Informs That Submittals Reviewed & Determined That Plan Provides Suitable Framework for Responding to NRC Request for Self Evaluation of Restart Readiness.Effectiveness of Implementing Plan Will Be Verified Later
ML20196A713
Person / Time
Site: Pilgrim
Issue date: 06/20/1988
From: Mcdonald D
Office of Nuclear Reactor Regulation
To: Bird R
BOSTON EDISON CO.
References
TAC-65870, NUDOCS 8806300090
Download: ML20196A713 (2)


Text

h. l

.. q ' June 20, 1988

)

Docket No. 50-293 l Mr. Ralph G. Bird Senior Vice President - Nuclear Boston Edison Company Pilgrim Nuclear Power Station RFD#1, Rocky Hill Road Plymouth, Massachusetts 02360

Dear Mr. Bird:

SUBJECT:

PILGRIM NUCLEAR POWER STATION R $ TART PLAN  !

Reference:

Tac Nember 65870 i

By letter dated July 30, 1987 and supplemented on October 27, 1987 and '

December 30, 1987 you submitted the Pilgrim Nuclear Power Station Restart Plan for our review. The staff has completed its review of your submittals including the April 14 and May 16, 1988 responses to our March ifs,1988 request for additional information.

We indicated in our May 6, 1988 letter that the NRC staff has concluded that I the Plan provieles a suitable framework for responding to our request for a self evaluation of restart readiness as described in the update of Confirmatory Action Letter (CAL) 86-10 dated August 27, 1986. As stated in the May 6, 1988 letter the effectiveness of implementing the Plan will be verified at a later date.

This completes our action related to the above referenced TAC number.

Sincerely, j original Signed by .

Daniel G. Mcdonald, Senior Project Manager Project Directorate I-3 Division of Reactor Projects l cc: See next page DISTRIBUTION: Docket File, NRC & Local PDRs, PDI-S r/f, SVarga, B8oger,  ;

MRushbrook, DMcDonald,+0GC, EJordan, ACRS (10), RWessman, PGrimes '

0FC :PDI-3 :PD -3 :DIR/P I-3^  :  :  :  :

NAME hook :DM nald:mw:RWessman  :  :  :  : : 4 DATE :06/ 88 :06/10/88 :06/J/88  : .  :  : '  !

\\ 1 0FFICIAL RECORD COPY 8806300090 800620 PDR ADOCK 05000243 p PDR l i

i C- --- _ - , _ _ _ _ _ _ , _ . . - _ . - .~ - ., ,_c . . , _ _

~,.

Mr. Ralph G. Bird Boston Edison Company Pilgrim Nuclear Power Station CC:

Mr. K. L. Highfill Mr. Ralph G. Bird i Station Directer Senior Vice President - Nuclear Pilgrim Nuclear Power Station Boston Edison Company RFD #1 Rocky Hill Road Pilgrim Nuclear Power Station Plymouth, Massachusetts 02360 RFD#1, Rocky Hill Road Plymouth, Massachusetts 02360 Resident Inspector's Office Mr. Richard N. Swanson, Manager U. S. Nuclear Regulatory Comission Nuclear E:igineering Department Post Office Box 867 Boston Edison Company Plymouth, Massachusetts 02360 25 Braintree Hill Park Braintree, Massachusetts 0?l84 Chairman, Board of Selectmen 11 Lincoln Street Ms. Elaine D. Robinson Plymouth, Massachusetts 02360 Nuclear Information Manager Pilgrim Nuclear. Power Station Office of the Commissioner RFD #1, Rocky Hill Road Massachusetts Department of Plymouth, Massachusetts 02360 Environmental Quality Engineering One Winter Street Charles V. Barry Boston, Massachusetts 02108 Secretary of Public Safety Executive Office of Public Safety Office of the Attorney General One Ashburton Place 1 Ashburton Place Boston, Massachusetts 02108 20th Floor Boston, Massachusetts 02108 Mr. Robert M. Hallisey, Director Radiation Control Frogram Massachusetts Depar', ment of Public Health 150 Tremont Street, 2nd Floor Boston, Massachusetts 02111 Regional Administrator, Region I U. S. Nuclear Regulatory Comission 475 Allendale Road King of Prussia, Pennsylvania 19406 Mr. James D. Keyes Regulatory Affairs and Programs Group Leader Boston Edison Company 25 Braintree Hill Park Braintree, Massachusetts 02184 e