U-602894, Final Part 21 Rept Re Discrepancies Between GE BWR Reactor Design Requirements Documents & Sys Vendor Manuals.Util Completed Evaluation & Concluded That Issue Is Not Reportable Per 10CFR21 as Reported in 971029 Rept

From kanterella
(Redirected from ML20197B897)
Jump to navigation Jump to search
Final Part 21 Rept Re Discrepancies Between GE BWR Reactor Design Requirements Documents & Sys Vendor Manuals.Util Completed Evaluation & Concluded That Issue Is Not Reportable Per 10CFR21 as Reported in 971029 Rept
ML20197B897
Person / Time
Site: Clinton Constellation icon.png
Issue date: 12/18/1997
From: Jackie Cook
ILLINOIS POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
REF-PT21-97 U-602894, NUDOCS 9712240065
Download: ML20197B897 (2)


Text

..

/*  ?, ( 1

-w 6

  • Ilhnois Power Company _

f.. -

Clinton Power Station -

_,_ P o Box 678

,,. C!inton IL 61727 -

^C Tel 217 035 5623 ~.

Fat 217 935-4632'-

John o. Cook

An m w=a compey -

R Sen.or V;;e President -

g; 4F.140

~ December 1 8 ,: 1 9 9 7-'

Docket No. 50-461 10CFR21.21 Document ControlDesk

-Nuclear Regulatory Commission Washingion, D, C. 20655 -

Subject:

10CFR21 Final Report 21-97-042:

Discrepancies Between General Electric Boiling Wster Reactor Damian Reauirements Documents and System Vendor Manuals

Dear Madam or Sir:

Illinois Power (IP) notified the NkC in 10CFR21 Interim Report 21-97-042 (IP letter U-602855) dated October 7 1997, that an evaluation under 10CFR21 was in -

progress regarding discrepancias between the General Electric (GE) Boiling Water Reactor (BWR) design requirements and system vendor manuals. The evaluation has been completed and IP has concluded that this issue is not reportable under the provisions of10CFR21.

> The interim report stated that on August 21,1997, IP identified a discrepancy between the GE BWR design requiremer ts 22A5604, " Turbine-Generator Control Requirements GE-Nuclear Energy Division," and the field line-up instructions contained in GE vendor manual K2804-0007C, "GEK-64903, Volume III, Steam Turbine-Generator (EHC and TSI Section)." The specific discrepancy identified was a

- difference between the GE BWR Design Requirements document and the system \g

vendor manual for the specified closing rate of the turbine control valves. Condition Report (CR) 1-97-08-183 was initiated to track an investigation of this issue. i g
On August 27,1997, during investigation of CR l-97-08-18'l, IP _ engineers

. determined that conflicts may exist between other GE BWR design requirements i documents and the system vendor manuals. Condition Report (CR) 1-97-08-303 was l

! initiated to track an investigation of this issue. The design document discrepancy issue L was determined to be potentially reportable under the provisions of 10CFR21 on September 2,1997.

& 3CRL j h,,l-9712240065 971218 '

EEEll PDR ADOCK 05000461 Bum

  • {HI ,- ,

S PDR j

- ~--,',,:, . . . = , . - - . ____ _ . ____ ___ _ __ _ - _-

.- ~ - - . . . - -- . . - - - . -... -.- - .

, ; o -;

U402894 7

  • Page 2 The scope of the gemvic issue involved documents supplied by GE under
specification K2801 which denne the rr pirements for interface between GE supplied
equipment and equipment supplied by others. The Architect-Engineer (AE) for Clinton Power Station was t esponsible for identifying specific requirement specifications and including them in purchase specifications for the equipment suppliers.

. IP has concluded that this issue is not reportable under the provisions of 10CFR21, l I

The basis for this conclusion is the review of the AE's program for controlling this process Additionally, the AE's program was previously audited by GE. To provide  :

further confidence of program effectiveness, IP reviewed a sample of GE requirements for safety-related or Technical Specification-related equipment and did not _ identify any failures of vendor supplied implementing drawings to meet the GE design requirements.

The AE's program is considered to have been effective in identifying specific requirement specifications and including them in purchase specifications for the equipment suppliers.

Further, the specific discrepancy between the GE BWR Design Requirements document and the system vendor manual for the specified closing rate of the turbine control valves would have no impact on a safety function and therefore would not create a substantial safety hazard ifit had gone uncorrected.

Additional information about this issue may be obtained by contacting W. L Shurlow, Engineering Projects, at (217) 935-8881, extension 3223.

Sincerely yours,

~

W [M

.G. Cook

. Senior Vice President RSF/krk cc: NRC Clinton Licensing Project Manager NRC Resident Office, V-690

, Regional Administrator, Region III, USNRC Illinois Department of Nuclear Safety INPO Records Center General Electric Sargent & Lundy

. . - _. - - _ _ _ . _ _ , . , , . _ _ __