), 4160 SWGR 1G - Breaker RHRP-1D

10/04/85

4160-1G-RHRPID(3), 4160 SWGR 1G - Breaker RHRP-10

10/04/85

4160-1G-SS1G(1) (Rec.), 4160 Volt Bus 1(G) (Rec.)

09/20/85

4160-1F-SS1F(1) (Rec.), 4160 Volt Bus IF (Rec.)

09/20/85

480-1F-MCC-L, 480 V. Bus IF - Feeder MCC-L

07/24/85

480-1F-MCC-L (Rec. ), 480 V. Bus IF - Feeder MCC-L(Rec. )

09/20/85

240-DP15-1A-1, DP15-1A Circuit 1

08/27/85

3A, Revision 3, Cooper Nuclear Station Appendix "R"

04/01/86

Circuit Separation

3B, Revision 3, Cooper Nuclear Station, Appendix "R"

04/01/86

Circuit Separation

4A, Revision 2, Cooper Nuclear Station, Appendix "R"

04/01/86

Circuit Separation

4A, Revision 2, Cooper Nuclear Station Appendix "R"

04/01/86

Circuit Separation

' , :. .

~

. .,..

.

,

..

,

.

,'

.

8

'

_

48,. Revision 2, Cooper Nuclear Station, Appendix "R"

06/17/86

Circuit Separation

7A, Revision 3, Cooper Nuclear Station, Appendix "R"

04/01/86

Circuit Separation

78, Revision 3, Cooper Nuclear Station, Appendix "R"

04/01/86

Circuit Separation

8A, Revision 3, Cooper Nuclear Station, Appendix "R"

04/01/86

Circuit Separation

88, Revision 3, Cooper Nuclear Station, Appendix "R"

04/01/86

Circuit Separation

CNS-1000, Revision 1, One Line Diagram 125 VDC Alternate

03/06/86

Shutdown

CNS-1001, Revision 1, Loop Diagram HPCI - Pump Discharge

03/06/86

Pressure Indication

CNS-1002, Revision 1, Loop Diagram HPCI - Turbine Steam

03/06/86

Inlet Pressure

CNS-1003, Revision 1, Loop Diagram HPCI - Pump Suction

03/06/86

Pressure Indication

CNS-1004, Revision 1, Loop Diagram HPCI - Turbine Speed

03/06/86

Indication

CNS-1005, Revision 1, Loop Diagram HPCI Turbine 125V DC to

03/06/86

Register Box

CNS-1006, Revision 1, Loop Diagram HPCI Flow Cont. & Ind.

03/06/86

CNS-1007, Revision 1, Loop Diagram RHR Flow Indication & Loop

03/06/86

CNS-1008, Revision 1, Loop Diagram Reactor Vessel Level

03/06/86

'*

-150" - +60"

CNS-1009, Revision 1, Loop Diagram Reactor Vessel Level

03/06/86

-100" to +200" H O

2

CNS-1010, Revision 1, Loop Diagram Suppression Chamber Water

03/06/86

Level

~

CNS-1011, Revision 1, Emerg. Condensation Storage Tank 1B

03/06/86

Level Indication

CNS-1012, Revision 1, Loop Diagram Torus Temperature

03/06/86

Indication

.

.

.

9

Dwg. 3144, Revision 3, Reactor Building - El. 931'-6"

Current

Lighting Plan

Revision

3.

Fire Protection / Prevention Program

This inspection was conducted to determine that the licensee was

implementing a program for fire protection and prevention in conformance

with regulatory requirements and industry guides and standards.

The NRC inspector reviewed the documentation constituting the licensee's

approved fire protection program.

These documents are referenced in

paragraph 2 of this report.

The licensee's program provides for the

control of combustible materials and housekeeping for reduction of fire

hazards.

Administrative controls have been established to handle disarmed

or inoperable fire detection or suppression systems; provide for

maintenance and surveillances on fire suppression, detection, and

emergency communications equipment; establishes personnel fire fighting

qualifications, training and fire protection staff responsibilities;

provides fire emergency personnel designations as well as plans and

actions; and, establishes controls for welding, cutting, grinding and

other ignition sources.

The NRC inspector conducted a walkdown of the fire suppression water

system and verified that it was operable as required by technical

specifications.

A tour of accessible areas of the plant was conducted to verify that

standpipe and hose stations were operable; adequate portable fire

extinguishers were provided at designated places in each fire zone.

