Safety Evaluation Re Revised Commitments Concerning Plant Operation.Delay in Satisfying Commitments Acceptable
ML20155F167
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 04/15/1986
From:
Office of Nuclear Reactor Regulation
To:
Shared Package
ML20155F164 List:
References
NUDOCS 8604210382
Download: ML20155F167 (2)


Text

ri L

UNITED STATES NUCLEAR REGULATOFtY COMMISSION y

g 5

W ASHINGTON,0. C. 20665 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATING TO REVISED COMMITMENTS BY PUBLIC SERVICE COMPANY OF COLORADO-FORT ST. VRAIN NUCLEAR GENERATING STATION DOCKET NO. 50-267

1.0 INTRODUCTION

By the letter dated December 27, 1985, (P-85485) the Public Service Company of Colorado (PSC) requested that certain comitments they had made to provide information to the NRC be revited.

Some commitments had originally been made on the basis that plant operation would resume in the summer of 1985. However, continued difficalties in demonstrating Fort St.

Vrain's (FSV) compliance with 10 CFR 50.49 resulted in only very limited, low-power operation during 1985. Currently, the plant is still restricted to operation at up to 35 percent of full pewer. Hence, the staff has reviewed these comitments and provided its evaluation below.

2.0' EVALUATION Item A - PSC has requested a revision to its commitment to provide control rod drive mechanism (CRDM) temperature data. The staff agrees that this delay is acceptable, since high-power operation is needed for the CRDM temperatures to rise to high levels. However, PSC is requested to provide a summary report with temperature data for their latest experience for up-to-35 percent power operation.

Item B - PSC has requested a delay for its comitment to evaluate the effectiveness of certain moisture ingress reduction modifications. The staff agrees that this delay is acceptable, since the evaluation requires extensive operational data. However, PSC is requested to provide a sumary report with the helium flow data for each CRDM penetration for their recent up-to-35 percent power operation.

Item C - PSC has requested a delay in its comitment to provide back-EMF data on the CRDMs. The staff agrees that this delay is acceptable, since the CRDMs should have less tendency to behave abnormally at low temperatures. However, PSC is requested to report initial accelerations of the CRDMs from surveillance testing for up-to-35 percent power opera tion, g42 og $

27 P.

-g Item D - PSC has requested a delay in its commitment to provide back-EMF data on control rods that failed in January 1985. The staff agrees that this delay is acceptable, since the CRDMs have been completely refurbished.

Item E,- PSC has requested a delay in its commitment to complete modif' cations of certain masonry block walls. The staff agrees with PSC that these modifications may be delayed until spent fuel is removed from adjacent storage wells.

Item F - PSC has requested a delay in its commitments to ship fuel test element FTE-2. The staff finds this minor delay acceptable.

Item 1 - PSC has requested to defer its commitment to provide an improved CRDM surveillance program. The staff agrees with PSC that the improved CRDM surveillance program should be deferred until sufficient operational experience is accumulated. However, PSC should provide a sumary report with the surveillance data requested in Items A, B, and C above.

Items 2 through 5 - The NRC concurs with PSC that these items are complete.

{

3.0 CONCLUSION

The staff concludes that the delays in satisfaction of its commitments, as discussed above, are acceptable. However, PSC should continue to make every effort to assure that these comitments are met in a timely manner.

Principal Contributor: Ker.neth Heitner l

Dated: April 15, 1986 1