ML20195C352

From kanterella
Jump to navigation Jump to search

Responds to 860512 & 15 Requests for Addl Info Re 860320 Application for Amends to Licenses NPF-9 & NPF-17,permitting Use of multi-element Spent Fuel Casks.Summary of Procedure OP/O/A/6550/13 Encl.W/Two Oversize Drawings
ML20195C352
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 05/23/1986
From: Tucker H
DUKE POWER CO.
To: Harold Denton, Youngblood B
Office of Nuclear Reactor Regulation
Shared Package
ML20195C357 List:
References
REF-GTECI-A-36, REF-GTECI-SF, RTR-NUREG-0612, RTR-NUREG-612, TASK-A-36, TASK-OR TAC-61099, TAC-61100, NUDOCS 8605300236
Download: ML20195C352 (7)


Text

1 i

l l

DUKE Pownn Goxn>m I*.O.1,0x '13180 CIIAHLOTTE. N.C. 2H242

!! AL II. Tt:CKER TELEPHONE we e.earoc.,

(704) 373-4!K31 mm. e m.

May 23, 1986 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Cossaission Washington, D.C. 20555 ,

ATIENTION: Mr. B.J. Youngblood, Project Director PWR Project Directorate #4

Subject:

McGuire Nuclear Station Docket Nos. 50-369 and 50-370 TN-8, TN-8L Multielement Spent Fuel Casks License Amendments

Dear Mr. Denton:

My letter of March 20, 1986 submitted proposed license amendments (pursuant to 10 CFR 50.90) to Facility Operating Licenses NPF-9 and NPF-17 for McGuire Nuclear Station Units 1 and 2, respectively. The proposed amendments seek to permit usa of the multielement TN-8-(and TN-8L) spent fuel casks for receipt of irradiated Oconee fuel in addition to the previously authorized NFS-4 (NAC-1) and NLI-1/2' single fuel assembly casks.

In telecons on May 12 and 15, 1986 between Mr. Darl Hood et. al. of your staff and Mr. P.B. Nardoci et. al. (DPC) during which NRC concerns related to the subject amendments were discussed, certain additional information was requested to support NRC staff review of the proposed amendments. This additional information concerning modifications necessary to allow use of the TN-8 and TN-8L casks, procedural changes and personnel training to be performed, compliance with NUREG-0612 Sections 5.1.1 and 5.1.2, and heat loads / decay time limits is provided as follows:

e Modifications required include: 1) enlarging the grating opening in the decontamination pit near elevation 764'-10" to permit use of the larger casks (see Drawing MC-1206-6-A, enclosed), 2) adding grating at the bottom of the decon pit elevated approximately 3", 3) adding permanent lighting in the decon pit near elevation 760' + 0", 4) Fabricate and mount a new spent fuel handling tool / crane hook adapter storage bracket in the transfer canal' area, and 5) Fabricate and mount storage stand for the cask primary lift beam on the south wall of the decontamination pit (see Drawing MC-1207-7-A, enclosed).

These modifications do not affect major structural components. The modifications are relatively simple and necessary to accommodate the additional handling tools and larger envelope of the cask. {*

ff D B605300236 860523 l PDR ADOCK 05000369 001 P PDR f 5 R G,5

, _ . -_ _ _ = _ - - . . .

4 Mr. Harold R. Denten May 23, 1986 Page 2 e Attachment 1 provides a summary of the procedure (OP/0/A/6550/13) used for B&W spent fuel receipt, storage and shipping with an NLI cask; and Attachment-2 provides a summary of the TN-8L unloading procedure for the McGuire Station. In addition, also included as Attachments IA and 2A are copies of the procedures themselves. Comparison of the attachments readily identifies procedural differences for use of the NLI-1/2 and TN-8L casks. It should be noted that the TN-8L unloading procedure is a draf t supplied by the cask vendor - the final version will be written at McGuire and will include appropriate limits and prec,autions (e.g. Technical Specifications and Load Paths) and receive appropriate QA and Station reviews / approvals prior to implementation. A similar procedure will be developed and implemented for the TN-8 cask should any shipments be made

using the TN-8 cask. Other station procedures (e.g. Spent Fuel Ventilation procedures) are unaffected by use of the TN-8/8L casks.