Access to fire suppression devices is not being restricted by any

materials or equipment.

Inspections and maintenance on all fire

suppression equipment or devices were verified as being satisfactorily

performed, and the general condition is satisfactory.

The NRC" inspector also observed the condition of fire barrier penetrations

during-this tour.

The closing mechanism for the fire door separating the

turbine building from the control room access corridor was found to be

weak.and would not always provide for positive latching of the door.

This

was brought to the attention of a licensee representative and action to

l

fix this door was initiated.

Locking mechanisms were found removed from

'

the access doors to the auxiliary relay room, reactor protection system

room 1B and room 1A in the control building, elevation 903'-6".

The NRC

inspector asked the licensee representatives if a continuous fire watch

had been established, since the removal of these mechanisms compromises

the fire rating of the doors.

The NRC inspector was informed that the

licensee considered the roving fire watch adequate.

This fire watch had

been established during re-work in this area to complete modification

!

commitments under the Appendix R exemption requests.

The NRC inspector

informed the licensee that the applicable technical specifications,

,

l

paragraph 3.19.8 does not recognize any other condition and only a

!

continuous fire watch satisfies the technical specification LCO.

The

.

I

.

.

,

,

.

10

licensee posted a continuous fire watch.

Failure to establish a

continuous fire watch is an apparent violation of technical

specifications.

(298/8615-06)

A review of the licensee's Procedure 0.16, " Control of Fire Doors"

revealed that the procedure defines various categories of doors and

further describes the requirements for posting or not posting a fire watch

or security guard on the various door categories.

CNS Technical

Specifications LCO 3,19 states that it applies to the integrity of all

fire barrier and fire wall penetration fire seals and that "A.

Fire

barrier and fire wall penetration fire seals integrity shall be

maintained. ", and "B.

If the requirement of 3.19.A cannot be met, a

continuous fire watch shall be established on at least 1 side of the

penetration within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />." The bases for 3.19 states that, " Fire barrier

penetration seals include cable penetration barriers, fire doors, and fire

dampers." Failure to have a procedure that properly implements the

requirements of the technical specifications is an apparent violation.

(298/8616-07)

In the same corridor on the same elevation, fire door H109 was found to

have a door to floor gap in excess of the 3/4" allowed by NFPA-80.

The

inactive side of this double door was installed by work item No. 86-0692

dated February 12, 1986.

A review of this work item disclosed that it

contained no acceptance criteria, did not define an installation

tolerance, was not identified as a technical specification item, was not

identified as a fire penetration and was identified as non-essential.

This is a 3-hour rated fire door for DC switchgear room 18.

Failure to

have a procedure that properly identifies, installs, and provides

acceptance criteria is an apparent violation of 10 CFR 50, Appendix B,

Criterion V.

(298/8615-08)

A review of surveillance records verified that the fire detection and

suppression systems currently meet the technical specification operability

testing requirements and that they are being conducted at the required

frequencies.

Fire brigade training and drill records were reviewed as well as selected

personnel records.

Individual qualifications and training were found to

meet CMEB 9.5.1 requirements. A review of the current roster of qualified

fire brigade members verified that brigade composition is in accordance

with technical specification requirements.

4.

Emergency Lighting System

The NRC inspector examined.the emergency lighting system required for safe

shutdown.

Section J of. Appendix R requires that emergency lighting units

with at least an 8-hour battery power supply be provided in all areas

needed for operation of safe shutdown equipment and in access and egress

routes thereto.

The licensee had not installed, at the time of this

-inspection, all of the emergency lighting units required for the operation

'

.- --

--

.

- - - - - - - - - - . --.

.- -

.-.

.-

- -

- - - .

. _ _ . _ _

__ _ ..

'

,

.

11

of safe shutdown equipment in the event of a fire that destroys and forces

evacuation of the control room. The NRC inspector did not inspect for

adequacy of emergency lighting in these areas.

The NRC inspector reviewed the maint'enance procedure for checking

emergency lighting units.

This procedure (7.3.12, " Emergency Lighting

Units Inspection," Revision 3, March 11,1985) outlines the requirement to

check the operation of the units with the test switch and check the

terminals for corrosion.

It was found that there did not exist a

procedure to periodically check the lamps for adequate alignment.

Although Appendix R does not specifically state this as a requirement it

is recommended that the licensee consider incorporating this item into a

procedure.

Also reviewed was the manufacturer's data for the emergency lights.

