If' McGUIRE NUCLEAR STATION MONTHLY OPERATING STATUS REPORT March 1992 1..
Personnel Exposure -
'For the month of March, no individual (s) exceeded 10 percent of their allowable annual radiation dose limit.
2.
The total stati.
liquid release for December has been compared with'the Technical Specifications maximum annual dose commitment and was less than 10 percent of this limit.
The. total station gaseous release for December has been compared with the Technical Specifications. maximum annual-dose commitment and.was less than 10 percent of this list.
J 9505190114 920513 PDR ADOCK 03000370 R.
?'"
^ ^
^
, ;m 7
w h
. ~.,
b..
l;
?UNITISliUTDOWNS. AND' POWER LREDUCTIONS.
DOCKEY NO.
50--370 F
Page L 3 of 2 UNIT. NAME Enwuint; z
.DATE uafInfvz Revision 1 REPORT MONTli March 1992-
. COMPLETED BY n.-c.
s i n n u n.v TELEPHONE _Jiusf-J/J-533W (1)
R(. 2)MET) -
(4)l (6)-
f3 E
llOD T'
A;r OF' LICENSE-.
J N-
- Y:
SL SHUT
. EVENT SYS-O PI
.. DURATION.~
O~
DOWN REPORT TEM COMPONENT ACTION TO CAUSE AND:CORRECTIVC DATE' E
' ilOURS.-
N" R/X:
NO..
CCDE CODE PREVENT RECURRENCE:
-1 92-.3-1-
S 317.77 C-
-~
e RC ;
FUELXX END -OF" CYCLE 7 - REFUELING OUTAGE :
1 2
92-3.' S' 24.00 A.
'FD' VALVEX 1 DAY DELAY DUE TO VALOE FAILURE I
-DELAYING FUEL TRANSFER 3
92-3-15'
-S1 6.23-
'Ai Cli PUMPXX 6 IlOUR DELAY DUE TO AUXILIARY
- FEEDWATER PUMP BEARING. REPAIRS 4
92-3 S 7.00 A:
CA-INSTRU-7 "llOUR DEI AY ' DUE TO REACTOR VESSEL
--INSTRUMENTATION' SYSTEM LEAKAGE S
9 2 - 15.'
F 41.73 A
'CB-PUMPXX 2.S ' DAY DEI AY DUE TO REACTOR COOLANTj j 'i
'i PUi4P BUSSBAR REPAIRS 1-P 92-3-17 S.
B liA TURBIN TURBINE SOAK FbR OVERSPEED TCST
- 6-92-3-18 S
0.80 B
2 IIA TURBIN
' TURBINE OVERSPEED. TRIP TEST 2-P 92-3-18 S
B IA' INSTRU SET REACTOR TRIP SETPOINTS
~(1
'(2) i, (3'
' Forced' Reason :
bethod:
(4)
S Scheduled oA-Equipment Failure (Explain) 1-Manual for Preparation of. Data-Exhibit G - Instructions-B-Maintenance-or test C-Refueling 2-Manual Scram 3 -Automatic Scram
~ Entry Sneets'For Licensee,
D-Regulatory Restrict.
.n Event Report'(LER)
E-Operator Training & License Examination 4-Other (Explain)-
File :(NUREG-0161)
F-Administrative G-Operator Error.(Explain)
(5) 11-Other - (Expla in)
Exhibit I - Same Source i
I E
j
+
,.m UNIT SliUTDOWNS AND POWER REDUCTIONS DOCKE'If NO.
50-370 UNIT NAME ncuujT?ts 2 DATE -' U4/15/9z Page 2 of 2 REPORT MONTH
~ March 1992 COMPLETED BY N.
- c. sIMMUNs TELEPliONE t1u4J-aic-undy Revision 1 f
(1)'
2)
(4)
(5)
I E
HOD T
A OF LICENSE N
Y S
SilUT EVENT SYS-CAUSE AND CORRECTIVE O
P DURATION O
DOWN REPORT TEM COMPONENT ACTION
"]
DATE E
liOURS N
R/X NO.
CODE CODE PREVENT RECURREICE IA INSTRU SET INTERMEDIATE RANGE CHANNEL
{
B 92-3-18 S
SETPOINTS 3
y, Cll llTEXCll "B" STEAM GENERATOR FIAW GAGE 4-P 92-3-19 S
A JA INSTRU POWER ltANGE NUCLEAR INSTRUMENTATION 5-P 92-3-20 5
B CALII3 RATIONS 7
92-3-21 F
10.43 A
3 lill llTEXCil TRIP DUE TO "C" STEAM GENERATOR LEVEL FAILURE 6-P 92-3-22 F
B IIG XXXXXX CIIEMISTRY l
111!
VALVEX "A"
FEEDWATER PUMP RECIRC VALVE
(
A 7-P 92-3-22 F
IA INSTRU NUCLEAR INSTRUMENTATION CALIBRATION 8 -l' 92-3-22 S
B l
(3)
(4)
Method:
Exhibit G - Instructions.
(1)
( 2['
l S Scheduled A-Equih> ment Failure (Explain) 1-Manual for Preparation of Data P Forced teason-2-Manual Scram Entry Sheets For Licensee B-Maintenance or test 3-Automatic Scram Event Report (NUREG-OI61))
(LER l
C-Refueling 4-Other (Explain)
File I
D-Regulatory Restriction i
E-Operator Trqiining & License Examination
..)
F-Administrative Exhibit I - Samae Source G-Operator Errorli-Other (Explain) (Exp, ain) l
,