ML20199J200

From kanterella
Jump to navigation Jump to search
Requests Approval of Alternative to ASME Code Requirements Re Liquid Penetrant Testing Requirements of N-518.4 of 1968 ASME Boiler & Pressure Vessel Code for Weld Repairs.Related Info Encl
ML20199J200
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 01/30/1998
From: Sorensen J
NORTHERN STATES POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20199J205 List:
References
NUDOCS 9802050255
Download: ML20199J200 (4)


Text

,

Northern States Power Company Praltle Island Nuclear Generating Plant 1717 Wakonado Dr. East Welch, Minnesota $5089 January 30,1998 10 CFR 50.55a(a)(3)

U S Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos. 50-282 License Nos. DPR-42 50 306 DPR-60 Reauest for Aporoval of Alternative to ASME Code Reauirements Prairie Island Unit 2 shut down on January 24,1997 to repair a small RCS leak. The source of this leakage has been identified as the intermediate canopy seal weld for the part length control rod drive mechanism (CRDM) penetration at location G9 on the reactor vessel head (Attachment 3).

Repair options were evaluated and it was determined that the most appropriate repair was the use of a weld buildup rather than removing the defect and performing a weld repair. Weld buildup was an acceptable repair technique because the canopy seal weld does not provide the structural strength or the pressure boundary for the joint. A fracture mechanics analysis was performed to justify not removing the existing defect.

Even though the canopy seal does not provide structural strength for tha joint, the weld buildup over the canopy seal is considered a repair under the rules of AsME Section XI, IWA-4000 because the welding is performed on pressure retaining components.

The need for NRC review and approval of the fracture mechanics analysis was discussed with the NRC Staff on June 1,1995 and it was determined that no NRC review was required.

Based on N-518.4 of the 1968 ASME Boiler and Pressure Vessel Code, a liquid penetrant examination of the weld buildup is required. However, liquid penetrant examination of the canopy seal weld buildup would be difficult. The canopy seals being repaired aro located in a high radiation area, with radiation fields of approximately 1000 mr/hr Adutionally, access to the canopy seats being repaired is difficult due to the limited clearance between the adjacent control rod drive housings. The separation between the outer rod travel housings is approximately 7.2 inches. This is not adequate clearance to gain complete access to the inner rod travel housings to perform the liquid 9002050255 900130 i

i PDR ADOCK 0500o282 P

PDR

. I

\\

(

a

USNRC NORTHERN STATES POWER COMPANY January 30,1998 PagQ 2 of 4 penetrant examination of the weld repairs. Final weld surface preparation (grinding),

' the liquid penetrant examination and the subsequent cleanup would be difficult and time consuming due to the limited access, and personnel performing these operations would incur substantial radiation exposure.

While the liquid penetrant examiriation specified by N-518.4 would provide indication of surface cracks, the processes used to perform the weld buildup and the visual examination of the welds provide the best measure of the intermediate canopy seal weld buildup acceptability due to the limited accessibility and high radiation fields. The surface to be repaired is examined with an 8x camera during weld surface preparntion.

The weld buildup is deposited using a fully automatic TIG process. All welding parameters are contro!!ed within the qualified range from a remote panel. The weld puddle / deposit is observed via a 8x camera during every phase of the welding. A final visual examination of the weld surface is completed using the same 8x camera. Much of the welding is observed at the contro! panel by an NSP 1 evel ill inspector. In additior the post outage hydrostatic test of the reactor coolant system will include a VT-2 inspection of the intermediate canopy seal weld adaptor and penetration for leakage.

10 CFR Part 50, Section 50.5'

@ ellows the use of alternatives to the ASME Code requirements, when authorizes e Director of the Office of Nuclear Reactor Regulation, if it can be demonstrated that:
1. The proposed alternatives would provide an acceptable level of quality and safety, or
2. Compliance with the specified requirements of this section would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.

In accordance with the provisions of 10 CFR Part 50, Section 50.55a(a)(3), we are proposing the following alternatives to the !! quid penetrant testing requirements of N-518,4 of the 1968 ASME Boller and Pressure Vessel Code for the weld repairs described above:

1. Use of a controlled automatic welding process.
2. Observation of the weld puddle / deposit via a 8x camera during the welding process.
3. A final visual examination of the weld surface using the same 8x camera.
4. Performance of a VT-2 inspection of the canopy seal weld adaptor and penetration for leakage during the post outage hydrostatic test.
5. Authorized Nuclear Inservice Inspector approval of alternative testing and NIS-2 acceptance.

ISI-IST\\SEALREQ3 DOC

USNRC NORTHERN 8TATEQ POWER COMPANY January 30,1998 Page 3 of 4

.. A liquid penetrant examination would provide a more stringent verification of the final weld surface condition and !herefore afford an added measure of the quality and safety of the completed weld bc,Jup. However, the liquid penetrant examiration does not provide a substantial increase in quality and safety above what is provided by the measures (controlled process, observation of weld process using 8x camera, final 8x visual inspection and hydrostatic test inspection) that have been and will be taken in lieu of the liquid penetrant examination.

An analysis was performed by Structural in'egrity Associates to demonstrate that a through-wall flaw could be detected by visual examination which has a flaw size which is sufficiently smaller than the critical flaw size, thus assuring sufficient safety margins.

The analysis demonstrated that, under a variety of conservative assumptions, the critical flaw size predicted for the repair geometry is in all cases of significant length, it is likely that a much smaller flaw could be credibly detected by visual examination under 8x magnification. The analysis results are summarized in Attachment 1.

In order to confirm the detectable flaw size, tests were performed by Welding Services incorporated to evaluate the capabilities of the camera system used in the performance of the weld repair. This testing confirmed that the critical flaw sizes resulting from the Structural Integrity analysis are detectable with margin by the visual inspection technique A summary of the tests performed and the test results are provided as,

in conclusion, the proposed alternatives (automatic weld process, observation of the process using 8x camera, final 8x visual examination and hydrostatic test inspection) to the liquid penetrant requirements of N 518.4 of the 1968 ASME Boiler Code and Pressure Vessel provide an acceptable level of quality and safety for weld repairs to the intermediate canopy seal welds. Furthermore, compliance with the liquid penetrant examination requirements of N-518.4 of the 1968 ASME Boiler and Pressure Vessel Code would result in hardship or unusual difficulty without a compensating incream in the Ic. vel of quality and safety.

We have made no new Nuclear Regulatory Commission commitments in this letter.

Please contact Dale Vincent (612-388-1121) if you have any questions related to this request.

C "Joel P. Sorensen Plant Manager Prairie Island Nuclear Generating Plant (Distribution of copies and attachments listed on page 4)

ISMST\\SEALRE03 DOC

USNRC-NORTHERN STATES POWER COMPANY Janu;ry 30,1998 Page 4 of 4

. c: Regional Administrator - Region 111, NRC Senior Resident inspector, NRC NRR Project Manager, NRC J E Silberg Attachments:

1. Evaluation of Limiting Flaws for Structural Integrity in Canopy Seal Repairs at Prairie Island Nuclear Plants, Calculation Package
2. Summary of Camera Testing
3. Control Rod Locations (Figure B5-2)

ISLISTWEALREQ3 DOC

e ATTACHMENT 1 CALCULATION PACKAGE:

EVALUATION OF LIMITING FLAWS FOR STRUCTURAL INTEGRITY IN CANOPY SEAL REPAIRS AT PRAIRIE ISLAND NUCLEAR PLANT STRUCTURAL INTEGRITY ASSOCIATES,INC

._