The

Exide Electronics 1983-84 emergency lighting catalog shows that for Exide

Model F-100 units, two 12 watt lamps will provide at least 85 percent

illumination after 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.

The NRC inspector had the licensee perform an

8-hour battery service test on two lighting units (R-38 and R-42) located

in the reactor building on elevation 931'-6".

The inspector performed a

visual check of the. illumination at the beginning and end of the test.

There was no discernible reduction in illumination after 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> of

continuous discharge.

5.

Post-Fire Safe ~ Shutdown Capability

~

a.

Systems Required for Safe Shutdown

The systems required for safe shutdown as essential are listed in the

-

SER of April 16, 1984, and the licensee's submittals (see

paragraph:2), but neither of these documents detailed the systems

required by fire area or zone.

l

The.following paragraphs list the systems used for safe shutdown by

fire areas or zones according to the current analysis (dated

i

April.1;8, 1986) produced by the licensee's consultant (EPM, Inc.).

(1) Reactivity Control

Upon detection of a disabling fire, the control rods will be

inserted using the scram switches in the control room, or

automatically by the reactor protection system (RPS) upon loss

of offsite power.

This is true for a fire in any fire zone or

area.

If neither action occurs, scram can be accomplished

outside of the control room by opening the RPS MG set output

breakers.

(2) Reactor Coolant Inventory Control and Decay Heat Removal

'

For most fire areas or zones, (which do not require alternate

shutdown), the reactor core isolation cooling (RCIC) system will

,

f

4

-

, - - ,

_

_ _ _ __- .

w.

_

_y

_

. , , _ , , , , _ _ _

_ ._

. . , _ _ . _ -

,y.

,

_

.

.

12

..

,

,

,

4~

be used.for. reactor coolant make-up. The source of water will

be both the emergency condensate storage tanks (2), and the

-

-suppression pool. The capability to switch suction sources will

be maintained throughout hot shutdown.

-

,

For five fire areas, there is no high pressure system available

.

for reactor make-up, and a combination of automatic

-

depressurization system (ADS) and low pressure injection will be

~

used.

For fire area RB-A, the low pressure coolant injection

-

'(LPCI) system (train A) will be used for coolant make-up and the

source of water will be the suppression pool.

For fire areas,

CB-A, CB-C, RB-E, and RB-I, the core spray system will be used

-

for coolant make-up and the source will be the suppression pool.

High pressure coolant injection (HPCI) is not used for coolant

inventory control except for those areas requiring alternate

shutdown.

For all fire areas, decay heat removal is accomplished by

suppression pool cooling using either train A or B of the

residual heat removal (RHR) pumps, and a minimum of one vessel

to the suppression pool as steam via the RCIC exhaust or the ADS

system.

This method of decay heat removal will be continued

until the shutdown cooling mode of the RHR can be placed in

service (~50 psig in the reactor vessel).

(3) Process Monitoring

For fires requiring control room evacuation, the following

instrumentation will be provided on the alternate shutdown

panel:

o

Reactor Pressure (HPCI Steam Inlet)

o

Reactor Level

o

Torus Level (suppression pool)

o

ECST Level (condensate storage)

o

Torus Temperature (4) (suppression pool)

Diagnostic instrumentation for the HPCI system, including HPCI

speed, water suction and discharge pressure, and HPCI flow will

also be available at the alternate shutdown panel.

(4) Support System and Equipment

For the safe shutdown systems described above, the following

, support systems are required and will be available:

o

Diesel Generator - at least one of two for RHR and SW pump

power.

-

-

.,

.-

.

.

-_ _

..

. -

. - - .

-_. -,

,

._

v,

'

'

.

13

o

Service Water - at least one of four pumps for diesel

engine cooling, REC (reactor building closed cooling

system), and RHR heat exchanger.

o

REC - at least one train for RHR pump cooling and room

coolers, or as an alternative the REC /SW intertie, allowing

service water to be used instead,

o

Emergency switchgear

one train for pump power.

o

D.C. batteries and battery charger - one train.

(5) Cold Shutdown

Cold shutdown is achieved by operating the RHR system in the

shutdown cooling mode once the reactor pressure has been reduced

to 50 psig.

The present EPM study shows that the RHR suction

valves (from the vessel) could fail to open on demand for

certain fires.

In this case, cold shutdown will be achieved by

filling the reactor vessel with water and discharging the water

to the suppression pool (torus) via the ADS valves.