Training with regard to use of the TN-8/8L casks will basically consist of

" hands on" experience through dry runs with the TN-8L cask using the appropriate procedures to be conducted at Oconee and McGuire in July, 1986 (any appropriate additional training will be given prior to any use of the -

~

TN-8 cask). Classroom training with respect to adherence to Technical Specifications, Fuel Handling Operations, etc. is essentially unchanged by use of the TN-8/8L casks.

e A new crane hook adaptor is being purchased. The adaptor is used to move the cask between the platform at elevation 756' 6" and the cask loading

area and return without wetting the crane block or cables. This method of
handling the TN-8 and TN-8L casks is similar to operation with the NLI-1/2 cask. However, a different adaptor is used for the NLI-1/2 cask. The

, crane hook adaptor will be designed, manufactured, tested and maintained in accordance with ANSI N146-1978, " Standard for Special Lifting Devices for Shipping Containers Weighing 10,000 Pounds (4500 kg) or More for

! Nuclear Materials."

In addition, new handling tools are being purchased for use with the TN-8/8L casks (although the fuel assemblies being transported in the casks are the same as those transported in the NLI-1/2 cask, the current handling tools cannot release the grapple in the TN-8/8L casks due to dimensional restrictions in the cask). However, these handling tools are i not subject to the provisions of NUREG-0612.

All other components of the handling system are addressed in Duke's NUREG-0612 submittals and T.M. Novack's letter to H.'B. Tucker of March 12, 1985 and are acceptable for use with the TN-8/8L casks (e.g. the cask weight is within the NUREG-0612 tested capacity of the crane, appropriate load paths are adhered to, etc.).

6 4

- -. , , , . . _ . - , . . . ~ ~ . . - .__-,_.o ,,.~~.,....-,-,_,e--- ,e~..%,- , - . ., , y-, . _ . - - __--,m, ,m.-_. r. - - . - , ... ,, .. , , , _r.,, -

z Mr. Hareld R. Dentan Key 23, 1986 Tage 3 e The TN-8L multielement spent fuel cask has a single assembly decay heat limit of 7.9 kw. This is slightly lower than the 10.6 kw limit for the NLI cask currently being used for shipment of Oconee fuel. The TN-8 cask decay heat limit is 12.0 kw which is slightly higher than the NLI limit.

The existing license allowing for these shipments dictates a minimum cooling time of 270 days which corresponds to approximately 5.7 kw of decay heat. Since this 270 day limit falls well below the ratings for either of the TN casks or the NLI cask, the transition to the larger

  • TN-8/8L casks will have no significant impact on the safety margin.

In addition to the safety margin provided by the 270 day decay limit. 11 should be pointed out that from a heat removal standpoint, the cask certificate of compliance (CoC) limits have ample margin built in already such that they could well serve as safe limits by themselves. As long as these shipments are made within the limits established by the license itself and by the cask certificates then decay heat limits are not a concern.

The table below illustrates the relationship between the cask design >

limits, license limits and actual conditions. Calculations are based on Branch Technical Position APCSB 9-2. This and other data is further illustrated in Figure 1.

Decay Heat Limit Days Cooled Actual Shipments 0-0.3 kw 5-10 years License Limit 5.7 kw 270 days TN-8L CoC Limit 7.9 kw 180 days NLI CoC Limit 10.6 kw 130 days TN-8 CoC Limit 12.0 kw 96 days In summary then, the combined safety margin provided by the extremely low decay heat load for the actual shipments, the license limit, and the cask design limits are not significantly impacted by introducing the larger TN-8 or TN-8L casks into Duke's transportation efforts.

Duke would like to reiterate its request that the proposed amendments receive approval by July 1, 1986 for the reasons outlined in the March 20, 1986 submittal and expanded upon in subsequent discussions with Mr. Hood. Should there be any questions or if additional information is required, please advise.