Thus, a

closed loop is created, transferring heat to the suppression

pool.

One train of core spray or one RHR pump is used for this

purpose, and one RHR pump / heat exchanger is operated in the

suppression pool cooling mode to transfer the heat to the

ultimate heat sink which is the Missouri River.

b.

Area Compliance with Appendix R,Section III.G.2

Although a general tour of all available fire areas pertaining to

safe shutdown was conducted by the team, both together and

individually, no conclusions can be reached regarding area compliance

until the licensee's analysis is completed.

At the time of the inspection, the licensee was in the process of

completing the associated circuit analysis.

To determine the

depth / effectiveness of the ongoing analysis, a limited random sample

of cables was examined in the field and compared to the analysis

data.

Sample results were as follows:

Fire Area IS-A, Service Water Pump Area, contains the following

redundant safe shutdown components:

Safe Shutdown

Equipment

Division

Type Cable

Cable Number

Service Water Pump

I

Power

H401

SW-P-A

.

-

- - ,

-

-

,-,i

7-

, -

-

-

r

-~T

.

.

14

.-

Service Water Pump

II

Power

H521

SW-P-B

Service Water Pump

I

Power

H411

SW-P-C

Service Water Pump

II

Power

H531

SW-P-D

The loss of cables H401, H521, H411 and H531/will cause a loss of

service water.

The pumps and cables are not in compliance with the separation

requirements of Section III.G.2. The associated circuit analysis

data documents the status of the cables and the existence of an

exemption from the noncompliance.

Fire Area RB-J, SWGR Room IF, and Fire Area RB-K, SWGR Room 1G,

contain cabling for the following redundant safe shutdown components:

Safe Shutdown

Equipment

Division

Type Cable

Cable Number

RHR Fan Coil Unit

I & II

Control

MK 119

FC-R-IJ

RHR Fan Coil Unit

I & II

Power

MS 101

FC-R-1H

These cables are located in both Fire Areas RB-J and RB-K.

Fan coil

unit FC-R-1H has start permissive contacts in RHR-P-B and RHR-P-D

breaker close circuits.

Fan coil unit FC-R-1J has start permissive

contacts in RHR-P-A and RHR-P-C breaker close circuits. The loss of

control cable MK 119 and power cable MS 101 will cause a loss of

remote starting of all redundant RHR pumps.

Cables MS 101 and MK 119

are not in compliance with Section III.G.2 separation requirements.

The associated circuit analysis data documents the status of

cables MS 101 and MK 119. Resolution is pending.

Fire Area CB-A, RHR Service Water Booster Pump and Service Air

Compressor Areas, contains cabling for the following redundant safe

shutdown components:

Safe Shutdown

Equipment

Division

Type Cable

Cable Number

Service Water Pump

I

Power

H401

SW-P-A

__

_

, _

___ _ __

.

-

,

.

- _ - .

. -- -

.

~.

._.

. - .. -

-

,

,

.

,

j

15

Service Water Pump

II

Power

H521

SW-P-B

Service Water Pump

I

Power

H411

SW-P-C

j

Service Water Pump

II

Power

H531

SW-P-D.

,

Diesel Generator'

I

Power

DG1A, DG1B

DG1

Diesel Generator

II

Power

DG37A, DG37B

~

!

The loss of cables H401, H521, H411 and H531 will cause a loss of

service water.

The loss of cables DG1A, DG18, DG37A and DG378 will

'

cause a loss of safe shutdown emergency power. These cables are not

in compliance with Section III.G.2 separation requirements.

The

associated circuit analysis documents the status of the cables and

the existence of an exemption from the noncompliance.

'

Fire Area CB-8, Battery Room IB, contains cabling for the following

!

p

redundant safe shutdown components:

Safe Shutdown

!

Equipment

Division

Type Cable

Cable Number

Service Water Pump

I

Power

H401

'

i

SW-P-A

i

Service Water Pump

II

Power

H521

i

SW-P-B

'

' Service Water Pump

I

Power

H411

SW-P-C

!

Service Water Pump

II

Power

H531

SW-P-D

~.

.'

7

.

_

Diesel. Generator

I

Power

DG1A, DG1B

'

f

DG1

7

(DieselGenerator

II

Power

DG37A, DG37B

,DG2,

"

"

-

,

e

,

~

.; Fire Area CB-B was found to be in compliance with the separation

.

requirements of Section III.G.2.

"

-

- '

~

. .

i

l

-_---,...-..-.___.m..

_ _ _ _ _ , _ . _ _ _ . _ . . _ . _ _ _ , _ _ _ _ _ .

. . _ ,

. , _ . _ , , , . _ .

_ _ _ , . . - , . .

.

.

.

16

c.

Alternate Shutdown

-

R

(1) Areas Requiring Alternate Shutdown-

The areas requiring alternate shutdown have not changed due to

the new EPM analysis. They include the following:

o

Control Room (Fire Area CB-D)

-

CableSpreadingRoom(FireAreaCB-D]

o

o

Cable Expansion Room (Fire Area CB-D,

o

Aux. Relay Room (Fire Area CB-D)

Computer Room (Fire Area CB-D)-

o

Reactor Bldg. 903' Elev. , N.E. corner (Fire Area RB-FN)*

o

In three of these areas, (noted by asterisks above), cabling for

both trains of diesel generator power (output), and both trains

of service water pump power are present. These cables, and a

high percentage of all other cabling at Cooper are run in

conduit. Since these are essential for safe shutdown and for

alternate shutdown, they were brought to the inspection team's

attention. Exemptions to the Appendix R requirements had

previously been granted by the NRR fire protection reviewers on

the basis of low combustible loading and adequate protection

from a floor based exposure fire. The inspection team's fire

protection specialist reviewed these areas and the findings are

discussed in paragraph 8.

(2) Systems Used for Alternate Shutdown

The EPM analysis and the design of the alternate shutdown system

were reviewed. They were consistent and indicated that the HPCI

system will be used for inventory control, with both the

emergency condensate tanks (ECTs), and the suppression pool used

as the source of coolant. The suppression pool cooling made of

RHR will be used for decay heat removal. All of the support

systems (one train), indicated in paragraph 5.a, will be

required, and the shutdown cooling mode of RHR will be used for

cold shutdown as described in paragraph 5.a.

The instrumentation listed in paragraph 5.a will be available on

the alternate shutdown panels, as well as the necessary controls

for HPCI, RHR, and three ADS valves.

(3) Modifications Required for Alternate Shutdown (New Panels)

The design of the alternate shutdown modifications is in the

final stages of completion, with all parts ordered, but

installation is just beginning. A schedule was presented by the

licensee which showed completion by the end of the next

refueling outage (end of December 1986).

.

. - .

-

_ _ _

. . - _ _

-

.

-

__

.

.

17

There will be three new control panels installed.in the

southeast corner of the reactor building at elevation 903'.

The

three panels, one each for the HPCI, RHR.and ADS system, .will be

housed in a new enclosure. This enclosure (room) will be

accessible in two ways: One from the reactor building

(elevation 903'), and from the outside using the reactor

building roof and a caged ladder.

The panels will be equipped with isolation switches for all of

the equipment controlled to ensure independence from the control

room.

6.

Procedure

a.

Safe Shutdown Procedures

The licensee presently uses symptom-oriented procedures for shutdown

in case of any transient or emergency, including fire. These

procedures do not depend on any particular event or malfunction and

can be used for shutdown in case of fire that does not require

control room evacuation. The procedures reviewed included the

following:

o 5.4.1

General Fire Procedure

o 5.4.2.1

Battery Room Fire

o 5.8

Emergency Operating Procedures (E.0.P.)

o

E.0.P.-C

Operator Precautions

o

E.0.P.-1

Reactor Pressure Control

b.

Possible Core Uncovery Using ADS / Low Pressure Systems for Inventory

Control

Since for the five areas outlined in paragraph 5.a. the licensee

intends to depressurize the vessel by using the ADS system and then

inject coolant via the low pressure systems (core spray or LPCI), the

possibility of core uncovery was reviewed. The licensee presented an

analysis entitled " Report on Core Uncovery Due to Depressurization

Using ADS in conjunction with the Core Spray System" dated July 15,

1985, by EPM. This report indicated that if depressurization (using

3 ADS valves) is begun within 6 minutes after rod injection (with

Wdter level at normal operating level), the water level would not go

below the top of active fuel:

'The procedure E.0.P.-1, hcwever, presently prescribes the use of this

method of shutdown, unless all other methods are unavailable, and the

Wdter level has fallen to the top of active fuel. Therefore, while

the analysis presented was plant speci*ic, it could not be accepted

as complete. The licensee was requested to include in the analysis a

case using top of active fuel as the s N rting point. This will most

probably result in partial core uncover; , and require an exemption

request. The licensee was also asked to expand the analyses to

-

.