Very truly yours,

  1. /k w Hal B. Tucker PBN/j gm l

Attachments Enclosures

Mr. Harald R. D;nton May 23, 1986 Page 4 xc: w/o enclosures Dr. J. Nelson Grace, Regional Administrator U.S. Nuclear Regulatory Commission Region II 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323 Mr. Dayne Brown, Chief Radiation Protection Branch Division of Facility Services Department of Human Resources P.O. Box 12200 Raleigh, North Carolina 27605 Mr. W.T. Orders NRC Resident Inspector McGuire Nuclear Station Mr. Darl Hood, Project manager Division of Licensing Office of Nuclear Regulatory Commission Washington, D.C. 20555

FIGURE 1 DAYS kw 30 - 20 27.6 40 19.7 60 15.7 l 13.4 i f 80 96(TN-8) 12.0 100 11.8 25- 130(NLI) 10.6 150 9.1 170 8.3 180(TN-8L) 7.9 190 7.7 210 7.1 20- 230 6.6 250 6.1 270(LICENSE) 5.7 300 5.2 3

- 330 4.8

>- 360 4.4 l

390 4.1 5 15-450 3.6 3 3.3 TN-8 500

>- p/ 550 3.0 4 2.8

  • 600
  • y NLI 650 2.6 750 2.3 4 10 . 1000 1.8 o TN-8L

< g /

LICENSE 5-1000 0 , , ,

600 70C 800 900 200 300 400 500 0 100 DAYS COOLED

ATTACHMENT 1

SUMMARY

OF NLI-1/2 CASK PROCEDURE ENCLOSURE SECTION . DESCRIPTION 4.1 --- Parking trailer in fuel building 1.0 Initial Conditions 2.0 Receive shipping papers; inspect cask and trailer 4.2 --- Upending, accessing, unloading, closing, replacing cask on trailer 1.0 Verify crane inspections, Area Radiation Monitors (EMF's) operable; tool list with current calibrations; verify air and water supplies; verify RWP is issued; verify lift adapters inspected i

2.0 Steps 2.1 to 2.13: . pend the ca'sk and move to decon pit Steps 2.14 to 2.32: fill cask with water and vent to fuel building ventilation duct Steps 2.33 to 2.37: loosen inner head bolts Steps 2.38 to 2.46: transfer cask to upper shelf of decon pit using designated load path (Enclosure 4.5 or 4.6)

Steps 2.47 to 2.59: attach long lift adapter; attached remote actuation system for lift yoke; lower cask to lower platform of cask pit; remove inner closure head while detaching yoke remotely REMOVE AND STORE FUEL ASSEMBLY Steps 2.61 to 2.67: replace inner closure head; reattach life yoke; raise cask to upper shelf of cask pit Steps 2.68 to 2.74: replace the long lift adapter with the short lift adapter Steps 2.75 to 2.78: move cask back to decon pit using designated load path Steps 2.79 to 2.100: cask flush and purge with air Steps 2.101 to 2.112: closing the cask 4.3 --- Return cask to trailer and prepare to ship 1.0 Verify cranes are inspected, lift adapters inspected, and area radiation monitors operable 2.0 Steps 2.1: decontamination Steps 2.2 to 2.12: transfer cask to trailer Step 2.13: final contamination survey Steps 2.14 to 2.17: install personnel barrier; provide shipping papers

Attachment 1 Page 2 ENCLOSURE SECTION DESCRIPTION 4.4 Part 1 Receiving Inspection Part 2 Cask Inspection Part 3 Record fuel assembly I.D. and storage location Part 4 Outer Closure Head Inspection Part 5 Record torque wrench I.D.'s and calibration dates 4.5 --- Travel path Unit 1 4.6 --- Travel path Unit 2 4.7- --- Authorization from reactor engineer to receive and store spent fuel 4.8 ---

Identification of valves 4.9 --- Cross-sectional view of cask 4.10 ---

Torqueing sequence for inner and outer closure heads 4.11 A Document daily visual inspection of short lift adapter B Document daily visual inspection of long life adapter C Document daily visual inspection of lift yoke i

I I

l i

k _.