.

18

include the use of LPCI and/or core spray.

Pending the licensee's

action this will be considered an unresolved item.

(298/8615-01)

c.

Alternate Shutdown Procedures

The alternate shutdown procedures have not been prepared yet, and

will also be symptom oriented.

They will, however, involve control

room evacuation and the use of the new alternate shutdown panels, and

therefore will be different from, and an addition to the present

E.0.P.'s.

These new procedures should be reviewed and walked down

when available.

The NRC review of the alternate shutdown procedures,

hardware installations, and emergency lighting and communication

equipment required by procedures will be considered an unresolved

item.

(298/8615-02)

'

d.

Repairs

The licensee has proposed post-fire repairs for two systems, which he

has designated as cold shutdown repairs.

The first is a repair to

cabling for the diesel fuel oil transfer pumps for fires in areas

where the cables are located.

The repair consists of replacing the

damaged cable by re-routing a new cable on the outside of all areas

affected.

This repair would be required in 8-16 hours since the day

tanks for the diesels each store enough fuel for 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> at rated

load. The licensee considers this a cold shutdown repair because he

has the ability to reach cold shutdown in 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />.

However, since

the emergency procedures presently in use preclude shutdown in a

manner which would reach cold shutdown in so short a time, this

repair is considered a hot shutdown repair.

The licensee was

requested to review this repair and either change his proposal or ask

for an exemption.

'

The second is a repair to cabling for the battery chargers.

Since

the batteries are rated for only 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> at full load, this is also

,

considered a hot shutdown repair, and the licensee was requested to

review this in the same manner as the diesel fuel pump cable repair.

Pending licensee action the above repairs will be considered an

'

unresolved item.

(298/8615-03)

7.

Protection for Associated Circuits

The Cooper Nuclear Station was inspected for compliance with the following

associated circuit provisions of 10 CFR 50.48, Appendix R:

o

Common Bus Concern

o

Spurious Signals Concern

o

Common Enclosure Concern

1

-

,

is

t

-

}

.

.

19

a.

Common Bus Concern

The common bus associated circuit concern is found in circuits,

either non safety-related or safety-related, where there is a common

power source with shutdown equipment and the power source is not

electrically protected from the circuit of concern.

In order to inspect for this concern at Cooper Nuclear Station, the

time-current curves developed during the licensee's bus coordination

study were reviewed.

The following randomly selected circuits were

reviewed during the audit:

Licensee's Recommended

Circuit

Action to Achieve Coordination

125 V DC Panel DG2

None - Circuit Coordinated

125 V DC Panel AA2

None - Circuit Coordinated

250 V DC SWGR Bus 1B

Replace 600 amp DB25 circuit

breaker with 600 amp FRS fuse

Service Water Pump SWP-1B

None - Circuit Coordinated

RHR Pump RHRP-10

None - Circuit Coordinated

4160 V Bus IF

Change Breaker SS1F Phase Relay

IAC (Relay) instantaneous

setting from 105 to 120

Change Breaker 1FE IFC (Relay)

T.L. setting from 5 to 6 and

.

IAC (Relay) instantaneous

setting from 40 to 50

4160 V Bus 1G

Change Breaker SSIG Phase Relay

IAC 53 (Relay) Tap setting

.

from 5 to 6 and instantaneous

'

setting from 105 to 120

Change Breaker 1GE Phase Relay

IFC (Relay) T.L. setting from

5 to 6, IAC (Relay) T.L. setting

from 4 to 5 and IAC (Relay)

instantaneous setting from 40 to

50

480 V 1F

Change MCC-LX Feeder 1000 amp

DB-50 circuit breaker LSI

(Amptector 1-A) Short Delay

Time setting from .18 to .5

_ .

. . .

.

20

Change MCC-K Feeder 1000 amp

DB-50 circuit breaker LSI

(Amptector 1-A) Short Time

Delay setting from .18 to. 5

120 V Panel DP15-1A

None - Circuit Coordinated

The licensee's bus coordination study was comprehensive and

recommended modifications (recommended modifications had not been

accomplished at the time of the inspection) to achieve coordination

for all circuits analyzed. The bus coordination study

l

recommendations are summarized below:

AC Bus recommended modifications / changes:

o

Four fuses to be replaced with larger fuses,

o

Seven circuit breakers to be replaced with fuses,

Four DB-50 circuit breakers Amptector I-A trip settin'gs to'be

o

changed,

o

Two DB-50 circuit breakers Amptector I-A tripping devices to be

replaced, and

o

Six overcurrent relay settings to be changed.

DC Bus recommended modifications / changes:

l

o

Twenty-two 08-25 circuit breakers to be replaced with fuses,

o

Four 08-50 circuit breakers to be replaced with fuses,

!

o

Two fuses to be replaced with higher amperage fuses, and

l

l

o

One fuse to be replaced with a lower amperage fuse.

f

Licensee action on-the above recommended modifications / changes is

pending.

'

- The licensee has a protective relay setting and testing program,

Maintenance Procedure 7.3.1, which provides for relay testing at 1,

2,-3 and 5 year' intervals.

The licensee has a' procedure, Maintenance Procedure 7.3.2, for

7

l

'

setting'and testing circuit breakers; however, the procedure does not

I

specify the interval for performance.

'

t

..

s

y

p m i-th-

--

g

1---e.s

>&p---

-y

9

.y->.ygd+r

-g

yym-p-gw..g

p.3-.mipe9-,-

one y p - g

ig-yy.,

y-gm.e99--m.gs a t

gey-een

%.e P=w tr ap

a.r---y-

---pew

+fy__

-

.

.

21

b.

Spurious Signals

The spurious signal concern is made up of two items:

o

The false motor, control, and instrument readings such as

occurred at the 1975 Brown's Ferry fire.

These could be caused

by fire initiated grounds, short or open circuits,

o

Spurious operation of safety-related or non safety-related

components that would adversely affect shutdown capability

(e.g., RHR/RCS isolation valves).

(1) Current Transformer Secondaries

Licensee analysis for burned out current transformer secondaries

including fires due to current transformer open circuits is

incomplete.

Licensee representatives stated that the current

transformer secondary analysis will be completed during the

l

ongoing associated circuit analysis.

(2) High/ Low Pressure Interface

Dcring the ongoing associated circuit analysis, 41 components

have been identified as high/ low pressure interface components.

The high/ low pressure interface components and resolution status

are tabulated below:

t

High/ Low Pressure

Interface Component

Resolution Status

-

HPCI-MOV-M014

Pending

-

,

HPCI-M0V-M015

Pending

HPCI-MOV-M016

Pending

MS-A0V-738AV

Pending

MS-A0V-739AV

Pending

MS-A0V-A080A

Pending

MS-A0V-A080B

Pending

MS-A0V-A080C

Pending

MS-A0V-A0800

Pending

,

l

MS-A0V-A086A

Pending

MS-A0V-A086B

Pending

i

l

MS-A0V-A086C

Pending

MS-A0V-A086D

Pending

MS-MOV-M074

Pending

l

MS-M0V-M077

Pending

l

MS-MOV-M078

Pending

l

MS-MOV-M079

Pending

MS-50V-SPV71A

Pending

MS-S0V-SPV71B

Pending

MS-50V-SPV71C

Pending

.

-

- . _ _ _

-

.

--

. - - - -

--

.-

.

-.

.- - ___ _ __

.

'

.-

P

.

22

,

.

'MS-50V-SPV71D

Pending

--

MS-50V-SPV71E

Pending

',MS-50V-SPV71F

Pending

.

,

"

Pending

'MS-50V-SPV71G

.

'

. .

.

-MS-50V-SPV71H

Pending

MS-V-263X-45

Pending

RCIC-MOV-M0121

Pending

'-

RCIC-MOV-M015

Pending

'

RCIC-MOV-M016

Pending

RHR-A0V-PCV70A

Pending

RHR AV0-PCV708

Pending

RHR-MOV-920MV

Pending

RHR-MOV-921MV

Pending

RHR-MOV-M017

Pending

RHR-MOV-M018

Pending

RHR-MOV-M025A

Pending

RHR-MOV-M025B

Pending

RHR-MOV-M0274A

Pending

RHR-MOV-M0274B

Pending

RWCU-MOV-M015

Pending

RWCU-MOV-M018

Pending

(3)

Isolation of Fire Instigated Spurious Signals

Licensee analysis for fire instigated spurious signals is

incomplete.

Licensee representatives stated that circuits that

require isolation for fire instigated spurious signals have been

identified and that resolution is pending.

Proposed methods of

resolution include:

o

Prefire rackout of breakers

o

Rerouting of cables

o

Wrapping or boxing in cables

o

Installing fire breaks on cable trays

o

Installing isolation switches

The following proposed alternate safe shutdown modifications

j

(DC86-21) were reviewed:

Component

Proposed Isolation

PT-83 HPCI-Pump Discharge Pressure

Transfer switch with fuses

!

Indication

PT-89 HPCI-Turbine Steam Inlet

Transfer switch with fuses

Pressure

l

l

t

. .

-,

.

.-

a

23

PT-100 HPCI-Pump Suction Pressure

Transfer switch with fuses

Indication

SC-2792 HPCI-Turbine Speed Indication

Transfer switch

FT-82 HPCI Flow Control and Indication Transfer switch with fuses

FT-1098 RHR Flow Indication B Loop

Transfer switch with fuses

LT-598 Reactor Vessel Level

Transfer switch with fuses

LT-918 Reactor Vessel Level

Transfer switch with fuses

LT-10 Suppression Vessel Level

Transfer switch with fuses

LT-681B Emerg. Cond. Storage Tank 1B

Transfer switch with fuses

Level

Torus Temperature Indication

Dedicated RTD Detectors

Proposed isolation was satisfactory for the circuits reviewed.

c.

Common Enclosure

The common enclosure associated circuit concern is found when

redundant circuits are routed together in a raceway or enclosure and

they are not electrically protected, or fire can destroy both

circuits due to inadequate fire protection means.

Licensee representatives stated that:

o

All circuits are electrically protected by breakers or fuses,

o

Cables for redundant safe shutdown divisions are not routed in

common enclosure.

o

Non-safety related cables routed in common enclosure with safety

related cables are never routed between divisions.

Random cable selection in the field did not identify any cable

routing in common enclosure that constituted a common enclosure

Concern.

d.

Multiple High Impedance Faults

The multiple high impedance fault concern is found in the case where

multiple high impedance faults exist as loads on a safe shutdown

power supply and cause the loss of the safe shutdown supply prior to

clearing the high impedance faults.

.

.

24

Licensee analysis for multiple high impedance faults is incomplete.

Licensee representatives stated that the multiple high impedance

faults analysis will be completed during the ongoing associated

circuit analysis,

e.

Associated Circuit Analysis

The licensee is conducting an associated circuit analysis.

The

analysis is being conducted thoroughly and has identified problems

requiring resolution to achieve compliance with Appendix R

requirements.

The completion of the associated circuit analysis, current

transformer analysis, multiple high impedance faults analysis,

high/ low pressure interface analysis, and outstanding modifications

from the breaker-fuse relay coordination study is considered an

unresolved item.

(298/8615-04)

8.

Fire Protection, Detection, Suppression

The NRC inspector reviewed the exemptions to Appendix R that were granted

by the NRC on September 21, 1983, in the following areas:

o

Service Water Intake Structure

o

Cable Spreading Room

o

Cable Expansion Room

o

Reactor Building, Northeast Corner Room

o

Control Building Basement

o

Auxiliary Relay Room

o

Control Room

o

Fire Area Boundaries - Four Areas

-

Reactor Building 932' Elevation (Critical Switchgear Rooms IF

and 1G)

-

Reactor Building 931' Elevation

-

Reactor Building 903' Elevation (excluding northeast corner)

-

Reactor Building 859' and 881' Elevations (quadrants and tours

area)

The areas above were inspected to ensure that the level of fire

protection, including detection and suppression, was adequate and as

described in the exemptions.

The level of protection was determined to be

adequate with the following exceptions:

o

The auxiliary relay room had only one smoke detector installed.

This

left one beam pocket without detection.

An additional smoke detector

was deemed necessary.

s

.:

25

o-

The installation of a flame impingement shield beneath the Division 2

conduit bank was found to not extend far enough to protect all the

conduits. The NRC inspector felt that some additional level.of

protection under the conduit bank was needed.

Pending the licensee's action, the above two findings are considered'as

one unresolved item.

(298/8615-05)

,

9.

Unresolved Item

~

An unresolved item is a matter about which more 'information is required in

order to detennine whether it is an acceptable item, a violation,' or a

deviation. Five unresolved items are discussed in paragraphs 6.b, 6.c, 6.d,

7.e, and 8 of this report.

10.

Exit Interview

An exit interview was conducted on April 25, 1986, with those Nebraska

Public Power District personnel denoted in paragraph 1 of this report. At

this meeting, the scope of the inspection and the findings were

sumarized.

,